ITEM 446 ASPHALT CONCRETE
446.01
Description
446.02 JMF Field Adjustments
446.03
Monitoring
446.04 Reports
446.05 Density
Acceptance
446.06 Joints
446.07 Basis of
Payment
446.01 Description. This work consists of
constructing a surface course or an intermediate course of aggregate and
asphalt binder mixed in a central plant and spread and compacted on a prepared
surface. The Department will base acceptance of the compacted mixture in place
on the level of density attained as sampled by the Contractor and analyzed by
the Department.
The
requirements of Item 441 apply, except as modified by
this specification.
446.02 JMF Field Adjustments. Determine
the need for any JMF gradation adjustments, provided
for in 441.05, in the first 3 days or first 3000
tons (3000 metric tons) of production, whichever comes last. Give the DET written notice of JMF
adjustments no later than the end of the following day’s production.
For
projects smaller than the above JMF field adjustment
period give the DET written notice of any JMF gradation adjustments within 1 workday following the
last day of production.
446.03 Monitoring. If there is poor comparison
between the Department’s comparison samples and the Contractor’s quality
control tests, the Monitoring Team may at any time disallow production to
continue under Item 446. In this case, conform to
Items 448 and 446. The
Department will notify the Contractor in writing to stop production.
446.04 Reports. Submit the Quality Control Report
according to 441.11 on the workday following the
production day of the material represented by the report.
446.05 Density Acceptance. The
requirements of 401.13 do not apply.
However, rollers must fully and satisfactorily provide the required compaction,
be mechanically sound, and meet Hot Mix Asphalt industry standards. The
Department retains the right to reject the use of rollers which are not in good
repair, or are not designed to do the work required. A three-wheel roller
according to 401.17 is not required.
Obtain
ten, 4-inch cores for the Department to test to determine the in-place density
of the compacted mixture as a percentage of the average QC Maximum Specific
Gravity (MSG) for the production day the material was placed. If
Department MSG VA tests show poor comparison to the average QC MSG according to
403.06 use Department determined MSG results in the density
calculation for each production day. Compact shoulders using the same
equipment and procedures as used on the mainline pavement. The
requirements of 401.16, except for the last four
paragraphs, are waived.
Payment
for compaction of the completed mainline pavement and ramps is by Lot, based
upon the degree to which density is attained. Payment for shoulders
depends on the degree to which the density is obtained on the adjacent mainline
pavement lane or ramp. However, when a cold longitudinal joint is made
between a mainline pavement lane and an adjoining shoulder, payment for the
shoulder will be based on the degree to which the density is obtained on the
shoulder.
A
Lot consists of an area of pavement placed during a production day, including
the shoulders. If less than 400 tons (400 metric tons) is produced in a
production day, then that production day is combined with the next production
day into a single Lot. If greater than 250 tons (250 metric tons) and
less than 400 tons (400 metric tons) are produced on the last day of production
for the project, then the day’s production is a separate Lot. If less
than 250 tons (250 metric tons) is produced on the last production day for the
project, it is part of the previous Lot for acceptance, provided the previous
Lot was placed within 3 days; otherwise, it is a separate Lot.
Within
48 hours after the pavement is placed, obtain ten cores for each Lot at random
locations the Engineer determines. The Engineer will divide a Lot into
five equal sublots and calculate two random core
locations in each sublot as described below using an
acceptable random number selection method. Both mainline pavement and
ramps will be included in Lot determinations. The Engineer will not give
the Contractor random core locations early in the Lot placement. The
Engineer will tell the Contractor the method used to determine random locations
as noted below before project start and will use the same method for all Lots.
For
each Lot three cores will be taken as follows from cold longitudinal joints and
seven cores will be taken from the mat not including the joints. If locations
not according to this specification are given, immediately inform the
Engineer. Do not take cores from ramp joints. Take joint cores from
the first, last and randomly from one of the three middle sublots.
Determine the longitudinal location of the joint core within the sublot randomly and also randomly determine whether or not
the cold longitudinal joint core is to be taken from a confined or unconfined
joint if both exist in the mat to be cored. Do not take cores on the
sloped face of a wedge before the adjoining lane is placed. Take joint
cores such that the core's closest edge is six inches (150 mm) from the edge of
the joint upper notch of a wedge joint or 4 inches (100 mm) from the edge of a
vertical face joint. If a nine inch or wider wedge joint is used take the
core three inches from the upper wedge joint notch. Take the seven random
mat cores that are not for the joint coring such that the core's closest edge
is at least twelve inches from the cold longitudinal joint wedge joint upper notch
or vertical face edge. If taken, locate cores for the Contractor’s
quality control (sister core) longitudinally from and within four inches (100
mm) of the random core.
The
Department will determine the pay factor for each Lot cored by the pay schedule
in Table 446.05-1 for Lots with three cold
longitudinal joint cores and Table 446.05-2
for Lots with less than three cold longitudinal joint cores. The
Department will verify the MTD if the MSG
determination has a deviation from the MTD of less
than or equal to 0.020. If the MTD is not
verified, establish a new MTD according to the
procedures established in 441.09. If less
than 10 cores are available for determining the mean, the Laboratory will
determine disposition of the Lot.
Fill
core holes by the next workday. Before filling, ensure the holes are dry
and tack them with asphalt material conforming to 407.02.
Properly compact the asphalt concrete used for filling the hole and leave it
flush with the pavement.
TABLE
446.05-1 FOR LOTS WITH 3 COLD JOINT CORES
Mean of Cores [1] |
Pay Factor |
|
Surface Course |
Intermediate Course |
|
98.0% or greater |
[2] |
[2] |
97.0 to 97.9% |
0.94 |
[2] |
96.0 to 96.9% |
1.00 |
0.94 |
93.4 to 95.9% |
1.04 [4] |
1.00 |
92.4 to 93.3% |
1.00 |
1.00 |
91.4 to 92.3% |
0.98 |
1.00 |
90.4 to 91.3% |
0.90 |
0.94 |
89.4 to 90.3% |
0.80 |
0.88 |
88.4 to 89.3% |
[3] |
[3] |
Less than 88.4% |
[2] |
[2] |
[1] Mean of cores as percent
of average MSG for the production day. |
||
[2] For surface courses,
remove and replace. For other courses, the District will determine whether
the material may remain in place. If the District determines the course
should be removed and replaced, the Contractor will remove and replace this
course and all courses paved on this course. The pay factor for
material allowed to remain in place is 0.60. |
||
[3] The District will
determine whether the material may remain in place. If the District
determines the course should be removed and replaced, the Contractor will
remove and replace this course and all courses paved on this course.
The pay factor for such material allowed to remain in place is 0.70. [4] No incentive will be
paid if any single cold joint core is less than 91.0%. |
TABLE
446.05-2 FOR LOTS WITH LESS THAN 3 COLD JOINT
CORES
Mean of Cores [1] |
Pay Factor |
|
Surface Course |
Intermediate Course |
|
98.0% or greater |
[2] |
[2] |
97.0 to 97.9% |
0.94 |
[2] |
96.0 to 96.9% |
1.00 |
0.94 |
94.0 to 95.9% |
1.04 [4] |
1.00 |
93.0 to 93.9% |
1.00 |
1.00 |
92.0 to 92.9% |
0.98 |
1.00 |
91.0 to 91.9% |
0.90 |
0.94 |
90.0 to 90.9% |
0.80 |
0.88 |
89.0 to 89.9% |
[3] |
[3] |
Less than 89.0% |
[2] |
[2] |
[1] Mean of cores as percent
of average MSG for the production day. |
||
[2] For surface courses,
remove and replace. For other courses, the District will determine
whether the material may remain in place. If the District determines
the course should be removed and replaced, the Contractor will remove and
replace this course and all courses paved on this course. The pay
factor for material allowed to remain in place is 0.60. |
||
[3] The District will
determine whether the material may remain in place. If the District
determines the course should be removed and replaced, the Contractor will
remove and replace this course and all courses paved on this course.
The pay factor for such material allowed to remain in place is 0.70. [4] No incentive will be
paid for lots where 3 joint cores are required to be taken but less than 3
cores are taken. |
446.06 Joints. Construct joints according to 401.17. Make a hot longitudinal joint between
the mainline pavement lane and the adjoining shoulder and all ramps and the
adjoining shoulders. If a hot longitudinal joint is specified between the
mainline pavement lanes, the Contractor may construct a cold longitudinal joint
between the mainline pavement lanes and the adjoining shoulders. Cold
longitudinal joints in mainline pavement will be tested according to 446.05.
446.07 Basis of Payment. The
Department will pay for accepted quantities, completed in place, at the
contract prices, as modified by 446.05, as
follows:
Item
Unit
Description
446
Cubic
Yard
Asphalt Concrete
(Cubic
Meter)
Intermediate Course, Type ___
446
Cubic
Yard
Asphalt Concrete Surface
(Cubic
Meter)
Course, Type ___