505 Pile Driving Equipment Mobilization

Basis of Payment (505.02)

Documentation Requirements – 505 Pile Driving Equipment Mobilization

 

Basis of Payment (505.02)

Payment is not to be made when the equipment arrives on site, but once the first service pile is installed and accepted. 

 

Documentation Requirements - 505 Pile Driving Equipment Mobilization

1.        Document equipment arrival and add to diary for payment.