ITEM 622  CONCRETE BARRIER

622.01  Description

622.02  Materials

622.03  Placing Concrete

622.04  Portable Concrete Barrier

622.05  Joints

622.06  Finish

622.07  Curing

622.08  Method of Measurement

622.09  Basis of Payment

 

622.01  Description.  This work consists of furnishing and placing portland cement concrete barrier on the accepted and prepared subgrade, subbase course, or existing pavement.  This item also consists of furnishing, placing, maintaining, and removing portable concrete barrier.

622.02  Materials.  Furnish materials conforming to:

Concrete, Class C......................................................... 499

Reinforcing steel and wire fabric............................. 509.02

Forms ..................................................................... 515.14

Preformed filler ....................................................... 705.03

Curing materials......................................... 705.05, 705.06,

............................................................... or 705.07 Type 2

Precast concrete ...................................................... 706.13

Dowel bars........................................... 709.01 thru 709.05

Steel......................................................................... 711.01

 

622.03  Placing Concrete.  Construct concrete barrier by cast-in-place, precast, or slip-form methods.  For slip-form construction, conform to 609.04.C.

622.04  Portable Concrete Barrier.  Furnish individual sections not less than 10 feet (3 m) long.  If intending to use the barrier at one location on the project, the Contractor may slip-form barriers in place without joints, or with grooved or sawed joints to facilitate removal.  As directed by the Engineer, repair or replace barrier sections damaged during handling or by traffic, for the life of the project.

622.05  Joints.  Construct joints for cast-in-place or slip-formed barrier of the type and dimensions and at the locations specified.

A.      Contraction Joints.  The Contractor may construct unsealed contraction joints by either sawing, using metal inserts inside the forms, using a grooving tool, or using full-width 3/4-inch (19 mm) thick preformed joint filler conforming to 705.03.  Make joints that are sawed, tooled, or formed by inserts a minimum of 1/8 inch (3 mm) wide and 3 inches (75 mm) deep.  Saw joints as soon as curing allows sawing to the required depth with minimal spalling of the concrete surface.

B.      Expansion Joints.  Use 3/4-inch (19 mm) preformed joint filler conforming to 705.03 to construct expansion joints at the centerline of and around each bridge pier column and on either side of each sign support foundation.

C.      Horizontal Construction Joints.  If and as shown on the plans, the Contractor may place horizontal construction joints.

622.06  Finish.  Immediately following removal of fixed forms or slip-form construction, check the surface of the barrier with a straightedge and correct all irregularities of more than 1/4 inch in 10 feet (6 mm in 3 m).  Finish and make corrections to the barrier surface according to 511.18.

622.07  Curing.  Cure concrete according to 511.17, Method B and the following additional requirements.  Apply the curing compound using an approved mechanical sprayer equipped with a shield to protect the spray from wind.  For small areas, the Engineer will allow the use of other acceptable methods.

Do not apply any load or conduct any work that will damage newly placed concrete.  Allow a minimum of 36 hours of cure time to elapse on any concrete placed first at a horizontal construction joint.  The Contractor may cure precast sections according to 515.15.  With the Engineer’s approval, the Contractor may also use radiant heated forms for curing.

The Contractor may use 511.17, Method A for curing of short sections of barrier (leave-outs); however, before the curing is completed for any leave-outs, apply material conforming to 705.07, Type 2 at the normal rate specified in 511.17, Method B.

The Contractor may cure horizontal construction joints between the foundation and the upper portion of the barrier, and between portions of the upper barrier placed separately according to 511.17, Method A or B.  Do not remove the membrane before placing the next portion of the concrete barrier.

622.08  Method of Measurement.  The Department will measure Concrete Barrier by the number of feet (meters) along the centerline of the top of the barrier, including all transitions, end terminals, and bridge pier sections as specified, complete in place.

The Department will measure Portable Concrete Barrier and Portable Concrete Barrier, Bridge Mounted by the number of feet (meters) for each application of the barrier placed according to the plans.  The Department will measure each re-use of barrier sections at a different location required by the plans separately.

The Department will not measure repaired or replacement barrier sections damaged during handling or by traffic.

622.09  Basis of Payment.  The cost of all inserts, sleeves, fittings, connectors, reinforcement, dowels, preformed filler, excavation, and backfill is incidental to these items.

The Department will pay for accepted quantities at the contract prices as follows:

Item           unit                                Description

622             Foot (Meter)                   Concrete Barrier, Type ___

622             Foot (Meter)                   Portable Concrete Barrier, ___" (___ mm)

622             Foot (Meter)                   Portable Concrete Barrier, ___" (___ mm)

                                                               Bridge Mounted