d52012 Construction Season Highlights for ODOT District 5

 
rollover or click a project area for information on a location
Visit ODOT's District 5 Site for more details on these and other projects in this area.   District 3 LinkSR 16 at the Cedar St. & Buena Vista exits: Interchange/Intersection upgrade including signal installation and bridge deck replacements. One lane of traffic will be maintained in both eastbound & westbound directions, with intermittent ramp closures.  Construction will close the bike trail during the bridge deck replacement over Ohio Central Railroad/Bike Trail, the date for which will be announced. More info at: http://www.dot.state.oh.us/districts/D05/Production/Pages/SR-16---Buena-Vista---Cedar-Street.aspxGuernsey Co. I-70 Resurfacing and Bridge Overlays Four-lane resurfacing project with bridge overlays.  I-70 resurfacing between SR 723 and SR 285.  One lane of traffic will be maintained in both eastbound & westbound directions.​Bridge replacement and road widening.  Entrance and exit ramp closures will take place on alternating ramps for 14 - 21 day periods of time.  SR 158 will close at points north and south of the interchange to allow for widening and culvert replacement.  Traffic will be maintained from the interstate to businesses on the south side of the interchange at all times; however, traffic will be restricted to one lane southbound over I-70 during the first phase of construction.  Short duration closures will take place on I-70 during bridge demolition & construction activities.  Resurfacing of I-70 in the area of the interchange will be performed at night with one lane maintained in each direction at all times.District 11 LinkDistrict 10 LinkDistrict 6 Link
Project
Description
  
Ohio County
  
  
  
  
Project
Guernsey Co. I-70 Resurfacing and Bridge Overlays
Description

Four-lane resurfacing project with bridge overlays.  I-70 resurfacing between SR 723 and SR 285.  One lane of traffic will be maintained in both eastbound & westbound directions.​

RouteInterstate 70
Ohio CountyGuernsey
PID21494
Est. StartJune 2012
Est. EndNovember 2012
 
Project
SR 158/I-70 Interchange Upgrade
Description

Bridge replacement and road widening.  Entrance and exit ramp closures will take place on alternating ramps for 14 - 21 day periods of time.  SR 158 will close at points north and south of the interchange to allow for widening and culvert replacement.  Traffic will be maintained from the interstate to businesses on the south side of the interchange at all times; however, traffic will be restricted to one lane southbound over I-70 during the first phase of construction.  Short duration closures will take place on I-70 during bridge demolition & construction activities.  Resurfacing of I-70 in the area of the interchange will be performed at night with one lane maintained in each direction at all times.​

RouteState Route 158 and Interstate 70
Ohio CountyLicking
PID84700
Est. StartMay 2012
Est. EndOctober 2013
 
Project
Interchange/Intersection Upgrade, SR 16 at Cedar St. & Buena Vista
Description

SR 16 at the Cedar St. & Buena Vista exits: Interchange/Intersection upgrade including signal installation and bridge deck replacements. One lane of traffic will be maintained in both eastbound & westbound directions, with intermittent ramp closures.  Construction will close the bike trail during the bridge deck replacement over Ohio Central Railroad/Bike Trail, the date for which will be announced.
More info at: http://www.dot.state.oh.us/districts/
D05/Production/Pages/SR-16---Buena-Vista---Cedar-Street.aspx

RouteState Route 16
Ohio CountyLicking
PID82757 
Est. StartDecember 2011
Est. EndOctober 2013