Year: 2004

FRU-CON CONSTRUCTION CORPORATION
Year: 2004
District: 2
Project Number: 010493
PID Number: 20208
Specification Year: 1997
Dispute/Claim: D2.025
Dispute Resolution Forum: Dispute Review Board
Location: LUC - IR 280 - 2.96
Description: Discrepancy in Concrete Quantity for Precast Segmental Concrete
Issues: Discrepancy in quantity, Signif. change in scope/character of work, Notice
Decision/Recommendation: D2.025

SHELLY & SANDS INC
Year: 2004
District: 4
Project Number: 030406
PID Number: 23412
Specification Year: 2002
Dispute/Claim: 04-0406(03)-01
Dispute Resolution Forum: Deputy Director's Board
Location: POR - SR 303 - 2.73 (City of Streetsboro)
Description: Partial Depth Repairs
Issues: Signif. change in scope/character of work, Partial Depth Pavement Repair
Decision/Recommendation: 04-0406(03)-01

KOKOSING CONSTRUCTION COMPANY INC
Year: 2004
District: 5
Project Number: 020068
PID Number: 13281
Specification Year: 1997
Dispute/Claim: 05-0068(02)-01
Dispute Resolution Forum: Deputy Director's Board
Location: FAI - USR 33 - 0.41 (City of Springdale)
Description: Ameritech Utility Delay
Issues: Utility delay, CPM Progress Schedule, Non-responsiveness as approval/acceptance, Overhead (home/field office), Extra work, Notice, Delay - critical/non-critical, CPM calendar/logic changes
Decision/Recommendation: 05-0068(02)-01

KOKOSING CONSTRUCTION COMPANY INC
Year: 2004
District: 7
Project Number: 010560
PID Number: 18249
Specification Year: 1997
Dispute/Claim: 07-0560(01)-01
Dispute Resolution Forum: Deputy Director's Board
Location: MOT - IR 75-29.305
Description: Ameritech Utility Delay
Issues: Utility delay, Mitigation, Notice, CPM Progress Schedule
Decision/Recommendation: 07-0560(01)-01

BECDIR CONSTRUCTION COMPANY
Year: 2004
District: 10
Project Number: 020236
PID Number: 23900
Specification Year: 1997
Dispute/Claim: 10-0236(02)-01
Dispute Resolution Forum: Arbitration
Location: VIN - CR 38A - 0.36/Various
Description: Covered Bridges
Issues: Constructive acceleration, Mitigation, Precaution against damage, Act of God, Dispute Resolution Process, Claim after final change order, Inefficiency/Loss of productivity, Delay - owner caused
Decision/Recommendation: 10-0236(02)-01

SMITH & JOHNSON CONSTRUCTION CO
Year: 2004
District: 10
Project Number: 010246
PID Number: 18288
Specification Year: 1997
Dispute/Claim: 10-0246(01)-0402-02
Dispute Resolution Forum: Director's Claim Board
Location: ATH - USR 33 - 40.981
Description: Timber Value & Production Loss
Decision/Recommendation: 10-0246(01)-0402-02