616 Dust Control

 

Documentation Requirements - 616 Dust Control

The minimum documentation and critical inspection requirements for Item 613 includes recording the following inspection points in the project daily reports.  Specifications or other requirements waived by the Project Engineer should also be noted in the daily reports.

1.        Measure or weigh water truck capacity to determine the water volume per load 

2.        The units of measurement can be converted using the following conversions: 1 ft3 = 7.48    gal.; 1 lb. water = 0.12 gal.

3.        Record the bag count or weigh bills for calcium chloride when used.