Issue: Constructive acceleration

BECDIR CONSTRUCTION COMPANY
Year: 2004
District: 10
Project Number: 020236
PID Number: 23900
Specification Year: 1997
Dispute/Claim Number: 10-0236(02)-01
Dispute Resolution Forum: Arbitratio
Location: VIN - CR 38A - 0.36/Various
Description: Covered Bridges
Issues: Constructive acceleration, Mitigation, Precaution against damage, Act of God, Dispute Resolution Process, Claim after final change order, Inefficiency/Loss of productivity, Delay - owner caused,
Decision/Recommendation: 10-0236(02)-01

NATIONAL ENGINEERING & CONTRACTING COMPANY
Year: 2006
District: 6
Project Number: 040163
PID Number: 77003
Specification Year: 2002
Dispute/Claim Number: 06-040163-03
Dispute Resolution Forum: Dispute Re
Location: FRA - SR 161/IR 270-25.900/40.260-Part 1 & 2 (City of Columbus)
Description: Multiple Project Impacts
Issues: Inefficiency/Loss of productivity, Utility delay, Delay - owner caused, Constructive acceleration, Extra work, Change order release/waiver, Winter protection, Overhead (home/field office),
Decision/Recommendation: 06-040163-03

VELOTTA COMPANY
Year: 2005
District: 4
Project Number: 030534
PID Number: 21004
Specification Year: 2002
Dispute/Claim Number: 04-030534-01
Dispute Resolution Forum: Deputy Dir
Location: POR - IR 76 - 9.50
Description: Fabrication of Structural Steel Plate Girders
Issues: Constructive acceleration, Unjust enrichment, Equitable Adjustment, Early Completion Schedule, Mitigation, Duty to coordinate subs, Voluntary Acceleration,
Decision/Recommendation: 04-030534-01