505.01 Description. This work consists of mobilizing
pile driving equipment to and from the project site and, as necessary, to
install the required piling.
This
work includes the fixed costs that are related to the installation of the
required piling.
505.02 Basis of Payment. The
Department will pay for accepted quantities, after the first service pile is
installed, at the contract price as follows:
Item
Unit
Description
505
Lump
Sum
Pile Driving Equipment Mobilization