652.01 Description. This work consists of
hauling and spreading topsoil from stockpiles and preparing the surface.
652.02 Construction Requirements. Prepare
the surface according to 653.03. Place and
spread the topsoil according to 653.03.
652.03 Method of Measurement. The
Department will measure Placing Stockpiled Topsoil by the number of cubic yards
(cubic meters) completed and accepted in place.
652.04 Basis of Payment. The
Department will pay for accepted quantities at the contract price as follows:
Item
Unit
Description
652
Cubic
Yard
Placing Stockpiled Topsoil
(Cubic Meter)