SS 878 Inspection and Compaction Testing of Unbound Materials

1. Specification:

Supplemental Specification 878

CMS 203, 204, 205, 206, 304, 307, 411, 503, 603

2. Materials:

Follow material requirements for the CMS items referenced above

3. Sampling and/or Inspection Requirements:

Perform contractor verification testing as described in 878.05. When results do not compare favorably stop work. While initial verification is required in 878.05, the specification does not limit that verification testing can be performed randomly at any time during the project.

If Quality Assurance testing (878.09) shows more than one lot failure in five re-perform verification testing conforming to 878.05

4. Method of Tests:

MOP Supplement 1015