d62012 Construction Season Highlights for ODOT District 6


rollover or click a project area for information on a location
Visit ODOT's District 6 Site for more details on these and other projects in this area. District 8 -  2011 Construction Highlights LinkDistrict 10 -  2011 Construction Highlights LinkDistrict 6 -  2011 Construction Highlights LinkU.S. 68/62 Resurfacing - Description:  Four-lane Resurfacing from northern corporation limit of Ripley to the 68/62 split near Red Oak. One lane of traffic maintained in each direction at all times. Route  U.S. Route 68 and U.S. Route 62. County:  Brown. PID:  75434. Est. Start:  April 2011. Est. End:  November 2011.U.S. 52 Resurfacing - Description:  Four-lane resurfacing from the Portsmouth/New Boston corporation limit to SR 522 at Wheelersburg. One lane of traffic maintained in each direction at all times. Route:  U.S. Route 52. County:  Scioto. PID:  80094.  Est. Start  March 2011. Est. End  November 2011.SR 220 Relocation and Extension - Description:  Relocate and extend SR 220 at its junction with Schuster Road at Zahn's Corner to SR 32. Traffic will continue to be maintained on existing routes and with the use of flaggers as needed. Route:  State Route 220. County:  Pike. PID:  81539. Est. Start  June 2011. Est. End  November 2011 District 3 LinkDistrict 1 LinkDistrict 9 LinkDistrict 5 LinkDistrict 7 LinkDistrict 8 LinkI-270 Southwest Side Reconstruction A major reconstruction project is underway on I-270 on the southwest side of Franklin County between US 62 and Roberts Road.  All ramps will remain open with two or three lanes (with contraflow crossovers) maintained in each direction. The speed limit through the work zone will be reduced to 55 mph so drivers should allow for extra time for their commute and remain alert since this is a seven mile construction zone.I-71/670 Columbus Crossroads - Phase I Two lanes maintained on I-71 and I-670 throughout the 1.7 mile construction zone. Access to the airport is not impacted. The reduced speed of 45 mph is strictly enforced. Any interstate closures are during overnights and weekends and prior notification is given.Morrow Co. I-71 Lane Addition and Pavement Replacement Full depth pavement replacement with addition of third lane in each direction from the Richland County line to approximately one mile south of SR 95 in Morrow County.  Two lanes of traffic will be maintained in each direction throughout construction.​
Project
Description
  
Ohio County
  
  
  
  
Project
I-270 Southwest Side Reconstruction
Description

A major reconstruction project is underway on I-270 on the southwest side of Franklin County between US 62 and Roberts Road.  All ramps will remain open with two or three lanes (with contraflow crossovers) maintained in each direction.

The speed limit through the work zone will be reduced to 55 mph so drivers should allow for extra time for their commute and remain alert since this is a seven mile construction zone. 
 
More details at: http://www.dot.state.oh.us/districts/D06/
projects/Pages/I-270-Reconstruction%20Southwest%20Side.aspx

RouteInterstate 270
Ohio CountyFranklin
PID76191
Est. StartOctober 2011
Est. EndNovember 2013
 
Project
Morrow Co. I-71 Lane Addition and Pavement Replacement
Description

Full depth pavement replacement with addition of third lane in each direction from the Richland County line to approximately one mile south of SR 95 in Morrow County.  Two lanes of traffic will be maintained in each direction throughout construction.

Project is located in ODOT District
​ 6, but is being administered through ODOT District 3

RouteInterstate 71
Ohio CountyMorrow
PID86916
Est. StartMarch 2012
Est. EndOctober 2013
 
Project
I-71/670 Columbus Crossroads - Phase I
Description

Two lanes maintained on I-71 and I-670 throughout the 1.7 mile construction zone. Access to the airport is not impacted. The reduced speed of 45 mph is strictly enforced. Any interstate closures are during overnights and weekends and prior notification is given.

More info at: http://www.ODOT71670.org

RouteInterstates 71/670
Ohio CountyFranklin
PID77369
Est. StartSeptember 2011
Est. EndNovember 2014