Year: 2011

SHELLY & SANDS INC
Year: 2011
District: 6
Project Number: 080080
PID Number: 81190
Specification Year: 2005
Dispute/Claim: 06-080080-01
Dispute Resolution Forum: Director's Claim Board
Location: PIC - US-23-10.38 AND VARIOUS
Description: Railroad Delay
Issues: Burden of proof, Inefficiency/Loss of productivity, Railroad Conflict
Decision/Recommendation: 06-080080-01

COMPLETE GENERAL CONSTRUCTION COMPANY
Year: 2011
District: 6
Project Number: 101039
PID Number: 80721
Specification Year: 2008
Dispute/Claim: 06-101039-01
Dispute Resolution Forum: Director's Claim Board
Location: FRA - IR-270-37.04
Description: Method of Payment of Topsoil in a Median Planter
Issues: Method of Measurement, Burden of proof
Decision/Recommendation: 06-101039-01

R B JERGENS CONTRACTORS INC
Year: 2011
District: 7
Project Number: 091060
PID Number: 80236
Specification Year: 2008
Dispute/Claim: 07-091060-01
Dispute Resolution Forum: Director's Claim Board
Location: MOT - LR-SOUTH DIXIE-PHASE 2
Description: Delays - due to utility - due to ODOT delay in scheduling pre-con - due to poor subgrade
Issues: Delay - owner caused, Overhead (home/field office), Burden of proof, CPM Progress Schedule, Utility delay
Decision/Recommendation: 07-091060-01

GREAT LAKES CONSTRUCTION CO
Year: 2011
District: 12
Project Number: 080598
PID Number: 21272
Specification Year: 2005
Dispute/Claim: 12-080598-02
Dispute Resolution Forum: Director's Claim Board
Location: CUY - SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - PART 2
Description: Railroad Delay - Crane holding girder over live track
Issues: Burden of proof, Delay - critical/non-critical, Inefficiency/Loss of productivity, Railroad Conflict
Decision/Recommendation: 12-080598-02