| 89397 | FHWA | 1 | Allen | LACRPC | LIMA | ALL BELLEFONTAINE/MARKET CORRID | REPLACE EXISTING PEDESTAL MOUNT SIGNALS WITH DECORATIVE MAST ARM MOUNT, REPLACEMENT OF EXISTING GALVANIZED STEEL LIGHT POLES/COBRA HEADS WITH DECORATIVE STREET LIGHTING AND LANDSCAPING | BELLEFOINTAINE AVENUE FROM KIBBY ST TO WOODLAWN AVENUE | Lighting | CO | $2,210,872.00 | | CO Air Quality Exempt | 1 | 2012stipID0001FDCO |
| 78999 | FHWA | 1 | Allen | LACRPC | ALLEN COUNTY ENGINEER | ALL CR 118-0.89 Elm Street | Rehabilitate bridge, Deck Replacement | ALL CR 118-0.89; Over the Ottawa River | Bridge Deck Replacement | CO | $1,520,200.00 | | CO Air Quality Exempt | 2 | 2012stipID0002FDCO |
| 90190 | FHWA | 1 | Allen | LACRPC | ALLEN COUNTY ENGINEER | ALL CR 88 LINCOLN HWY, PHASE 2 | CUT OUT AND FIX JOINTS, GRIND, AND PAVE 2 ASPHALT COURSES | CAIRO CORP TO BEAVERDAM CORP | Mill and Fill | CO | $1,250,000.00 | | CO Air Quality Exempt | 3 | 2012stipID0003FDCO |
| 90185 | FHWA | 1 | Allen | LACRPC | LIMA | ALL ELM STREET | STREET WIDENING AND RECONSTRUCTION W/2 TRAVEL LANES AND ONE PARKING LANE. WILL INCLUDE CURB AND GUTTER, SIDEWALKS AND RELATED DRAINAGE. | ELM STREET BETWEEN CABLE ROAD AND WOODLAWN AVENUE | Minor Widening | CO | $2,206,220.00 | | CO Air Quality Exempt | 4 | 2012stipID0004FDCO |
| 87556 | FHWA | 1 | Allen | LACRPC | LIMA (TCC) | ALL FY 2012 Reg Trans Plng | Lima Allen County Regional Planning Commission SFY 2012 Regional Transportation Planning Program Supplemental Funding | 0 | Planning & Research | SPR | $237,500.00 | | | 5 | 2012stipID0005FDSP |
| 87557 | FHWA | 1 | Allen | LACRPC | LIMA (TCC) | ALL FY 2013 Reg Trans Plng | Lima Allen County Regional Planning Commission Regional Transportation Planning Program SFY 2013 supplemental funding | 0 | Planning & Research | SPR | $237,500.00 | | | 6 | 2012stipID0006FDSP |
| 87558 | FHWA | 1 | Allen | LACRPC | LIMA (TCC) | ALL FY 2014 Reg Trans Plng | Lima Allen County Regional Planning Commission Regional Transportation Planning Program SFY 2014 supplemental funding | 0 | Planning & Research | SPR | $237,500.00 | | | 7 | 2012stipID0007FDSP |
| 76691 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL IR 75 5.53 | Major Rehab from Interstate Plan. IR75 reconstruction from MM 5.53 thru SR81 interchange. Geometrics to be corrected. Capacity needs analyzed. Interchanges & bridges will be reconstructed. Some work that had been covered under this PID is now covered | Allen County IR 075 5.53 to 10.00 | Major Rehabilitation | CO | $84,416,733.00 | | CO Air Quality Nonexempt | 8 | 2012stipID0008FDCO |
| 76691 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL IR 75 5.53 | Major Rehab from Interstate Plan. IR75 reconstruction from MM 5.53 thru SR81 interchange. Geometrics to be corrected. Capacity needs analyzed. Interchanges & bridges will be reconstructed. Some work that had been covered under this PID is now covered | Allen County IR 075 5.53 to 10.00 | Major Rehabilitation | RW | $5,365,763.60 | | CO Air Quality Nonexempt | 9 | 2012stipID0009FDRWUT |
| 89029 | FHWA | 1 | Allen | LACRPC | | ALL IR 75-0.21 | MAJOR REHAB FROM INTERSTATE PLAN. IR 75 RECONSTRUCTION FROM AUGLAIZE CO LINE THRU MM 5.53. GEOMETRICS TO BE CORRECTED. CAPACITY NEEDS ANALYZED. INTERCHANGES & BRIDGES WILL BE RECONSTRUCTED. | FROM AUGLAIZE CO LINE TO MM 5.53 | Major Rehabilitation | CO | $79,537,496.00 | | CO Air Quality Nonexempt | 10 | 2012stipID0010FDCO |
| 89029 | FHWA | 1 | Allen | LACRPC | | ALL IR 75-0.21 | MAJOR REHAB FROM INTERSTATE PLAN. IR 75 RECONSTRUCTION FROM AUGLAIZE CO LINE THRU MM 5.53. GEOMETRICS TO BE CORRECTED. CAPACITY NEEDS ANALYZED. INTERCHANGES & BRIDGES WILL BE RECONSTRUCTED. | FROM AUGLAIZE CO LINE TO MM 5.53 | Major Rehabilitation | RW | $6,521,000.00 | | CO Air Quality Nonexempt | 11 | 2012stipID0011FDACUT |
| 87965 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL IR 75-6.11/7.85 | REPLACE BRIDGES OVER IR 75 ON FOURTH STREET AND RESERVOIR ROAD | FOURTH STREET OVER IR 75 AND RESERVOIR ROAD OVER IR 75 | Bridge Replacement | CO | $7,928,636.00 | | CO Air Quality Exempt | 12 | 2012stipID0012FDCO |
| 90217 | FHWA | 1 | Allen | LACRPC | LIMA | ALL KIBBY STREET | 5000' OF COMBINATION STREET REHAB AND REPLACEMENT. PROFILE TO BE ADJUSTED IN SOME AREAS. INCLUDES CURB AND GUTTERS, SIDEWALK AND DRAINAGE WORK. BREADTH OF SIGNAL WORK TO BE DETERMINED. | SR 65 (Pine St) to the beginning of ODOT'S 88421 PROJECT | Minor Rehabilitation - Pavement Gnrl Sys | CO | $2,488,632.00 | | CO Air Quality Exempt | 13 | 2012stipID0013FDCO |
| 90948 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima Elizabeth/West Streets | Modify Elizabeth and West Streets to one-way, one lane operations between Elm Street and North Street. Implement "complete streets" features. Convert Elizabeth and West Streets to two-way operations south of Elm Street and north of North Street. (AKA | Both Elizabeth Street and West Street from Elm Street to Wayne Street. | Section Improvement | PE | $140,000.00 | | CO Air Quality Exempt | 14 | 2012stipID0014FDDD |
| 90948 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima Elizabeth/West Streets | Modify Elizabeth and West Streets to one-way, one lane operations between Elm Street and North Street. Implement "complete streets" features. Convert Elizabeth and West Streets to two-way operations south of Elm Street and north of North Street. (AKA | Both Elizabeth Street and West Street from Elm Street to Wayne Street. | Section Improvement | RW | $46,667.00 | | CO Air Quality Exempt | 15 | 2012stipID0015FDAC |
| 80441 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima RR Grade Separation | Study potential Grade separation of Indiana & Ohio Railroad between Bellefontaine Avenue and North Street. Then construct a grade separation at the chosen location. | Bellefontaine Ave. to North St. along the Indiana & Ohio Railway | Railroad Grade Separation | PE | $450,000.00 | | CO Air Quality Exempt | 16 | 2012stipID0016FDDD |
| 82576 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima Traffic Study | Study effectiveness of converting one way streets to two way streets, state routes thru City, and signal optimization. Construction will follow based on results. | City of Lima | Section Improvement | CO | $1,530,612.00 | | CO Air Quality Exempt | 17 | 2012stipID0017FDCO |
| 90949 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima Wayne/High Streets | Modify High Street to a one-way, one lane operation between Metcalf Street and Central Avenue. Implement "complete streets" features. Convert Wayne Street to a two-way operation between Jameson Avenue and Central Avenue. (AKA - Phase 3 of the ALL-Traff | High Street from Metcalf Street to Central Avenue AND Wayne Street from Jameson Avenue to Central Avenue. | Section Improvement | PE | $160,000.00 | | CO Air Quality Exempt | 18 | 2012stipID0018FDDD |
| 90949 | FHWA | 1 | Allen | LACRPC | LIMA | ALL Lima Wayne/High Streets | Modify High Street to a one-way, one lane operation between Metcalf Street and Central Avenue. Implement "complete streets" features. Convert Wayne Street to a two-way operation between Jameson Avenue and Central Avenue. (AKA - Phase 3 of the ALL-Traff | High Street from Metcalf Street to Central Avenue AND Wayne Street from Jameson Avenue to Central Avenue. | Section Improvement | RW | $46,667.00 | | CO Air Quality Exempt | 19 | 2012stipID0019FDAC |
| 87190 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 117 3.19 | GRIND AND RESURFACE WITH ASPHALT CONCRETE | FROM THE ECL OF SPENCERVILLE TO THE WCL OF LIMA | Resurfacing, Undivided System | CO | $1,631,552.00 | | CO Air Quality Exempt | 20 | 2012stipID0020FDCO |
| 75467 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 117/309 18.65/15.17 | Improve safety of corridor by designing and constructing recommendations made from Corridor study. Safety improvements include, but are not limited too; signal coordination, raised concrete curb median east of I-75 along SR309, driveway definition through | SR117, from 0.02 mile west of Roschman Ave. jct. to Greely Chapel Rd. jct.; SR309, from Willard St. to Devonshire Dr. | Section Improvement | CO | $4,358,000.00 | | CO Air Quality Exempt | 21 | 2012stipID0021FDCO |
| 75467 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 117/309 18.65/15.17 | Improve safety of corridor by designing and constructing recommendations made from Corridor study. Safety improvements include, but are not limited too; signal coordination, raised concrete curb median east of I-75 along SR309, driveway definition through | SR117, from 0.02 mile west of Roschman Ave. jct. to Greely Chapel Rd. jct.; SR309, from Willard St. to Devonshire Dr. | Section Improvement | RW | $675,000.00 | | CO Air Quality Exempt | 22 | 2012stipID0022FDACUT |
| 87135 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 309 0.00 | GRIND AND RESURFACE WITH ASPHALT CONCRETE | From US 30 to Pioneer Road in the Village of Elida. | Resurfacing, Undivided System | CO | $1,584,846.00 | | CO Air Quality Exempt | 23 | 2012stipID0023FDCO |
| 90849 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 309 7.17 | Widen roadway to meet design standards, improve drainage, install curb and gutter, and resurface with asphalt. | From Pioneer Road in Elida to 0.2 miles west of Eastown Road. | Mill and Fill | CO | $3,146,000.00 | | CO Air Quality Exempt | 24 | 2012stipID0024FDCO |
| 82036 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 65-0.00 | resurfacing of 2-lane pavements with asphalt concrete | On SR65 from Auglaize CL to the SCL of Lima | Resurfacing, Undivided System | CO | $780,411.00 | | CO Air Quality Exempt | 25 | 2012stipID0025FDCO |
| 88306 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 65-6.60 | REPLACE 3 CONCRETE BOX BEAMS THAT ARE SPALLED AND HAVE STEEL STRANDS RUSTED THROUGH | SR 65 BRIDGE OVER THE OTTAWA RIVER | Bridge Repair | CO | $695,745.00 | | CO Air Quality Exempt | 26 | 2012stipID0026STCO |
| 86634 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 81 18.10 | RESURFACE PAVEMENT WITH ASPHALT CONCRETE FROM SUGAR STREET TO IR75. ADD CURB, GUTTERS AND SIDEWALKS FROM SUGAR STREET INTERSECTION TO JUST WEST OF NUEBRECHT ROAD. | SUGAR STREET TO JUST WEST OF NUEBRECHT ROAD | Drainage Improvement | CO | $836,559.00 | | CO Air Quality Exempt | 27 | 2012stipID0027FDCO |
| 87189 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 81 3.31 | GRIND AND RESURFACE WITH ASPHALT CONCRETE | From eastern jct. with SR66 to the WCL of Lima. | Resurfacing, Undivided System | CO | $1,664,390.00 | | CO Air Quality Exempt | 28 | 2012stipID0028FDCO |
| 80492 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 81-19.05 | 2 LANE RESURFACING | FROM SR 81 & IR75 JUNCTION TO THE HARDIN COUNTY LINE | Resurfacing, Undivided System | CO | $1,783,191.00 | | CO Air Quality Exempt | 29 | 2012stipID0029FDCO |
| 88840 | FHWA | 1 | Allen | LACRPC | ODOT SPONSORING AGENCY | ALL SR 81/117/309- 15.72/13.86 | 2 LANE RESURFACING WITH ASPHALT CONCRETE | SR81 FROM SR309 TO JACKSON ST; SR117 FROM RJ COLEMAN RR OVERPASS TO ELM STREET; SR309 FROM ROBB AVENUE TO SR81 | Resurfacing, Undivided System | CO | $945,768.00 | | | 30 | 2012stipID0030FDCO |