 Division of Innovative Delivery - P3 Projects

 
 

 Division of Innovative Delivery - Reports (Non-Project Specific)

 
  
  
  
20130809_OpandMaint_Service_Delivery_Assessment-FINAL.PDFODOT Performance Based Operations and Maintenance - Service Delivery Analysis
  
082712_ODOT_Rest_Area_Study-Final Version.pdfODOT Rest Area/Service Plaza Study
  
AppendixH-Completed_Rest_Area_Surveys_I71Pt1.zipODOT Rest Area/Service Plaza Study-Appendix H-Completed Rest Area Surveys I71 Part 1
  
AppendixH-Completed_Rest_Area_Surveys_I71Pt2.zipODOT Rest Area/Service Plaza Study-Appendix H-Completed Rest Area Surveys I71 Part 2
  
AppendixH-Completed_Rest_Area_Surveys_US33.zipODOT Rest Area/Service Plaza Study-Appendix H-Completed Rest Area Surveys US33
  
Movable_Bridges_RFI_Final_081613.pdfRFI - Movable Bridges
  
Movable Bridges_RFI_Final_Addendum_1_Clean_08232013.pdfRFI - Movable Bridges - Final Addendum 1 - Clean
  
Movable_Bridges_RFI Final_Addendum1_Markup_08232013.pdfRFI - Movable Bridges RFI - Final Addendum1 Markup
  
 

 Division of Innovative Delivery - Tentative Schedule for P3 Projects

 

The Division of Innovative Delivery ​is actively working on several projects summarized below:

  • Innerbelt Bridge Construction Contract Group 2 - Demolition of the existing bridge and construction of eastbound bridge
    • Design Build
    • Procurement documents being developed
    • Final RFP release in April 2013
    • Technical and Financial Proposals received in August 2013
    • Successful Proposer selected in September 2013
  • Portsmouth Bypass – Greenfield 
    • Design Build Finance Operate and Maintain with Availability Payment
    • Value for Money Analysis completed in early 2013
    • RFQ release on June 7, 2013
    • SOQ Due Date on August 9, 2013
    • Shortlist release on September 6, 2013
    • Draft RFP released on January 8, 2014
    • Final RFP release in April 2014
    • Announced appparent Successful Proposer (Portsmouth Gateway Group) in September 2014
    • Awarded to Portsmouth Gateway Group in October 2014
    • Reached Commercial Close on December 5, 2014
  • Brent Spence Bridge – Bridge Reconstruction 
    • Design Build Finance Operate and Maintain with Tolling (Availability Payment)
    • Procurement schedule - To be determined
 