624.01 Description. This work consists of the
preparatory work and operations including, but not limited to, those necessary
for the movement of personnel, equipment, supplies, and incidentals to the
project site; for the establishment of all field offices, buildings, and other
facilities necessary for work on the project; for all other work and operations
that must be performed or costs incurred before beginning the Work on the other
contract items; and for demobilization.
If
Mobilization is not included as a pay item in the Contract, the Department will
not pay for this work separately but will consider it incidental to the other
Contract Items.
624.02 Limitation. The Department will limit the sum
of the partial payments specified in 624.04.A
and 624.04.B to the amounts shown in Table 624.02-1 under “Maximum Total of Partial
Payments”. The Department will pay the balance of the lump sum amount
bid, as specified in 624.04.C.
Total Contract Amount |
Maximum Total of Partial Payments |
|
More than |
Up to, inclusive |
|
($) |
($) |
($) |
0 |
50,000 |
0 |
50,000 |
100,000 |
2,000 |
100,000 |
200,000 |
4,000 |
200,000 |
500,000 |
10,000 |
500,000 |
1,000,000 |
20,000 |
1,000,000 |
2,000,000 |
40,000 |
2,000,000 |
5,000,000 |
100,000 |
5,000,000 |
10,000,000 |
200,000 |
10,000,000 |
20,000,000 |
400,000 |
20,000,000 |
40,000,000 |
800,000 |
40,000,000 |
60,000,000 |
1,200,000 |
60,000,000 |
80,000,000 |
1,600,000 |
80,000,000 |
-- |
2,000,000 |
If
the lump sum amount bid for Mobilization exceeds the total shown in Table 624.02-1 for partial payments, the Department
will pay the excess upon completion of the project.
624.03 Method of Measurement. The
Department will measure Mobilization as a unit, acceptably performed.
624.04 Basis of Payment. The
Department will make partial payments according to 109.09 and as modified by the following
schedule:
A. The Department will release 50 percent
of the lump sum amount bid for Mobilization or 50 percent of the amount shown
in 624.02, whichever is less, to the Contractor
with the first estimate payable, but not sooner than 15 days after the start of
work at the project site.
B. The Department will release an
additional 40 percent of the lump sum amount bid for Mobilization or 40 percent
of the amount shown in 624.02, whichever is
less, with the first regular estimate after 10 percent of the original total
contract amount, including payments for delivered materials but excluding
Mobilization, is earned.
C. Upon completion of all work on the
project, including final cleanup, the Department will release payment of the
remaining 10 percent of the lump sum amount bid for Mobilization and any amount
of the lump sum price bid for Mobilization, in excess of the total amount shown
in 624.02 for partial payment. Final
cleanup includes but is not limited to the removal of construction layout
stakes and sediment and erosion control items.
The
Department will pay for accepted quantities at the contract price as follows:
Item
Unit
Description
624
Lump
Sum
Mobilization