ITEM 504 SHEET PILING LEFT IN PLACE
504.01
Description
504.02
Materials
504.03 Driving
504.04 Method
of Measurement
504.05 Basis of
Payment
504.01 Description. This work consists of
furnishing and driving steel sheet piling to be left in place, including
furnishing and installing any specified anchors or other attachments to
structures.
504.02 Materials. Furnish new sheet piling
conforming to 711.03. The
Contractor may use used sheet piling in good condition that conforms to project
requirements provided it is inspected and approved by the Engineer.
504.03 Driving. Drive steel sheet piling to the
tip elevation shown on the plans. Thread each sheet pile with adjacent
sheets. Use corner piles, junction piles, and interlocking connectors as
necessary so that all sheet piles are interlocked.
504.04 Method of Measurement. The
Department will measure Steel Sheet Piling Left In Place [Minimum Section
Modulus of ____ cubic inches per foot (____ mm³/m)] of Wall by measuring the
number of square feet (square meters) in the plane of the face of the sheeting,
completed and accepted in place.
504.05 Basis of Payment. The
Department will pay for accepted quantities at the contract price as follows:
Item
Unit
Description
504
Square Foot
Steel Sheet Piling Left In Place [Minimum
(Square
Meter)
Section Modulus of____ cubic inches
per foot (____ mm³/m)] of Wall