IMPLEMENTATION OF WARRANTED ITEMS
IN STATE OF OHIO HIGHWAY
CONSTRUCTION PROJECTS
EXECUTIVE SUMMARY
In response to House Bill 163, effective July 1, 1999, a set of warranty contract documents have been developed for implementation in highway construction projects. These documents also meet constraints of federal rules for federally funded highway projects. The contract documents were developed by teams of Ohio Department of Transportation (ODOT), Federal Highway Administration (FHWA) and affected industry personnel. Included in the development was a review of warranty practice for highways around the country by interviewing all 50 states Departments of Transportation (DOTs). Of course, most said, "good luck and let us know how you make out".
The implementation of warranties in a low bid contracting environment presents many potential benefits and challenges. Many are obvious and many are not. The most important obvious benefit to be achieved, if properly specified, is better product performance which means better use of taxpayer money and less impact on highway users due to closures for repairs. A second obvious benefit is the ability for industry to use it's knowledge more productively. Primarily this means an attitudinal shift from 'getting in and getting out' of a project to getting in, getting out and doing it the best we know how.
Some challenges associated with implementation of warranties can be substantial.
For industry, the ability of any company to carry substantial bonding on multiple items on multiple projects for up to 7 years per bond is in question. As well, smaller companies will have a very difficult, if not impossible, time obtaining any bonding, thus eliminating them from warranty contracts. This is significant to Ohio industry when little correlation exists between company size and work quality. Also a challenge for industry are the unknowns associated with being evaluated on performance. Contractors haven't had to be measured for performance many years into the future before and therefore have limited knowledge of what to expect is some cases.
For the bonding companies much reservation exists. While most concede bonds are obtainable in today's growing market there are tremendous unknowns in the quick implementation of warranties in highway projects making it very difficult for bonding companies to determine their risks associated with selling bonding. As well, when the market turns downward what impact will this have on the ability or willingness to bond or on buying bonds?
For ODOT the most significant challenge is in the development of meaningful contract documents that will allow the industry flexibility in construction practice while not giving up standards which exist to ensure desired product quality. In a low bid contracting environment, should these standards not be maintained or improved, quality will decrease.
With the above in mind ODOT and industry have worked diligently these past months to develop a process to implement the legislated warranty requirements. The warranty contract documents are currently being selectively applied to highway projects to meet the bill requirements for fiscal year 2000. This process will progress with project sales to July 1, 2000. Following this a report will be written conveying impacts, costs, and expected success of the warranted projects. With this limited experience adjustments to contract documents will be made for meeting the final requirement of a warranty on all controlled access, multilane pavements in 2001 as well as application of other warranted items in ODOT contracts. ODOT sees at this point no major obstacles to successful implementation of warranties.
TABLE OF CONTENTS
Page
Executive Summary
Introduction and Background 1
National State of Practice
Opportunities and Challenges
Development and Implementation
Tables
Table 1 Warranty items, Periods & Criteria
Table 2 Warranted and performance items list/status
Appendices
Appendix A Warranty Requirements, Ohio H. B. 163, 7/1/99
Appendix B State DOT Contacts
Appendix C Industry Comments
INTRODUCTION and BACKGROUND
As required in House Bill 163 passed by the Ohio House of Representatives, this report is written to convey plans for implementation of warranty provisions of the bill in ODOT contracts.
The process to achieve implementation takes into account the history and use of warranties around the country as well as in Ohio.
Discussions in the late winter of 1999 between State Representatives, ODOT administration and the contracting industry resulted in the drafting of what would become warranty provisions in House Bill 163. The bill was sponsored by Representative Core in the 123rd General Assembly and became effective July 1, 1999. The warranty provisions are in a temporary law section and a permanent law section. The warranty sections of the bill are in Appendix A.
The temporary law section requires this implementation report which shall contain the number and type of projects meeting the permanent law requirements. Finally, a separate report of implementation and analysis is due by December 31, 2000.
The permanent law section sets forth the volume of warranty projects and minimum warranty periods, depending on the items. Two categories for volume are used; capital construction projects and capital construction program. The first requires one-fifth or 20% of projects which simply means all construction project contracts (Federal or State). The second requires one-tenth or 10% of the ODOT program value in dollars.
As well, the permanent law section sets forth the minimum warranty period for specific warranty items. Newly constructed pavement (asphalt or concrete) shall have at least a seven year warranty. Rehabilitated pavement shall have five years minimum. Other items for warranty are up to the discretion of the director beyond those listed for a two year warranty.
Some minor language concerns do with the legislation. One is with the suggested items for a two year warranty. In retrospect a couple of these items are not practical candidates for warranty while other items may be good to add to the list. Also, some definition could be added for preventative maintenance as some disagreement over the intent exists between industry and ODOT. These minor concerns will be pursued thru recommendation at a later date.
The entire bill can be located on the web at: http://www.legislature.state.oh.us/bills.cfm?ID=123_HB_163
The idea for warranties in highway construction has been around thru the 1990s. Warranties for highway construction have been used in Europe for many years. Although the contracting environment in Europe is quite different from the United States many of the benefits of warranties are still desirable. Should the current limitations of contracting practice in the U.S. not be an obstacle those benefits will be realized. To allow for a look at warranties the Federal Highway Administration (FHWA) in 1995 approved a means for states to use warranties in highway projects with federal funding. The FHWA rule stated that warranty provisions must be for a specific construction product or feature, routine maintenance items are not eligible, and warranties are prohibited for items not within the control of contractors.
ODOT has some experience with warranty development in the US. In 1992 ODOT participated in the development of an early FHWA warranty contract document for a specific type of pavement treatment. In 1996 ODOT, as a result of an ODOT quality initiative, began development of an asphalt pavement warranty for use on pilot projects. Utilized at that time for some guidance were contract documents developed in Wisconsin and Indiana. In 1997 three projects were sold using the new Ohio warranty specification for asphalt. In 1998 one additional project was sold with the same specification.
The lessons learned from these early experiences have been applied to new contract documents for implementation of warranties.
NATIONAL STATE OF PRACTICE
Beyond trial warranty projects constructed around the country in the 1990's little has been accomplished nationwide to move warranties forward in order to determine their full practical impacts on quality levels and contracting practice. Appendix B shows the existing practice for warranties for all fifty states as of this year based on the DOT representatives we conversed with. All projects encountered have warranted only one specific construction feature. The warranty duration ranged from one year to five years. Construction on most projects was completed between 1992 and 1997. Most projects have federal aid funding and are constructed on high traffic volume, interstate highways. Note that while there were constructed projects, particularly in states such as Wisconsin and Michigan, all, with the exception of Michigan for specific items, are in a trial phase only and are moving very cautiously.
Copies of those states' contract documents for trial projects were obtained and reviewed for innovative techniques and potential application. Not surprisingly, identical implementation challenges existed with all the states reviewed as did with Ohio. In the final analysis ODOT, industry and suppliers had to sort thru all the major issues of warranty contract document development. The possible outcomes of poor warranty contract document development are significant. Should the warranty contract document be too restrictive to construction companies a heavy cost to the organization might be unduly incurred. Should the contract documents be too loose contract bidding pressures will, in time, produce quality in some cases inferior to current quality levels.
In summary, the use of warranties in state contracts for highway construction is a new and innovative practice to all and careful consideration at all phases is necessary.
OPPORTUNITIES AND CHALLENGES
Discussion of advantages and disadvantages of warranties for highway contracting have taken place in many forms in the past ten years. Following are those believed most pertinent to the discussion for Ohio. They are described as opportunities and challenges as this best describes the situation for industry and ODOT.Opportunities
DEVELOPMENT and IMPLEMENTATION
Implementing warranties for any product for highway construction involves pulling all of the resources and knowledge of an agency together for the best chance of success and minimizing risk. However, the contract documents cannot be successfully developed and contracts cannot be sold and successfully applied without full input from industry, suppliers and surety companies.
Contract Document Development
To reach the goal of implementable contract documents for warranty products used in highway construction each warrantable item must be addressed individually considering all associated risks and goals. As such, ODOT undertook meeting or exceeding the requirements of the legislation by forming teams of individual experts from within ODOT and from industry. These work groups then somewhat independently undertook the task of meeting over a several month period to arrive at acceptable warranty criteria for each warranted highway construction item. It is estimated that to date nearly 50 separate planning meetings and over 225 individuals from ODOT, industry and suppliers have met to address the development of these individual warranty items. As well, common contract language for warranty methods and processes were developed that could be applied to most warranty items.
Table 1 shows the developed warranty items with criteria and warranty periods. Table 2 gives the items and current status of development.
Two items are not in Table 1 that were required in the legislation. These are raised pavement markers and guardrail. Raised pavement markers are removed every few years for reflector replacement. A poor installation warranty method already exists thru a different contract procedure. Guardrail is not a good warranty candidate. The tests for quality are more efficiently performed in a lab as a means of pre-qualification than in the field. Since installation of guardrail is a major safety issue the installation must be checked prior to project completion. ODOT has never experienced a good installation go bad later.
Table 1
Warranty Items, Periods & Criteria
Asphalt: (5 and 7 year, working on probable 3 year; different applications) 1) Supp Spec 880 approved, for structurally designed pavements Concrete: 1) Supp Spec 884 for concrete pavement partially approved, final meeting on several issues Aug 17th. (7 year) Bridge Painting: Supp Spec 885 approved (5 year) Microsurfacing: Supp Spec 881 approved (3 year) Chip Seal: Supp Spec 882 approved (3 year) Hot in Place Recycling: Supp Spec 886, Final draft out for comments. Approval September (3 year) Crack Seal, Saw and Seal: Final drafts being sent to industry for comments 8/23. Approval September (2 year) Pavement markings: Supp Spec 887 Approval September (5, 3 or 1 year depending on type specified) Raised Pavement Markers: Use delayed acceptance for improvement in installation, in use. (No warranty period, delayed acceptance) Seeding and Mulching: Various approaches explored , Performance reviewed and contractor recalled within 1 year. Signal lighting: 1) A failure rate has been established to maintain supplier qualification for bidding purposes. Already included in 1998 bid. Lighting: A 2 part spec is developed to apply supplier warranty on the lighting and a contractor guarantee on
workmanship to existing lighting standards. Expected October (Performance history for being on bid
list) Pipe Installation: A performance specification. Trial projects will be conducted for evaluation of new process.
(Performance review as part of contract) Spraying: Contract performance % or respray Reflective Sign Sheeting: Prequalification based on 1 year exposure testing, approved in 1998 No work to date: polymer expansion joints, landscape/trees Implementation into ODOT Projects Ensuring the right projects are selected for a warranty item and that they are properly tracked for
future data collection and reporting will be fully in the hands of ODOT districts. The natural
tendency of a designer applying warranty items to projects would be to see a previous problem
on an old project and thus want to apply a warranty to alleviate that problem. This approach
could not be more wrong, however. This approach will lead to much contention and raise the
potential of litigation which in turn could hamper implementation of warranties in general. The proper application of warranties starts with understanding the type and extent of existing
conditions thus allowing an analysis as to whether or not a particular warranty item can be
applied. Poor existing conditions make for a poor application of warranties. The better
approach is to select those projects with uniform and average to good existing conditions that can
be readily upgraded with a warranty item. This gives contractors a better chance at accurately
bidding (with all his associated risks) and thus better assurance of success. Of course, new
projects are the best situation for application of warranty. The importance of this cannot be
overstated. ODOT is, in essence, warranting the existing conditions upon which we are asking a
contractor to place and warrant an item. ODOTs Preventive Maintenance program that is in
development would be one tool to give good guidance in appropriate use of warranties.
However, application of warranties should not be limited to this. With proper analysis warranties
can be successfully applied to pavements with conditions less than those called for in preventive
maintenance. To assist the district in this important task a guide document will be created giving application
advice for the various warranty items. To also assist in uniform and well thought out application
of warranty items each district has selected a warranty coordinator. This person has
responsibility for communication, selection and application of warranted items. This person will
as well provide all information on warranty items applied to projects to central office for proper
tracking of warranty items over time. This will assist with decisions to be made regarding the
future content of warranty contract documents and application of those contract documents. As
well, this information is essential for providing a report to the legislature in December of 2000 as
required in the legislation. The targets given to the district warranty coordinators for this first year implementation of
warranty items are the same as given in the legislation. That is, one-fifth or 20% of all
construction project contracts (Federal or State funds) and one-tenth or 10% of ODOT program
value in dollars. However, for targets each district's program value in dollars and number of
projects are used. In some cases a district may not have the right number of pavement projects to
meet the 10% criteria but this can be made up by added work in other districts. As required in the legislation the impact of warranties on bids and initial work quality will be
recorded and reported in the December 2000 report. As well, a couple selected pavement
projects in each district will be reviewed annually regardless of pavement condition. This is for
the purpose of taking the opportunity to learn as much as possible about the progress of these
projects as they age. This may prove important in future decisions on content of material and
construction requirements. Finally, a review of surety company and industry experiences and outlook will be conducted and
included in the final report. ODOT is well on the way to successful implementation of warranties to meet the requirements of
HB 163 and sees at this point no major impediment to accomplishing this.
APPENDIX A
Legislation Pertaining to Warranties http://www.legislature.state.oh.us/bills.cfm?ID=123_HB_163 Permanent Law Section Sec. 5525.25. (A) IN MAKING CONTRACTS, THE DIRECTOR OF TRANSPORTATION SHALL COMPLY WITH
THE FOLLOWING REQUIREMENTS FOR EACH FISCAL YEAR: (2) AT LEAST ONE-TENTH OF THE DEPARTMENT'S CAPITAL CONSTRUCTION PROGRAM
SHALL BE BID REQUIRING A PAVEMENT WARRANTY AS SPECIFIED IN THE BIDDING
DOCUMENTS AND IN DIVISION (B) OF THIS SECTION. (B) A WARRANTY PERIOD UNDER THIS SECTION SHALL BE: (2) NOT LESS THAN FIVE YEARS, IN THE CASE OF PAVEMENT RESURFACING AND
REHABILITATION; (3) NOT LESS THAN TWO YEARS, IN THE CASE OF PAVEMENT PREVENTATIVE
MAINTENANCE, BRIDGE PAINTING, PAVEMENT MARKINGS, RAISED PAVEMENT
MARKERS, GUARDRAIL, AND OTHER PROJECT ITEMS AS DETERMINED BY THE DIRECTOR. (C) THIS SECTION DOES NOT APPLY TO CONTRACTS THE DIRECTOR MAKES ON BEHALF
OF A POLITICAL SUBDIVISION. Temporary Law Section Section 11. (A) Not later than 90 days after the effective date of section 5525.25 of the Revised Code, the
Director of Transportation shall report to the Controlling Board on the Department of Transportation's
comprehensive implementation plan for warranties. The report shall include the following: (1) The number and type of projects to be bid meeting the requirements of divisions (A) and (B) of that
section; (2) An investigation of alternative warranty contracting options, including incentives, different bidding
methods, and implementation of new technologies, construction techniques, and materials to prolong
pavement life considering such factors as density, smoothness, and segregation; (3) Development of a surface warranty for all pavement projects on interstate highways and multi-lane,
fully controlled-access highways under jurisdiction of the director. The surface warranty shall warrant
only against common pavement distresses, including, but not limited to, delamination, raveling, and
rutting. The implementation plan must include a schedule of introduction of the surface warranty into the
department's annual construction program so that all pavement projects let by the department require the
warranty not later than June 30, 2001. (B) Not later than December 31, 2000, the director shall report to the General Assembly the
department's findings on the use of warranties, including comparisons of cost, techniques and quality of
warranted and non-warranted items, and recommendations for further use of warranties. APPENDIX B States Usage of Warranties (as of 8/99)
Item
Spec #
Period
Application
Criteria Asphalt
SS 880
5 / 7 years
Designed rehabilitated/new pavement 3
inches or greater overlay thickness
Cracking-500ft/.25 inch, disintegrated areas-none, flushing-125SF,
previous patching-300SF, rutting-.25in 5yr, .38in 7yr Asphalt??
SS 890
3 years
Other overlays on multilane, divided, trial
Disintegrated areas-none, previous patching-300SF, rutting-1yr Concrete
SS 884
7 years
Designed pavement structure
Cracking-see SS 884, disintegrated areas-1SF, faulting-3/16in, joint
seal-none Deck Overlay
SS 892
2 years
First overlay only
Popout-none, Delamination-none New Deck
SS 893
Bridge Paint
SS 885
5 years
Any place old spec used
Visible rust, blisters, peeling, scaling, slivers, mis-applied over
debris etc, incomplete coating, coating damage by contractor Microsurfacing
SS 881
3 years
For average to good existing conditions
Bleed/flush-300SF, loss-120SF, raveling-300SF, rutting-.25in Chip Seal
SS 882
3 years
Same
Patterns->40%, bleed/flush->5%, loss>10%/>20% Hot Recycling
SS 886
3 years
Same and good structure
Disintegrated-none, flush-125SF, previous patch-300SF, rut-.25in Crack Seal
SS 825/925
2 years
For average to good existing conditions
Debond->1% linear in 10 joints, or any > 2 FT Saw & Seal
SS 889
2 years
As part of rehab overlay
Missed joint-none, same as above Pavmnt Marking
SS 887
1,3,5 years
Depends on marking type
reflectivity, color fade, material loss Landscape??
Table 2 Status list of warranty/ performance items - as of Sept 10, 1999
2) Have had two industry meetings for a specification where we have no design (interstate/multilane and trial 2 lane projects), expected late Sept
2) Bridge deck overlay spec in development, expected approval October
3) New bridge deck spec expected October
2) Suggested add language for next bid to include district data collection method (Performance only for being on bid list)
(1) AT LEAST ONE-FIFTH OF THE DEPARTMENT OF TRANSPORTATION'S CAPITAL
CONSTRUCTION PROJECTS SHALL BE BID REQUIRING A WARRANTY AS SPECIFIED IN
THE BIDDING DOCUMENTS AND IN DIVISION (B) OF THIS SECTION.
(1) NOT LESS THAN SEVEN YEARS, FOR PAVEMENT IN THE CASE OF NEW CONSTRUCTION;
State
Personnel
Position
Phone
Note
Alabama
Pete Anderson
Construction Eng.
334 242 6208
NONE Alaska
Gary Hogins
Chief, Design & Construction
907 465 2985
NONE Arizona
George Way
Materials Engineer
602 255 7286
NONE
Leroy Brady
Road Side Development
602 712 7357
Warranty on Plant Establishment Arkansas
David Henning
Specification Engineer
501 569 2251
NONE California
Ray Seto
916 653 5507
NONE Colorado
Larry Brinch
Construction Specs.
303 757 9474
2 Pavement jobs Connecticut
Charles S. Barone
Intermodel Programming & Policy Planning
860 594 2051
Paint Delaware
Jim Pappus
Materials Engineer
302 760 2385
NONE Florida
Ken Luderalbert
Inovative Contracts
850 414 4382
NONE Georgia
Wouter Gulden
State Materials & Research Engineer
404 363 7512
NONE Hawaii
Dennis Santo
Material & Research Engineer
808 832 3403
NONE Idaho
Cindy
Construction
208 334 8426
NONE Illinois
Eric E. Harm
Bureau Chief of Material & Physical Research
217 782 7202
New legislation for pilot program Indiana
David Andrewski
Materials Eng.
317 232 5280 Ext.212
5 Pavement jobs Iowa
Tom Reis
Spec Division Director
515 239 1566
NONE Kansas
Rod Mottny
Material & Research
785 296 2231
NONE Kentucky
Jim Stone
Div. of Materials
502 564 3160
NONE Louisiana
Doug Hood
Research Engineer
225 929 9131
NONE Maine
Ken Swenny
Construction
207 287 2171
2 Pavement jobs Maryland
Samuel R. Miller Jr.
Deputy Chief Engineer
410 321 3100
Bridge painting Massachusetts
Clement Fung
Material & Research Engineer
617 526 8686
NONE Michigan
Judy Ruszkowski
Engineer of Specification
517 322 5669
12 warranty jobs
John LaVoy
Concrete Staff Engineer
517 335 2244
Dave Smiley
Materials Engineer
517 322 1766
Steve Bower
Pavement Design Engineer
517 373 0551
Mike Frankhouse
Bituminous Engineer
517 322 5672
Minnesota
Dave Johnson
651 282 2270
NONE Mississippi
Rich Shefield
Material Section
601 944 9132
NONE Missouri
Tom Keith
Material Section
573 751 3706
3 asphalt rubber jobs in early '90's Montana
Bob Passow
Construction
406 444 6009
NONE
Jim Stevenson
Maintenance Division
Paint striping Nebraska
Eldon D. Orth
Engineer, Materials & Tests Division
402 479 4750
NONE
Eldon Orth
Engineer, Material & Testing Division
402 479 4750
NONE Nevada
Roger
Construction
702 888 7460
1 crumb rubber job New Hampshire
Gleen Roberts
Research Engineer
603 271 3151
NONE New Jersey
Frank Palise
Construction
609 530 6363
NONE New Mexico
Max Valerio
Construction
505 827 9862
1 job letting now New York
Zoab Zavery
Material Bureau
518 457 3240
1 Pavement job North Carolina
Steve DeWitt
Construction Engineer
919 733 2210
NONE North Dakota
Ron Horner
Material & Research Engineer
701 328 6904
NONE Ohio
David Powers
Asphalt Engineer
614 275 1387
Many very soon Oklahoma
no name
Material Section
405 521 2677
NONE Oregon
Jeff Gouer
503 986 3123
NONE Pennsylvania
Ed Fuhrer
New Contracts
717 787 7034
NONE Rhode Island
J. Michael Bennett
Highway Engineer
401 222 2023
NONE South Carolina
Richard Stewart
Research & Material Engineer
803 737 6681
NONE South Dakota
Larry Weiss
Research
605 773 4423
NONE Tennessee
Floyd Pettty
Material Engineer
615 350 2414
NONE Texas
Thomas Bahuslav
Construction Engineer
512 416 2500
NONE Utah
Gerald Barrett
Engineer of Materials
801 965 4328
NONE Vermont
Robert F. Cauley
Material & Research Engineer
802 828 2561
NONE Virginia
Norma Gilbert
Construction
Wilford King
Construction
804 786 2859
NONE Washington
Rudy Malfabon
State Construction Eng.
360 705 7821
NONE West Virginia
Randy Epperly
Engineer of Development
304 558 6266
Plastic Pavement Markers Wisconsin
Rafig Bawany
Specification Engineer
608 266 3902
Over 10 jobs Asphalt only
John Volker
608 246 7930
Call with questions Wyoming
Tin Babbitt
Materials
307 777 4476
NONE