d52013 Construction Season Highlights for ODOT District 5

rollover or click a project area for information on a location
Visit ODOT's District 5 Site for more details on these and other projects in this area.    District 3 2013 HighlightsDistrict 11 2013 HighlightsDistrict 10 2013 HighlightsDistrict 6 2013 HighlightsState Route 158/I-70, Licking County: Bridge replacement and road widening as part of interchange upgrade. The eastbound entrance and exit ramp closures will occur on alternating ramps for a maximum of 19 days, weather permitting. Short duration closures will occur on I-70 during specific project activities. SR 158 traffic will be maintained at all times. Resurfacing of I-70 in the area of the interchange will be performed at night with one lane maintained in each direction at all times. Begin: May 2012 Complete: October 2013 Interstate 70, Licking County: Replace bridge, just west of the village of Gratiot. Two lanes of traffic will be maintained at all times. Begin: June 2013 Complete: November 2013Interstate 70, Licking County: Reconfiguration of ramps at the I-70/SR 79 interchange. Work on I-70 and SR 79 will create various lane and ramp closures. Closure dates and detour information will be communicated by message boards and media releases. Begin: May 2013 Complete: September 2013Interstate 70, Licking County: Replace and widen existing structures on I-70 over Canal Rd., located two miles west of the SR 79 interchange. Two lanes of traffic will be maintained at all times, with the exception of intermittent lane restrictions. Canal Rd. will be closed for 30 days beginning in mid-March. The Park Trail, beneath the structures will be closed for a total of 10 weeks. Begin: March 2013 Complete: November 2014Interstate 70, Fairfield/Licking County: Bridge rehabilitation work will be permed at three separate locations on I-70 (Blacklick Trail, SR 256 and Palmer Road). Closure dates and detour information will be communicated by message boards and media releases. •	Blacklick Trail and  SR 256 One lane will be maintained in each direction, with work being performed on four separate weekends, closing I-70 from Friday at 7 p.m. to Monday at 4 a.m. Begin: June 2013 Complete: September 2013 Palmer Road One lane will be maintained in each direction, with work being performed on two separate weekends, closing I-70 from Friday at 7 p.m. to Monday at 4 a.m. Begin:  June 2013 Complete: September 2013
Project
Description
  
Ohio County
  
  
  
  
Project
SR 158/I-70 Interchange Upgrade
Description

Bridge replacement and road widening as part of interchange upgrade. The eastbound entrance and exit ramp closures will occur on alternating ramps for a maximum of 19 days, weather permitting. Short duration closures will occur on I-70 during specific project activities. SR 158 traffic will be maintained at all times. Resurfacing of I-70 in the area of the interchange will be performed at night with one lane maintained in each direction at all times.

RouteState Route 158 and Interstate 70
Ohio CountyLicking
PID84700
Est. StartMay 2012
Est. EndOctober 2013
 
Project
I-70 Bridge Rehabs
Description

Bridge rehabilitation work will be performed at three separate locations on I-70 (Blacklick Trail, SR 256 and Palmer Road). Closure dates and detour information will be communicated by message boards and media releases.

•    Blacklick Trail and  SR 256
One lane will be maintained in each direction, with work being performed on four separate weekends, closing I-70 from Friday at 7 p.m. to Monday at 4 a.m. 
     Palmer Road
One lane will be maintained in each direction, with work being performed on two separate weekends, closing I-70 from Friday at 7 p.m. to Monday at 4 a.m.
RouteInterstate 70
Ohio CountyFairfield, Licking
PID88957
Est. StartJune 2013
Est. EndSeptember 2013
 
Project
I-70 Resurfacing
Description

Resurfacing and associated work on the section of I-70 extending from the SR 513 interchange to the Belmont County line. Two lanes of traffic will be maintained in each direction from 2 p.m. to 6 p.m., Monday through Thursday, and 11 a.m. through 6 p.m., Friday through Sunday, for the duration of the project. Work requiring a lane closure will be performed outside of those hours.

RouteInterstate 70
Ohio CountyGuernsey
PID87595
Est. StartJune 2013
Est. EndNovember 2013
 
Project
I-70 Bridges at Canal Road
Description

Replace and widen existing structures on I-70 over Canal Rd., located two miles west of the SR 79 interchange. Two lanes of traffic will be maintained at all times, with the exception of intermittent lane restrictions. Canal Rd. will be closed for 30 days beginning in mid-March. The Park Trail, beneath the structures will be closed for a total of 10 weeks.

RouteInterstate 70
Ohio CountyLicking
PID85540
Est. StartMarch 2013
Est. EndNovember 2014
 
Project
I-70/SR 79 Interchange Reconfiguration
Description

Reconfiguration of ramps at the I-70/SR 79 interchange. Work on I-70 and SR 79 will create various lane and ramp closures. Closure dates and detour information will be communicated by message boards and media releases.

Route Interstate 70, Licking County
Ohio CountyLicking
PID84695
Est. StartMay 2013
Est. EndSeptember 2013
 
Project
I-70 Bridge Replacement
Description

Replace bridge, just west of the village of Gratiot. Two lanes of traffic will be maintained at all times.

RouteInterstate 70
Ohio CountyLicking
PID81253
Est. StartJune 2013
Est. EndNovember 2013