Issue: Delay - owner caused

BECDIR CONSTRUCTION COMPANY
Year: 2004
District: 10
Project Number: 020236
PID Number: 23900
Specification Year: 1997
Dispute/Claim Number: 10-0236(02)-01
Dispute Resolution Forum: Arbitratio
Location: VIN - CR 38A - 0.36/Various
Description: Covered Bridges
Issues: Constructive acceleration, Mitigation, Precaution against damage, Act of God, Dispute Resolution Process, Claim after final change order, Inefficiency/Loss of productivity, Delay - owner caused,
Decision/Recommendation: 10-0236(02)-01

BURTON SCOT CONTRACTORS LLC
Year: 2012
District: 12
Project Number: 100186
PID Number: 80252
Specification Year: 2008
Dispute/Claim Number: 12-100186-01
Dispute Resolution Forum: Director's
Location: CUY - SR-43-6.18
Description: Home Office Overhead and Inefficiency
Issues: Changed contract condition, Inefficiency/Loss of productivity, Delay - owner caused, Notice, Signif. change in scope/character of work, Utility delay,
Decision/Recommendation: 12-100186-01

C J MAHAN CONSTRUCTION COMPANY LLC
Year: 2002
District: 9
Project Number: 010178
PID Number: 11858
Specification Year: 1997
Dispute/Claim Number: 09-0178(01)-01
Dispute Resolution Forum: Deputy Dir
Location: SCI - USR 23-0.00 (City of Portsmouth)
Description: Erection Engineering Delay and Cost
Issues: CPM Progress Schedule, Delay - owner caused, Errors and Omissions,
Decision/Recommendation: 09-0178(01)-01

KOKOSING CONSTRUCTION COMPANY INC
Year: 2009
District: 3
Project Number: 050343
PID Number: 14018
Specification Year: 2002
Dispute/Claim Number: 03-050343-02
Dispute Resolution Forum: Director's
Location: MED - IR 71-9.56
Description: Delay Costs due to Delay in VE response
Issues: CPM Progress Schedule, Change order policy, Delay - owner caused,
Decision/Recommendation: 03-050343-02

KOKOSING CONSTRUCTION COMPANY INC
Year: 2009
District: 6
Project Number: 040294
PID Number: 77118
Specification Year: 2002
Dispute/Claim Number: 06-040294-03
Dispute Resolution Forum: Director's
Location: CLA - IR 70-25.11/28.95/29.32/0.00 - Part 1, 2 & 3
Description: Contractor is seeking $223, 560 for home and field overhead for the winter of 2006/2007. This was a workday contract rather than a completion date contract.
Issues: Delay - owner caused, Overhead (home/field office),
Decision/Recommendation: 06-040294-03

KOKOSING CONSTRUCTION COMPANY INC
Year: 2009
District: 6
Project Number: 040294
PID Number: 77118
Specification Year: 2002
Dispute/Claim Number: 06-040294-04
Dispute Resolution Forum: Director's
Location: CLA - IR 70-25.11/28.95/29.32/0.00 - Part 1, 2 & 3
Description: This project was sold with no provision for a fuel price adjustment. In 2005 ODOT established a fuel price adjustment policy and allowed for such adjustments on ongoing projects and extended that until 2006. The Contractor is asking for the adjustment for work it did in 2007.
Issues: Delay - owner caused, Industry standard, Material escalation,
Decision/Recommendation: 06-040294-04

KOKOSING CONSTRUCTION COMPANY INC
Year: 2009
District: 6
Project Number: 040294
PID Number: 77118
Specification Year: 2002
Dispute/Claim Number: 06-040294-06
Dispute Resolution Forum: Director's
Location: CLA - IR 70-25.11/28.95/29.32/0.00 - Part 1, 2 & 3
Description: This project used a workday contract in lieu of a completion date contract. Parties agree to 45 days of extra work and 102 days of weather. Kokosing is seeking site rental costs for land leased for their portable plant ($8,727.12) and for labor escalation ($10,182.05) for extension of the contract into 2007.
Issues: Delay - owner caused, Material escalation,
Decision/Recommendation: 06-040294-06

KOKOSING CONSTRUCTION COMPANY INC
Year: 2008
District: 6
Project Number: 060264
PID Number: 77467
Specification Year: 2005
Dispute/Claim Number: 06-060264-03
Dispute Resolution Forum: Dispute Re
Location: FRA - USR 62-14.11 (Main Street)
Description: Transportation Delay Claim
Issues: Delay - owner caused, Means and methods, Past practice,
Decision/Recommendation: 06-060264-03

MAHAN/NATIONAL A JOINT VENTURE
Year: 2009
District: 10
Project Number: 020510
PID Number: 19714
Specification Year: 1997
Dispute/Claim Number: 10-020510-01
Dispute Resolution Forum: Director's
Location: MEG - USR 33-15.70 (Village of Pomeroy)
Description: P-T Air Testing Quantum Only
Issues: CPM calendar/logic changes, Delay - critical/non-critical, Delay - owner caused, Entitlement agreed/damages in dispute, Mutual Mistake,
Decision/Recommendation: 10-020510-01

NATIONAL ENGINEERING & CONTRACTING COMPANY
Year: 2006
District: 6
Project Number: 040163
PID Number: 77003
Specification Year: 2002
Dispute/Claim Number: 06-040163-03
Dispute Resolution Forum: Dispute Re
Location: FRA - SR 161/IR 270-25.900/40.260-Part 1 & 2 (City of Columbus)
Description: Multiple Project Impacts
Issues: Inefficiency/Loss of productivity, Utility delay, Delay - owner caused, Constructive acceleration, Extra work, Change order release/waiver, Winter protection, Overhead (home/field office),
Decision/Recommendation: 06-040163-03

NATIONAL ENGINEERING & CONTRACTING COMPANY
Year: 2010
District: 6
Project Number: 040163
PID Number: 77003
Specification Year: 2002
Dispute/Claim Number: 06-040163-07
Dispute Resolution Forum: Director's
Location: FRA - SR 161/IR 270-25.900/40.260-Part 1 & 2 (City of Columbus)
Description: Failure of 1500 mm pipe
Issues: Workmanlike construction, Defective specification, Delay - owner caused, Pipe removal,
Decision/Recommendation: 06-040163-07

R B JERGENS CONTRACTORS INC
Year: 2011
District: 7
Project Number: 091060
PID Number: 80236
Specification Year: 2008
Dispute/Claim Number: 07-091060-01
Dispute Resolution Forum: Director's
Location: MOT - LR-SOUTH DIXIE-PHASE 2
Description: Delays - due to utility - due to ODOT delay in scheduling pre-con - due to poor subgrade
Issues: Delay - owner caused, Overhead (home/field office), Burden of proof, CPM Progress Schedule, Utility delay,
Decision/Recommendation: 07-091060-01

RUHLIN COMPANY
Year: 2007
District: 3
Project Number: 040082
PID Number: 18631
Specification Year: 2002
Dispute/Claim Number: 03-040082-02
Dispute Resolution Forum: Director's
Location: WAY - USR 30/250-9.18/9.98 (City of Wooster)
Description: requesting return of liquidated damages, additional costs for MOT due to
Issues: Delay - owner caused, Duty to coordinate subs, Inefficiency/Loss of productivity,
Decision/Recommendation: 03-040082-02