Ohio.gov State Agencies  |  Online Services
Skip Ribbon Commands
Skip to main content
Sign In
I-75 Widening and reconstruction project
Interstate 75 in Hancock County from the area south of Harrison Street/County Road 144, which is just south of the state Route 15/U.S. Route 68 interchange, to the County Road 99 interchange in Findlay will be under construction beginning spring of 2017. The purpose of the project is to improve the safety and efficiency of the corridor and increase its capacity.
 
The project will add one travel lane in both the northbound and southbound direction along I-75 within the project area.
 
 
The interchanges at U.S. 68/SR 15 and Lima Avenue will also be reconstructed as part of the project. Beaver Construction, Canton, will serve as the general contractor for the project. The anticipated completion is May 2020.
 
Please see project information and construction updates below.
​​
 

 Social Media

 
ODOT- D3 on FacebookODOT- D3 on Twitter  
 

 Project Updates

 

 

Nov. 10, 2017 - Traffic switch means lane, exit closures beginning Tuesday

Oct. 19, 2017 - Harrison Street bridge deck pour to close ramp

Oct. 6, 2017 - I-75 southbound entrance, exit ramps at U.S. 224 to close Oct. 10

September 19, 2017 - Beam setting to close I-75 southbound lane on October 2

September 1, 2017 - Closures at state Route 12 interchange, bridge beam setting upcoming

August 11, 2017 - Additional lane restrictions scheduled for next week​​

July 25, 2017 - I-75 northbound at Sandusky Street reduced to one lane for pothole repair

July 11, 2017 - Ramp from U.S. 68/SR15 to I-75 southbound to close Thursday until Saturday

June 23, 2017 - I-75 northbound ramp to U.S. 68/SR15 now closed, shift in traffic scheduled next week

June 15, 2017 - Ramp scheduled to close Monday

June 9, 2017 - I-75 northbound ramp to U.S. 68/15 to close June 19

May 26, 2017 - Barrier wall going up northbound following holiday

May 18, 2017 - Lane shifts scheduled for early next week

May 5, 2017 - Weather delays lane shifts on I-75

May 1, 2017 - Daytime operations to increase on I-75 in coming weeks

April 21, 2017 - Work zone expands on I-75, lane shifts upcoming

April 14, 2017 - Night work continues, all ramps remain open

April 7, 2017 - Night work continues on I-75, lane shifts upcoming

March 24, 2017 - Night work on I-75 in Findlay to begin Sunday

March 17, 2017 - First work to impact I-75 traffic begins next week

March 8, 2017 - ODOT to hold public meeting regarding I-75 construction

February 9, 2017 - Beaver Excavating, Canton, apparent low bidder for Hancock I-75

 
 
 
 
 

 Lima Avenue Roundabouts

 

The proposed project will have roundabouts at the Lima Avenue interchange.

The website of the Mid Ohio Regional Planning Commission (MORPC) has some general information and information on the benefits of roundabouts, as well as how to drive in roundabouts. Additional information about roundabouts is available on the Traffic Studies page of ODOT District 1.

 

 Live Web Cam on I-75 and U.S. 224, Findlay

 

Loading...
 

 Picture Library Slideshow Web Part

 

Previous Image Pause Next Image
 

 Contact Information

 

 

Rob White, construction project engineer, 419-999-6957; robert.white@dot.ohio.gov 

Eric Scheckelhoff, design project manager; 419-999-6879; eric.scheckelhoff@dot.ohio.gov

ODOT District 1 public information office; 419-999-6803; d01.PIO@dot.ohio.gov

 
 
 

 Project Facts