ITEM 254PAVEMENT PLANING

254.01Description

254.02Equipment

254.03Planing

254.04Surface Patching

254.05Surface Tolerances

254.06Method of Measurement

254.07Basis of Payment

 

254.01Description.This work consists of planing the existing asphalt concreteand disposing of the cuttings, and, if specified in the Contract, patching the planed surface.

254.02Equipment.Use self-propelled planing equipment that has sufficient power and stability to consistently and efficiently meet the requirements of 254.05 and the plans.Use equipment with either grinding, sawing, or milling type cutters.Ensure that the cutters are mounted rigidly to the carrier and are adjustable to control the depth of cut and cross-slope.Accomplish longitudinal planing action by using equipment with a suitable carrier wheelbase or with an automatic control system having an external reference.Ensure that cross-slope adjustments or automatic controls are capable of producing either a variable or a constant cross-slope, as required.

For small or confined areas, the Contractormay use suitable supplemental equipment or methods approved by the Engineer.

254.03Planing.Make one or more planing passes, as necessary, over the designated area to the depth specified in the plans.Remove irregularities such as bumps, corrugations, and wheel ruts, when required, to establish a new pavement surface elevation or cross-slope.

Remove cuttings from the surface following each pass.Before opening the completed area to traffic, thoroughly clean the surface of all loose material that would create a hazard or nuisance, or would redeposit into the surface texture.Dispose of cuttings according to 202.

Implement effective measures to control dust, pavement contamination, and the scattering of loose particles during planing and cleaning operations.

If planing damages the adjacent pavement, repair the damaged area to the Engineerís satisfaction.Ensure that the repaired area matches the adjacent pavement in terms of smoothness and mix type.

254.04Surface Patching.Patch areas of the planed surface that the Engineerdesignates to have spalling or dislodged unsound pavement.Before patching, clean areas of loose material, coat with 407.02 asphalt material, and fill with Item 448, Type 1 material.Level and compact new material flush to the adjacent planed pavement.

254.05Surface Tolerances.Plane the surface free from grooves, ridges, gouges, or other irregularities detrimental to the safe operation of vehicles on the planed surface.

If the Contract specifies planing without resurfacing, plane the surface to a smoothness of 1/8 inch in 10 feet (3 mm in 3 m).If the Contract specifies resurfacing after planing, plane the surface to a smoothness of 1/4 inch in 10 feet (6 mm in 3 m).Match the surfaces at the edges of adjacent passes within 1/8 inch (3 mm).Ensure that the cross-slope of the planed surface is within 3/8 inch in 10 feet (10 mm in 3 m) of the specified cross-slope.

254.06Method of Measurement.The Engineerwill measure the quantity of PavementPlaning, AsphaltConcreteby the number of square yards (square meters).

The Engineerwill measure the quantity of Patching Planed Surface by the number of square yards (square meters).

254.07 Basis of Payment.The Department will not pay for repairs due to damage caused by planing operations.If the depth of the planed surfaces is increased by more than 3/8 inches (10 mm) the Department will compensate for the additional work.

The Department will pay for accepted quantities at the contract prices as follows:

Item†††††††††† unit††††††††††††††††††††††††††††††† Description

254†††††††††††† Square Yard††††††††††††††††† PavementPlaning, AsphaltConcrete
†††††††††††††††††††††† (Square Meter)††††††††††††

254†††††††††††† Square Yard

†††††††††††††††††††††† (Square Meter)††††††††† Patching Planed Surface