d12013 Construction Season Highlights for ODOT District 1

rollover or click a project area for information on a location
Visit ODOT's District 1 Site for more details on these and other projects in this area.  
 
 
ODOT District 6 2013 HighlightsODOT District 3 2013 HighlightsODOT District 7 2013 HighlightsODOT District 2 2013 HighlightsODOT District 2 2013 HighlightsReplacement of the Fourth St. and Reservoir Rd. bridges over I-75 is the first of three projects which will reconstruct I-75 from the Auglaize County line to just north of SR 81 through Allen County and the city of Lima. The project was largely completed last year but finish work will take place this season. Begin: February 2012 Complete: May 2013Interstate 75 from Fourth Street to SR 81, Allen County
Reconstruction of the existing two lanes of pavement, replacement of all mainline and overhead bridges and reconstruction of the interchanges at Fourth St., SR 81 and SR 309 is the second of three projects which will reconstruct I-75 from the Auglaize County line to SR 81 through Allen County and the city of Lima. Begin: March 2013 Complete: October 2015State Route 117/309, Allen County Safety upgrade project which includes installation of a raised curb median, construction of roadside curb and installation of drainage from the interchange with Interstate 75 to Bowman Rd. on the east side of Lima. Begin: March 2013 Complete: November 2015 
Project
Description
  
Ohio County
  
  
  
  
Project
Fourth St. and Reservoir Rd. Bridge Replacements over Interstate 75, Allen County
 
Description

Replacement of the Fourth St. and Reservoir Rd. bridges over I-75 is the first of three projects which will reconstruct I-75 from the Auglaize County line to just north of SR 81 through Allen County and the city of Lima. The project was largely completed last year but finish work will take place this season. Begin: February 2012 Complete: May 2013

More info at: http://www.dot.state.oh.us/
districts/D01/Pages/I75-Reconstruction.aspx

RouteInterstate 75
Ohio CountyAllen
PID87965
Est. StartFebruary 2012
Est. EndDecember 2012
 
Project
I-75 Reconstruction, Fourth Street to SR 81
 
Description

Reconstruction of the existing two lanes of pavement, replacement of all mainline and overhead bridges and reconstruction of the interchanges at Fourth St., SR 81 and SR 309 is the second of three projects which will reconstruct I-75 from the Auglaize County line to SR 81 through Allen County and the city of Lima.

More info at: http://www.dot.state.oh.us/
districts/D01/Pages/I75-Reconstruction.aspx

RouteInterstate 75
Ohio CountyAllen
PID76691
Est. StartMarch 2013
Est. EndOctober 2015
 
Project
State Route 117/309 @ I-75    
 
Description
Safety upgrade project which includes installation of a raised curb median, construction of roadside curb and installation of drainage from the interchange with Interstate 75 to Bowman Rd. on the east side of Lima.
 
RouteState Route 117/309
Ohio CountyAllen
PID75467
Est. StartMarch 2013
Est. End November 2015