construction | contracts | districts | engineering | financial | home | intranet | otis | policy | services |
|
ODOT SUPPLEMENTAL SPECIFICATIONS, SUPPLEMENTS
and PROPOSAL NOTES
to be used with the 2002 CMS
last updated: 04/16/08
For the list of updates Click Here
( PN 0-100 are Maintained by the Office of Contract Sales) |
|||
NO. |
DATE |
DESCRIPTION - CONSTRUCTION ITEMS |
|
~ 101-02 |
10/15/2004 |
BOILER-PLATE PROPOSAL NOTE TO BE USED ON ALL PROJECTS USING THE 2002 CONSTRUCTION AND MATERIAL SPECIFICATIONS 10-15-2004 Designers Note: This note should be used on all projects using the 2002 Construction and Materials Specifications. |
|
~ 101-02DB |
10/15/2004 |
BOILER-PLATE PROPOSAL NOTE TO BE USED ON ALL DESIGN BUILD PROJECTS USING THE 2002 CONSTRUCTION AND MATERIAL SPECIFICATIONS 10-15-2004 Designers Note: This note should be used on all projects using the 2002 Construction and Materials Specifications AND are Design Build. |
|
~ 102 |
1/2/2002 |
BAR CHART SCHEDULE Designers Note: Use this note on all projects that do not use PN 107 |
|
~ 103 |
1/7/1998 |
VALUE ENGINEERING CHANGE PROPOSAL - CONSTRUCTION COSTS Designers Note: This note should be included on all projects that do not have PN 104. This note shall not be used along with PN 120, PN 121, PN 122, PN 124. For additional information on the policy and application of this note contact the Office of Construction Administration at (614)466-4788. |
|
~ 104 |
1/7/1998 |
VALUE ENGINEERING CHANGE PROPOSAL - CONSTRUCTION COSTS AND TIME Designers Note: This note may be included on major bridge, major new, and four or more lane divided projects. Projects which have an Incentive/Disincentive clause, or which use A plus B bidding or Lane Rental are not eligible for Value Engineering Change Proposals for time savings. Close consideration of the project completion date must be made when selecting this note. This note shall not be used along with PN 120, PN 121, PN 122, PN 124. The District Production Administrator shall determine when this note is necessary. For additional information on the policy and application of this note contact the Office of Construction Administration at (614)466-4788. |
|
~ 105 |
5/5/1998 |
VOLUNTARY ON-THE JOB TRAINING PROGRAM PROVISIONS Designers Note: This note must be included on all Federal-aid contracts. Any questions should be addressed to Wilbert Crockett in the Office of Contracts at 614-644-8243. |
|
~ 107 |
1/16/2004 |
CRITICAL PATH METHOD PROGRESS SCHEDULE Designers Note: This note should be used for projects whose cost is greater than $5 million; which have more than 3 phases; or, as may otherwise be appropriate. The Critical Path Method Progress Schedule is now a contract pay item as per Section VII of the note. This note shall also be used when PN 120, PN 121, PN 122, PN 123, and PN 124 are specified. |
|
~ 108 | 11/7/2000 |
DISPUTE REVIEW BOARD Designers Note: This note should be considered for use on all projects over $20, 000, 000. The Three Party Agreement must be used with this note. Any questions should be addressed to Clint Bishop in the Office of Construction Administration [614-387-1164] or Mark G. Kelsey in the Office of Contracts [614-466-3778] |
|
~ 120 | 1/16/2004 |
WORK DAY CONTRACT Designers Note: This note shall be used on projects selected according to the Innovative Contracting Manual. Do not include a contract completion date as this introduces conflicting information into the proposal. Modifications
are ONLY allowed in designated areas: 1
Number of Work
Days to complete all work [Must be filled in] |
|
~ 121 | 7/18/2003 |
INCENTIVE/DISINCENTIVE CONTRACT Designers Note: This note shall be used on projects selected according to the Innovative Contracting Manual. Modifications
are ONLY allowed in designated areas: 1. A date established for the completion of all identified critical work. The date may be the project completion date or any other day when a certain phase or phases of the contract must be completed. [Must be Filled in] 2. Critical work - Describe what has to be open to unrestricted traffic. 3a. Daily User Cost or Daily Incentive [Default: $3,000] 3b. Daily User Cost or Daily Disincentive [Default: $3,000] may be equal to the Daily Incentive. 4. Maximum incentive - maximum total dollar amount of Daily Incentives - [Default: 5% of contract] |
|
~ 122 | 7/18/2003 |
LIQUIDATED SAVINGS CONTRACT Designers Note: This note shall be used on projects selected according to the Innovative Contracting Manual. Modifications
are ONLY allowed in designated areas: 1. Critical Work - Description of what has to be open to unrestricted traffic [Default: Project] 2. Time is established for the completion of all identified critical work. The LS/LD time may be the contract length or shorter when traffic is impacted only during a certain phase or phases of the contract. A date or critical time will be established for unrestricted traffic. [Must be Filled in] 3. Liquidated Savings Amount - Daily User Costs [Default: $3,000] 4. Maximum incentive - maximum total dollar amount of Daily Liquidated Savings [Default: 5% of contract] 5. Liquidated Damages Amount - Daily User Costs [Default: $3,000] |
|
~ 123 | 7/18/2003 |
LUMP SUM INCENTIVE CONTRACT Designers Note: This note shall be used on projects selected according to the Innovative Contracting Manual. Modifications
are ONLY allowed in designated areas: 1. A date half way through the project by which the Contractor must submit letter of intent [Must be Filled in] 2. A date established for the completion of all identified critical work. The date may be the contract length or shorter when traffic is impacted only during a certain phase or phases of the contract. [Must be Filled in] 3. Description of what has to be open to unrestricted traffic [Default: Project] 4. Lump Sum Incentive [Default: 5% of contract] OAC Rule 5501:2-7-04 provides that the Director shall not pay more than five per cent of the total contract amount in incentive payments unless he determines that the work is so critical that a higher percentage is warranted. |
|
~ 124 |
7/18/2003 |
SPECIAL CLAUSES FOR CALENDAR DAYS OF CONTRACT TIME FOR OPENING TO UNRESTRICTED TRAFFIC: A+B BIDDING Designers Note: This note shall be used on projects selected according to the Innovative Contracting Manual. Modifications
are ONLY allowed in designated areas: 1. Description of what has to be open to unrestricted traffic [Default: Project] 2. Line and page number of Part B in proposal [Must be filled in] 3. Maximum Calendar Days [Default: 40 days] 4. Daily User Cost [Default: $3,000] 5. Additional Calendar days for completion [Default: 10 days] 6. Possible start date window [Must be filled in] 7. Maximum incentive amount [Default: 5% of Contract] |
|
~ 150 |
6/27/1996 |
COOPERATION WITH RAILROADS Designers Note: This note should be used for projects which include work on or adjacent to railroad property where no separate agreement with the railroad company is required. The note should be edited to identify the specific railroad/railway company involved. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 151 |
10/18/2002 |
COOPERATION WITH RAILROADS - NORFOLK AND SOUTHERN RAILWAY COMPANY Designers Note: This note should be used for projects which include work on or adjacent to Norfolk and Southern Railway property where no separate agreement with the railroad company is required. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 152 |
6/27/1996 |
COOPERATION WITH RAILROADS - CSX TRANSPORTATION, INC. Designers Note: This note should be used for projects which include work on or adjacent to CSX Transportation property where no separate agreement with the railroad company is required. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 153 |
6/27/1996 |
COOPERATION WITH RAILROADS - GREATER CLEVELAND REGIONAL TRANSIT AUTHORITY Designers Note: This note should be used for projects which include work on or adjacent to Greater Cleveland Regional Transit Authority property where no separate agreement with the railroad company is required. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 157 |
6/27/1996 |
COOPERATION WITH RAILROADS - INDIANA AND OHIO RAIL SYSTEM Designers Note: This note should be used for projects which include work on or adjacent to Indiana and Ohio Rail System property where no separate agreement with the railroad company is required. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 159 |
5/31/2000 |
COOPERATION WITH RAILROADS - WHEELING AND LAKE ERIE RAILWAY COMPANY Designers Note: This note should be used for projects which include work on or adjacent to Wheeling and Lake Erie Railway Company property where no separate agreement with the railroad company is required. Technical questions should be addressed to Heidi Nunemaker, Central Office Rail Coordinator at 614-387-3091 |
|
~ 205 |
4/17/2004 |
TEMPORARY SEDIMENT AND EROSION CONTROLS WITH PRICES Designers Note: Provide this proposal note on all plans that have Project Identified earth-disturbing activities, as defined as, any activity that exposes bare ground or an erodible material to storm water and anywhere CMS Item 659 Seeding, SS 870 Seeding, CMS Item 660 Sodding, or SS 870 Sodding is being furnished. Delete all CMS 207 Items and all SS 877 Items Provide SS 832 and SS 833 with this proposal note. Provide under the Erosion Control Heading the following Reference Items: Item 832 Each Erosion Control. Item 832 Each Storm Water Pollution Prevention Plan. Provide a encumbered dollar value to be placed in the proposal for the Item: 832 Each Erosion Control. This amount is for both the quantity and total spaces. This amount should only be provided in the C2 Estimate and in the Special Considerations Field on the Plan Package Submittal Form and in the plans. For additional guidance see the NPDES Construction Permit Implementation Plan flowchart on the Office on Production website. Example 10,000$ set up for Item 832 Each Erosion Control then 10,000 placed in the quantity and total spaces. |
|
~ 414 |
10/18/2002 |
ASPHALT CONCRETE SURFACE SMOOTHNESS REQUIREMENTS Designers Note: This note should be used with 446 asphalt concrete surface courses when the project: 1. Involves constructing or resurfacing greater than 1 centerline mile of a divided highway with 2 or more lanes in each direction; and, 2. The total new pavement thickness is greater than 4 inches without planing the existing surface or greater than 3 inches if the existing pavement is planed. |
|
~ 414DB | 10/18/2002 | ASPHALT CONCRETE SURFACE
SMOOTHNESS REQUIREMENTS FOR DESIGN-BUILD PROJECTS
Designers Note: This note is to be used ONLY on Design-Build projects with 446 asphalt concrete surface courses when the project: 1. Involves constructing or resurfacing greater than 1 centerline mile of a divided highway with 2 or more lanes in each direction; and, 2. The total new pavement thickness is greater than 4 inches without planing the existing surface or greater than 3 inches if the existing pavement is planed. The note is similar to PN414 except that the "pay adjustments with incentives" table and basis of payment" section have been modified to be used in the Design-Build Lump Sum environment. Questions regarding this note should be directed to Dan Groh in the Office of Construction Administration (614) 387-1162. Implementation Plan: This note should be used effective immediately. It replaces PN 415 which has been rescinded. This note can usually be used without the need for additional plan details. |
|
~ 416 |
12/7/1995 |
DESIGN REQUIREMENTS FOR PLANT MIX PAVEMENTS (HEAVY) Designers Note: Use this note on all projects having 301, 402, 403, 404, 412, 446, or 448, where the number of trucks (ADT x T24) in the current traffic is 1500 or more. If the project is in a mining or manufacturing area where there will be loaded coal, gravel, stone, steel, etc. trucks making starting, stopping, or turning movements creating higher stresses in the pavement, use 750 trucks for the threshold of "Heavy". Questions concerning this note should be directed to the Office of Pavement Engineering 614-995-5990. |
|
~ 417 |
12/7/1995 |
DESIGN REQUIREMENTS FOR PLANT MIX PAVEMENTS (MEDIUM) Designers Note: Use this note on all projects having 301, 446 or 448, where the number of trucks (ADT x T24) in the current traffic is 50 to 1499. If the project is in a mining or manufacturing area where there will be loaded coal, gravel, stone, steel, etc. trucks making starting, stopping, or turning movements creating higher stresses in the pavement, use 50 to 749 trucks as the criteria for "Medium". Questions concerning this note should be directed to the Office of Pavement Engineering 614-995-5990. |
|
~ 418 |
12/7/1995 |
DESIGN REQUIREMENTS FOR PLANT MIX PAVEMENTS (LIGHT) Designers Note: Use this note on all projects having 301, 446 or 448, where the number of trucks (ADT x T24) in the current traffic is less than 50. Questions concerning this note should be directed to the Office of Pavement Engineering 614-995-5990. |
|
~ 419 |
6/11/1997 |
DESIGN REQUIREMENTS FOR PLAN MIX PAVEMENTS (MULTIPLE TRAFFIC) - Designers Note: Use this note when the project includes sections of roadway where different traffic volume designs should be specified. Fill in Blank (1) with Heavy, Medium, or Light. Fill in Blank (2) with Part or Route numbers. Use a Heavy Traffic designation where the number of trucks (ADT x T24) in the current traffic is 1500 or more or if the project is in a mining or manufacturing area where there will be loaded coal, gravel, stone, steel, etc. trucks making starting, stopping or turning movements creating higher stresses in the pavement, use 750 trucks for the threshold of "Heavy." Use a Medium Traffic designation where the number of trucks (ADT x T24) in the current traffic is 50 to 1499 or if the project is in a mining or manufacturing area where there will be loaded coal, gravel, stone, steel, etc. trucks making starting, stopping, or turning movements creating higher stresses in the pavement, use 40 to 749 trucks as the criteria for "Medium." Use a Light Traffic designation where the number of trucks (ADT x T24) in the current traffic is less than 50. Questions concerning this note should be directed to the Office of Pavement Engineering 614-995-5990. |
|
~ 420 |
10/30/2003 |
SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS Designers Note: This note should be used on all paving projects when: 1. The project involves constructing or resurfacing a divided highway with 2 or more lanes in each direction; 2. The project is at least 1 centerline mile (1.6 km) long; 3. The design speed is 50 miles per hour (80 km/h) or greater; and, 4. The total new pavement thickness is greater than 4 inches (100 mm) without planing the existing surface or greater than 3 inches (75 mm) if the existing pavement is planed. The 3-inch (75 mm) minimum on a planed surface is increased to 4 inches (100 mm) if planing down to a concrete surface. This note replaces the previous PN414, PN414DB, PN450, and PN450DB notes. |
|
~ 450 |
3/3/1992 |
SURFACE SMOOTHNESS REQUIREMENTS FOR ITEMS 451, 452 Designers Note: Use this note on all projects using Items 451, 452 Concrete Pavement exceeding 1 mile in centerline length. |
|
~ 450DB | 8/29/2000 | SURFACE SMOOTHNESS
REQUIREMENTS FOR ITEMS 451, 452 ON DESIGN-BUILD PROJECTS
Designers Note: This note is to be used ONLY on Design-Build projects using Items 451, 452 Concrete Pavement exceeding 1 mile in centerline length. The note is similar to PN450 except that the "pay adjustments with incentives" table and basis of payment" section have been modified to be used in the Design-Build Lump Sum environment. Questions regarding this note should be directed to Dan Groh of the Office of Construction at 614-387-1162 Implementation Plan: This note should be used effective immediately. This note can usually be used without the need for additional plan details. |
|
~ 511 |
4/19/2002 |
ITEM SPECIAL - PATCHING CONCRETE BRIDGE DECK OVERLAYS WITH MICRO-SILICA MODIFIED CONCRETE Designers Note: Intended for use where spot patching of an existing concrete bridge deck overlay is performed instead of replacing the entire existing overlay. Micro-Silica Modified Concrete is used regardless of the composition of the existing concrete overlay. This repair, as any patch, should be considered a short term fix. This fix is better than the use of cold patch or other asphalt material as the asphalt material gives the salt laden water a location to continue to pond on the concrete and help keep the corrosion process active. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 512 |
4/19/2002 |
ITEM SPECIAL - PATCHING CONCRETE BRIDGE DECKS Designers Note: Intended for use where spot patching of an existing concrete bridge deck is performed instead of placing a new overlay over the entire existing deck. The method of patching must be selected from the note and included on the pay item description. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 514 |
4/19/2002 |
6 MM (1/4") EPOXY WATERPROOFING OVERLAY FOR BRIDGE DECKS Designers Note: Intended for use on an existing concrete bridge deck on which the existing surface finish has worn away to the point where there is insufficient skid resistance available and needs to be restored, or where an existing concrete deck is cracked to the point where waterproofing is necessary but where the additional deadload on the superstructure needs to be kept to an absolute minimum so that the bridges load rating is not significantly lowered, or both. This proposal note is not for use on any deck material (ex. timber) except for concrete. The proposal note, "Patching Concrete Bridge Decks" (proposal note 512), is referenced in this note and must be listed for inclusion in the contract documents. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 515 |
4/19/2002 |
TREATING CONCRETE BRIDGE DECKS WITH GRAVITY-FED RESIN Designers Note: Intended for use on an existing concrete bridge deck which has cracked to the point where waterproofing is necessary but where the additional deadload on the superstructure needs to be kept to an absolute minimum. This is typically used on decks where the cracks are full depth. This is also often used on new decks that have experienced severe cracking from the onset. If looking for a long term fix, consideration should be first given to using a concrete overlay in lieu of this. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 522 |
5/22/1997 |
ITEM SPECIAL - CONCRETE REPAIR BY EPOXY INJECTION Designers Note: Used whenever cracks in concrete members are to be repaired. Crack limitations are listed in the note and widths beyond those shown will require a different procedure to repair them. This is not to be used to seal cracks in concrete bridge decks. The use of this procedure to repair deck delaminations on the underside of a deck is strongly discouraged as its effectiveness and durability are unknown. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 523 |
4/19/2002 |
CONCRETE REPAIR USING PREPLACED AGGREGATE CONCRETE Designers Note: Used when making repairs to existing concrete members that require formwork but the new concrete cannot be placed by traditional methods (chute, pumping, etc.) due to physical limitations that are imposed by the location of the repair area. This should only be used when it has been determined by the designer that the other repair methods discussed in the Bridge Design Manual are not appropriate for the project. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 525 |
8/2/2004 |
STEEL PRICE ADJUSTMENT Designers Note: For use on all projects that require steel of the types listed in the note |
|
~ 527 |
11/7/1994 |
ITEM 515 - HIGH EARLY STRENGTH KEYWAY GROUT FOR PRESTRESSED/POST-TENSIONED CONCRETE MEMBERS Designers Note: Standard Bridge Drawing PSBD-1-93, on sheet 1 of 4, requires that a different mortar be used when traffic (either construction or normal vehicle) will be on the beams within seven days of grout placement or when part-width construction is being used. Reference is made in the drawing to a proposal note for the specifications regarding the mortar to be used under these circumstances. Proposal Note 527 is the note that is referenced and must be included in the contract documents on all projects where the before mentioned standard bridge drawing is used. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 528 |
4/19/2002 |
ITEM SPECIAL - HEAT STRAIGHTENING OF DAMAGED STRUCTURAL STEEL Designers Note: Used when heat straightening is to be used to straighten damaged portions of existing beams/girders. The damage can be either from vehicular (or load) impact or from construction activities. The note is geared towards vehicular impact. The locations needing repair need to be shown in the plans. The designer should note that the straightening of truss members requires special considerations and may require some additional plan details and/or notes. As far as specifying a best sequence of repair, since heat straightening is more of an "art", it is usually better to leave the actual sequence of repairs up to the Contractor and place a note in the plans requiring the Contractor to submit a detailed procedure for review and approval prior to the commencement of any work. The repair plans should show in detail the desired final end (finished) condition of the bridge. If a certain procedure or sequence is specified, it might limit the abilities of the Contractor. The proposal note "Concrete Repair By Epoxy Injection" (proposal note 522) is referenced in this note and must be listed for inclusion in the contract documents. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 530 |
4/19/2002 |
ITEM SPECIAL - STRUCTURAL SURVEY AND MONITORING OF VIBRATIONS Designers Note: This note is used where there exists the potential of an existing structure being damaged by ground vibrations caused by certain construction activities that are performed in close proximity to the structure. Some activities that could possibly produce damaging vibrations are rock blasting and blasting for the purpose of removing an existing structure. While pile driving is often thought of as being a vibration problem (and this note has been used with pile driving on a few occasions), ODOT has found no vibrational damage to adjacent buildings, etc. due to pile driving. The note requires that a survey be conducted of the condition of the structures and the monitoring of ground vibrations by qualified personnel. This note is seldom used. The designer should contact the Office of Structural Engineering as to whether or not the note should be used on a specific project. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 531 |
4/19/2002 |
ITEM 511.11 ANTI-WASHOUT ADMIXTURE FOR UNDER WATER CONCRETING/GROUTING Designers Note: This note is only used when concrete is placed directly under water. This note is rarely used. It is not used in conjunction with the construction of drilled shafts. This note should not be automatically used by the designer since the placement of structural concrete under water is only allowed by permission of the Department. This note should only be used after consultation with and approval by the Office of Structural Engineering. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
|
~ 608 |
11/22/1994 |
ITEM 603, PIPE CULVERTS, SEWERS, DRAINS AND ITEM 638 WATER LINES UNDER RAILROAD Designers Note: This note should be added whenever conduit or pipe is placed under railroad tracks. Edit note to include railroad company name. The construction plans should show additional details such as locations, elevations, materials, quantities, etc. |
|
~ 621B |
4/16/1996 |
SIGNAL MAINTENANCE PERSONNEL REQUIREMENTS (632, 633) Designers Note: This note will be included in all signal maintenance plans and other electrical traffic control device maintenance contracts where more than one crew is required to perform work when items 632 or 633 are called out. |
|
~ 651 |
6/13/2003 |
HERBICIDAL PRODUCT DATA Designers Note : Use this note for any projects which include Herbicidal Spraying. Herbicidal Spraying may be listed separately on the General Summary as an Item Special; or it may be included in other items, for example, Item 209 - Linear Grading. |
|
~ 701 |
10/31/1986 |
ITEM SPECIAL - CRACK AND JOINT CLEANING AND SEALING, 705.04 DESIGNERS NOTE: This note should be used on all projects which include Item Special -Crack and Joint Cleaning and Sealing, 705.04. This item is designed to seal concrete pavement. |
|
~ 860 |
4/8/1974 |
GUARANTIES AND WARRANTIES DESIGNERS NOTE: This note should be used to extend the completion date for repair of equipment that is supplied under warranty or guarantee. This note is generally used with equipment related items such as 625, 631, 632 and 633. It is not associated with pavement or pavement marking warranties. |
|
~ 882 |
2/1/1986 |
COMPLETION OF ORIGINAL WORK AND FINAL CONTRACT COMPLETION DESIGNERS NOTE: This note should be used on all district wide pavement marking projects. The Final Contract Completion date must be revised on a yearly basis. Except traffic paint (Item 642) |
|
~ 890 |
7/30/2004 |
PAVEMENT MARKING FOR DISTRICT WIDE PAVEMENT MARKING PROJECTS DESIGNERS NOTE: This note should be used on all district wide pavement marking projects. |
|
~ 891 |
3/22/2004 |
PAINTING OF STRUCTURAL STEEL DESIGNERS NOTE: This note should be used on all projects that reference CMS Item 514. |
|
NO. |
DATE |
DESCRIPTION - CONSTRUCTION ITEMS |
|
10/30/2003 |
Crack and Joint Cleaning and Sealing with Silicone Sealant | ||
7/19/2002 |
Post Construction Inspection of
Storm Sewers and Drainage Structures
Designer Note: Add to all jobs that have any 603 Type B or C Storm Sewers or any 604 catch basins or manholes. No other changes are required. |
||
7/19/2002 |
Rubberized Open Graded Asphalt Friction Course Designer Note: A Use where surface water drainage is a concern, a high skid condition exists or it is desired to control sound in abnormally high sound problem areas. B This product uses only air cooled slag so check on availability and cost for your area. C Use a 0.75 inch lift on an existing or new 446 or 448 Type 1 or 442 9.5 or 12.5mm asphalt course. D Do not apply over milled surfaces. Apply over existing surfaces that have sound aggregate and no visual evidence of stripping. E When selecting for use be careful if applying in low tonnage applications. The best production product is achieved in production of at least 300 tons. F No special maintenance of traffic considerations. |
||
11/6/2001 |
Cement Stabilized Subgrade Designer Note: Use Cement Stabilized Subgrade per the Guidelines for Plan Subgrade Treatments or upon the recommendation of the Office of Geotechnical Engineering. |
||
805 |
|
Fiber Optic Cable (Under development) Designer Note: To be developed |
|
806 |
|
Dynamic Message Signs (Under development) Designer Note: To be developed |
|
807 |
|
Closed Circuit Television (CCTV) Pole (Under development) Designer Note: To be developed |
|
808 |
|
Closed Circuit Television Camera System (Under development) Designer Note: To be developed |
|
809 |
|
Ramp Metering Station (Under development) Designer Note: To be developed |
|
810 |
|
Radar Detection System (Under development) Designer Note: To be developed |
|
7/19/2002 |
Asphalt Undersealing of Existing Concrete Pavement | ||
4/19/2002 |
Grout Subsealing of Existing Concrete Pavement | ||
4/19/2002 |
Correcting Elevation of Concrete Approach Slab and Pavement | ||
4/11/2002 |
Dowel Bar Retrofit | ||
7/19/2002 |
Hot In Place Recycling, Intermediate Course | ||
7/18/2003 |
Asphalt Concrete with Fibers Designer Note: A This product can be selectively applied as an anti-rutting treatment according to the High Stress Guidelines Appendix B of the Pavement Design Manual. B Use this item just as any 448 item would be used in the Pavement Design Manual. C There are no special considerations beyond those described in the Pavement Design Manual. D No special maintenance of traffic considerations. |
||
4/17/2004 |
Temporary
Sediment and Erosion Control |
||
2/12/2003 |
OEPA Storm Water Pollution Prevention Plan Permit Designer Note: Final note to be used along with 832 |
||
12/6/2001 |
Seeding and Erosion Control
with Turf Reinforcing Mat |
||
3/9/1999 |
Liner
Pipe Designer Note: Must also list Supplemental Specification 937. |
||
5/6/1997 |
Gabions | ||
4/19/2002 |
Soluble Reactive Silicate (SRS) Concrete Treatment | ||
4/18/2003 |
Patching Concrete Structures with Trowelable Mortar | ||
845 |
|
Field Metalizing (Under Development) | |
10/15/2004 |
Treating
Concrete Bridge Decks with HMWM Resin Designer Note: Must also list Supplemental Specification 954 |
||
2/8/2002 |
Bridge
Deck Repair and Overlay with Concrete Using Scarification and Chipping Designer Note: This combines MSC and LMC overlays under the same Supplemental Specification - Must designate type of overlay and provide separate pay items for removal of existing Asphalt Overlay and/or Concrete Overlay. Must also list Supplemental Specification 954. Click Here |
||
2/8/2002 |
Bridge
Deck Repair and Overlay with Concrete Using Hydrodemolition Designer Note: This combines MSC and LMC overlays under same Supplemental Specification - Must designate type of overlay and provide separate pay items for removal of existing Asphalt Overlay and/or Concrete Overlay. Must also list Supplemental Specification 954. |
||
849 |
|
QC/QA Bridge Deck Repair and Overlay (Under development) Designer Note: To be developed |
|
4/19/2002 |
Diamond Grinding Portland Cement Concrete Pavement. Designer Note: Intended for use on existing concrete pavements in need of grinding; purpose is to eliminate joint and fault cracking, and restore proper ride |
||
4/19/2002 |
Ultra-Thin Whitetopping Overlay with Steel Fiber Reinforced Concrete Designer Note: For use on flexible pavements only, not composite. Not for use on mainline interstate and interstate lookalikes. Intended mainly for high stress locations as defined in the High Stress Guidelines, Pavement Design & Rehabilitation Manual, Appendix B. Requires a strong base - the asphalt must be in good condition. Locations with potholes or medium or high severity wheel track cracking are not candidates for ultra-thin whitetopping. Requires good edge support in the form of a concrete curb or concrete gutter or solid asphalt. Locations with edge cracking within about one foot of the edge of the overlay are not good candidates for ultra-thin whitetopping. A minimum of 6 inches of asphalt is required below the ultra-thin whitetopping. |
||
7/19/2002 |
Fine Graded Polymer Asphalt Concrete Designer Note: These products are intended to be used for pavement preventive maintenance but may have other applications as well. 1 Type A mix is a very fine graded mix composed of primarily natural sand and contains a very high binder content. It is designed to give a very long life but generally is not for high truck situations. 2 Do not crack seal within 1 year prior to applying Type A. 3 Apply Type A at 5/8 inch lift. B Type B mix is a fine graded mix composed of more angular materials and contains less binder content than type A. It is designed to be more rut resistant than Type A but still contains a polymer binder for durability and ease of maintenance. Type B can be placed on medium and high volume roads, including most interstate applications. 1 Do not crack seal within 1 year prior to applying Type B. Apply type B at 3/4 to 1 inch, in general. C No special maintenance of traffic considerations. D Include SS908 for asphaltic cement. |
||
10/18/2002 |
Stone Matrix Asphalt Concrete Designer Note: (1) Typically, do not use SMA for projects of less than 1 lane mile in continuous length of SMA surface course. (2) Design SMA with a minimum 38mm (1.5in) thickness. (3) Use pay item "Stone matrix asphalt concrete, 12.5mm, PG 76-22M, (446)" in accordance with Appendix B of the Pavement Design and Rehabilitation Manual. |
||
7/19/2002 |
Asphalt Concrete with Gilsonite Designer Note: This product can be selectively applied as an anti-rutting treatment according to the High Stress Guidelines Appendix B of the Pavement Design Manual. B This product can be used with 448 or 446 mixes per the Pavement Design Manual . C No special maintenance of traffic considerations. |
||
|
7/19/2002 |
Asphalt Concrete with Verglimit Designer Note: A This item is designed to assist with de-icing in certain temperature ranges and has usually been applied on bridge decks. B Due to the product nature it must be specified as a 446 and accepted per the specification requirements. C District 9 has the most experience with this product and may be of help with application and effectiveness questions. D Lift thickness is per the Pavement Design Manual. E No special maintenance of traffic considerations. |
|
7/11/2000 |
Sealing of Concrete Surfaces Designer Note: This new Supplemental Specification 864, Sealing of Concrete Surfaces, replaces existing Proposal Note 516-84 by October 1, 2001. Used whenever concrete surfaces, either existing or new, are to be sealed. The limits of sealing are to be shown in the plans. The designer is allowed the option of either specifying a specific type (not brand) of sealer or leaving the choice up to the Contractor. The designer should coordinate this with the owner of the structure. The designer should be aware that the Bridge Design Manual has specific guidance as to which types of sealers are to be used and where their use is acceptable. Questions regarding this note should be directed to the Office of Structural Engineering at 614-466-3893. |
||
7/19/2002 |
Embankment Construction Using Recycled Materials Designer Note: This note was written to safely use these recycled products without jeopardizing the embankment or pavement integrity or long-term performance. The Department does not require the use of recycled materials because this specification does not eliminate all risk or liability to the Department, it only minimizes such risks. For complete note Click Here |
||
872 | 10/30/2003 |
Light Emitting Diode Traffic Signal Lamp Units Designer Note: This supplemental specification 872 will be provided on all projects where LED signal heads are specified for State maintained traffic signals. It may be provided on other projects at the maintaining agency's discretion. |
|
873 | 10/30/2003 |
Wet Reflective Removable Tape Designer Note: This supplemental specification 873 will be provided on all projects where Wet Reflective Removable Tape is specified |
|
874 | 7/19/2002 |
Ultra Thin Bonded Asphalt Overlay Designer Note: A This product is intended to be used for pavement preventive maintenance but may have other applications as well. B This product uses a high angularity aggregate to provide rut resistance. The product is gap graded to allow for more top size stone contact and to provide a higher binder content for durability. The emulsion prior to hot mix application provides sealing of the old surface and adhesion of the 5/8 inch hot mix gap graded layer. C The pavement on which this process is applied should be in suitable condition with few significant defects. In general, following the guidance of the Preventive Maintenance policy for application will suffice. D Do not crack seal within 1 year prior to constructing this item. E No special maintenance of traffic considerations. F Requires inclusion of SS 902 for polymer emulsion. |
|
879 | QC/QA Embankment (under development) | ||
10/18/2002 |
Asphalt
Concrete with Warranty |
||
10/18/2002 |
Micro-Surfacing with Warranty | ||
10/18/2002 |
Chip Seal with Warranty Designer Note: No pay item changes. Add SS 902 when using. |
||
10/18/2002 |
Crack Sealing, Hot Applied with Warranty Designer Note: [1] In September 1999 Supplemental Specification 825 was updated to include warranty requirements. [2] In July 2000 the warranty requirements were removed from SS825 to facilitate adding these requirements to the new spec book.[3] At this time we are creating new Supplemental Specification 883, Crack Sealing, Hot Applied with Warranty. Conventional crack sealing projects should use the July 2000 version of SS825; crack sealing projects with warranty should use new SS883. [4] Continue to specify SS925 for the material requirements. |
||
4/18/2003 |
Concrete
Pavement with Warranty Designer Note: Must also list Supplemental Specification 812 and 813. |
||
4/18/2003 |
Hot
In-Place Recycling with Warranty Designer Note: Must also list Supplemental Specification 908. Defined hot in-place recycling; no pay item changes. |
||
1/3/2002 |
QC/QA Concrete Pavement |
||
7/16/2004 |
QC/QA Concrete for New Bridge Decks with Warranty | ||
10/18/2002 |
Class
S Concrete for New Bridge Decks with Warranty Designer Note: Must also list Supplemental Specification 848 and 846. |
||
10/18/2002 |
High Performance Concrete for New Bridge Decks with Warranty | ||
895 | 4/16/2004 | Manufactured Water Quality Structure | |
10/15/2004 |
QC/QA Concrete Pavement with Warranty | ||
7/16/2004 |
QC/QA Concrete for Structures Designer Note: For reference see 7/18/2003 notes |
||
7/18/2003 |
QC/QA Concrete for Structures
Designer Note: This
is a QC/QA specification for structure concrete. It contains performance requirements and pay factors based on
the test results reported by the contractor.
It was developed to replace Item 511, class C, S and HP concretes
in structures. Use class QSC1
for substructure concrete and QSC2 for superstructure components of the
bridge. See 898.02 for a
definition of which components of the bridge are considered substructure
and which are considered superstructure.
The design strengths and permeabilities are 4000 psi and 2000
coulombs respectively for QSC1; and 4500
psi and 1500 coulombs for
QSC2. |
||
NO. |
DATE |
DESCRIPTION - MATERIALS |
|
7/19/2002 |
Polymer Asphalt Emulsion Designer Note: Use with SS 882 or with Item 422 in 2002 CMS | ||
4/18/2003 |
Performance
Grade (PG) Binder Requirements Designer Note: Include this on ALL projects which contain asphalt concrete. |
||
4/19/2002 |
Hot Applied Crack Sealing Material | ||
6/14/1995 |
Self-Lubricating Bronze Bearing Plates | ||
3/9/1999 |
Polyethylene Liner Pipe | ||
6/14/1995 |
Latex for Concrete Modification | ||
9/9/1997 |
High Molecular Weight Methacrylate (HMWM) Resin | ||
10/30/2003 |
Portable Traffic Signals | ||
NO. |
DATE |
DESCRIPTION - Miscellaneous Requirements and Methods of Test |
|
4/19/2002 |
Approval and Testing of Air Entraining Agents and Chemical Admixtures for Concrete | ||
4/19/2002 |
Microfilm of Shop Drawings | ||
4/19/2002 |
High Voltage Direct Current Test Procedure | ||
4/19/2002 |
Method of Test for Sieve Analysis of Fine and Coarse Aggregates (AASHT0 Method T 27 Modified) | ||
4/12/2002 |
Sieve Analysis for all Materials in 304, 411, 603 Type 1 & 2 , and 617 | ||
8/14/1995 |
Plastic Limit Determination of Soil- Aggregate Materials for Use in Items 304, 310, 411, and 617 | ||
4/19/2002 |
Testing of Agricultural Liming Materials | ||
4/19/2002 |
Method of Test for Glass Beads (740.10 and Special Gradations) | ||
4/19/2002 |
Method of Test Weight of Coating on Zinc- Coated (Galvanized) or Aluminum-Coated Iron or Steel Articles | ||
1010 | |||
7/30/2004 |
ODOT Revision to AASHTO/AWS Bridge Welding Code D1.5-95 | ||
4/19/2002 |
Method of Test for Rubber Compound | ||
4/19/2002 |
Methods of Testing Asphalt Emulsions | ||
4/19/2002 |
Methods of Testing Cut-Back Asphalt Emulsions | ||
11/6/2001 |
Compaction of Unbound Materials | ||
4/19/2002 |
Method of Test for Loss of Ignition of Top Soil | ||
4/19/2002 |
Method of Test for Clay Lumps in Aggregate | ||
4/19/2002 |
Method of Testing Joint Sealants, Hot-Poured, for Concrete and Asphalt Pavements | ||
11/1/2001 |
Certification Procedure for Corrugated Metal Pipe |
||
1/17/2003 |
Driveable Flexible Delineator Post Prequalification Procedure | ||
4/19/2002 |
Method of Test for Determination of the Percent of Fractured Pieces in Gravel | ||
7/19/2002 | Certification Procedure for Agricultural Seed | ||
4/19/2002 |
Making and Testing Concrete Beams | ||
1024 | 11/7/2000 |
Method of Testing Coarse Aggregates to Determine Susceptibility to D-cracking |
|
4/19/2002 |
Method of Test for Deflection of Light Poles | ||
10/15/2004 |
Fly Ash Certification Procedure | ||
1/16/2004 |
Sulphur Leachate Test for Air Cooled Blast Furnace Slag for Acceptance of Items 203, 204, 304, 306, 307, 308, 503 and 603. | ||
10/15/2004 |
Cement Certification Procedure | ||
4/19/2002 |
Method of Test for Determining the Percentage of Deleterious Materials in Coarse Aggregate | ||
4/19/2002 |
Method of Test for Acid-Insoluble Residue in Fine Aggregate | ||
4/19/2002 |
Method of Test for Determining Specific Gravity and Percent Absorption for Coarse and Fine Aggregate | ||
4/19/2002 |
Bituminous Material Certification Procedure | ||
1033 | Using Hiperpave Software for Concrete Pavement (under development) | ||
1034 | GGBF Slag Certification (under development) | ||
4/19/2002 |
Field Sampling Asphalt Concrete | ||
4/16/2004 |
Method of Test for Determination of Percent Air Voids in Compacted Dense Bituminous Paving Mixtures | ||
4/19/2002 |
Method of Test for Determination of Percent Voids in the Mineral Aggregate (VMA) in Compacted Bituminous Paving Mixtures | ||
4/19/2002 |
Quantitative Extraction of Bitumen from Bituminous Paving Mixtures | ||
4/19/2002 |
Method of Test for Mechanical Analysis of Extracted Aggregate | ||
4/19/2002 |
Determination of Statistical Outliers | ||
10/15/2004 |
Bituminous Concrete Mix Design and Quality Control Program | ||
11/1/2001 |
606 Guardrail Certification Program | ||
4/19/2002 |
Calibration and Test Procedures for Use of Asphalt Concrete Nuclear Gauges | ||
1/11/2000 |
Mix Design Method for Bituminous Aggregate Base | ||
1045 | Micro-Silica Certification (under development) | ||
1/16/2004 |
Vehicular Signal Lamps Prequalification Procedure (732.041) | ||
3/10/2004 |
Pavement Marking Materials Field Service Testing Procedure | ||
4/19/2002 |
Loop Detector Sealant Prequalification Procedure | ||
1/17/2003 |
Reflective Sign Sheeting Prequalification Procedure (730.18, 730.19, 730.191, 730.192) | ||
1050 |
1/17/2003 |
Prequalification Procedure for Portable Traffic Signals | |
4/19/2002 |
Resistance of Compacted Bituminous Concrete to Moisture Induced Damage | ||
4/19/2002 |
Determination of Methylene Blue Adsorption Value of Mineral Aggregate Fillers and Fines | ||
4/19/2002 |
Storage and Introduction of Antistrip Additives into an Asphalt Concrete Plant | ||
4/19/2002 |
Test Method for Determination of Asphalt Content by the Ignition Method | ||
6/15/1999 |
Requirements for Producing A Polymer Modified Asphalt Concrete | ||
10/30/2003 |
Work Zone Raised Pavement Markers | ||
4/19/2002 |
Loaded Wheel Tester Asphalt Mix Rut Testing Method | ||
7/16/2004 |
Surface Smoothness Requirements | ||
4/18/2003 |
Asphalt Concrete Surface Course Warranty Requirements | ||
9/14/2001 |
Tank Car and Tank Truck Volume Calculations of Asphalt Materials from Net Weights | ||
4/19/2002 |
PCMS Pre-qualification Procedure | ||
4/18/2003 |
Testing Procedures for Raised Pavement Marker Materials | ||
4/19/2002 |
Signal Construction Personnel Requirements (631, 632, 633) | ||
4/19/2002 |
Procedures for Rigid Pavement Thickness Determination | ||
4/19/2002 |
Method of Test for Distillate Fuels | ||
10/18/2002 | Certification Procedure for Plastic Pipe | ||
11/1/2001 |
607 Fence Certification Program | ||
11/1/2001 |
Reinforcing Steel and Welded Wire Mesh Certification Program | ||
2/8/2002 |
Pre-qualified Aggregate Supplier Program | ||
4/19/2002 |
Quick Setting Concrete Mortar (705.21) Field Service Testing | ||
4/19/2002 |
Quality Control Requirements for Steel Slag Aggregate Producer/Processors | ||
11/1/2001 |
Certification Procedure for Pressure Treated Lumber | ||
10/18/2002 |
Precast Concrete Certification Program Designer Note: Requires certification of Precast box culverts, three-sided or Conspan units, manhole components, temporary barriers, etc. |
||
2/12/2003 | Concrete Pipe Certification Program | ||
4/19/2002 |
Load Deflection Test Procedures for U-Channel Sign Posts |
||
1/4/2002 |
Conflict Monitors for Use with Model 170E and 2070 Controllers/Cabinets |
||
1077 | (under development) | ||
1078 | 7/19/2002 | Qualification and Evaluation of Structural Steel Fabricators | |
1079 | 10/18/2002 | Qualification and Evaluation of Prestressed Concrete Fabricators | |
4/19/2002 |
Requirements for High Strength Steel Bolts, Nuts and Washers (711.09) | ||
7/10/1997 |
Testing and Acceptance of Plastic Supports for Reinforcing Steel | ||
4/16/2004 |
Recycled Raised Pavement Markers (RPMs) Authorization and Transfer Slip | ||
10/18/2002 |
Method of Acceptance of Graffiti Protection Coatings for Concrete | ||
10/18/2002 |
Bridge Paint Certification Requirements | ||
10/30/2003 |
Wet Reflective Removable Tape | ||
5/9/2003 |
Certification Procedure Non Standard Cementitious Replacement Materials | ||
10/30/2003 |
Work Zone Pavement Markings | ||
1088 |
Hot Applied Joint Sealer Acceptance Program (under development) | ||
3/10/2004 |
Traffic Markings Sampling Requirements | ||
1/10/2002 |
In Place Gradation Sampling | ||
1/16/2004 |
Certification Procedure For Fabricators of Light Poles and Light Towers | ||
1/16/2004 |
Certification Procedure For Fabricators of Signs | ||
1/16/2004 |
Certification Procedure For Fabricators of Sign Supports | ||
1/10/2004 |
Certification Procedure For Fabricators of Signal Supports and Strain Poles | ||
1095 |
Certification Procedure for Fabricators of Closed Circuit Television (CCTV) Poles (under development) | ||