d92014 Construction Season Highlights for ODOT District 11

rollover or click a project area for information on a location
Visit ODOT's District 11 Site for more details on these and other projects in this area.    ODOT D-5 2014 HighlightsODOT D-3 2014 HighlightsODOT D-10 2014 HighlightsODOT D-4 2014 HighlightsInterstate 70 Bridge Replacement at State Route 9 Interchange: Rehabilitating the I-70 bridge over SR 9, lengthening the westbound I-70 on-ramp from SR 9, and replacing the bridge that carries I-70 over the National Road Bikeway and Chambers Run.Interstate 70 Pavement Rehabilitation and Resurfacing: Three miles of I-70 will be repaired and resurfaced from Bridgeport west. Work will include resurfacing, full depth repairs, guardrail, concrete median reconstruction, and pavement markings.County Route Bridge Repairs over Interstate 70: Two projects approximately five miles apart – CR 26 about a mile west of Exit 208 (SR 149) and CR 80 about a mile west of the SR 331 Exit.Interstate 70 Bridge Deck Replacement, Bridge Rehab, and Bridge Removal: Two projects including six structures – two located almost four miles west of SR 800 and just east of the Guernsey Co. line, and four located just east of SR 800 and Hendrysburg.State Route 7 Slide/Slope Repairs: Three projects within five miles – SR 7 has been reduced to one lane due to rock slides on both sides of Brilliant since 2011.Interstate 77 Bridge Removal over Abandoned Railroad: About one mile north of the CR 80 Exit in Dover Twp.State Route 39 (West High Ave.) Safety Improvement/Widening in New Philadelphia: Widening from the railroad tracks to 7th St.Interstate 77 Preventive Maintenance Resurfacing: About 3.5 miles both north and south of U.S. 36/Newcomerstown (Exit 65).
Project
Description
Ohio County
  
  
  
  
Project
Interstate 70 Bridge Replacement at State Route 9 Interchange
Description
Rehabilitating the I-70 bridge over SR 9, lengthening the westbound I-70 on-ramp from SR 9, and replacing the bridge that carries I-70 over the National Road Bikeway and Chambers Run
Ohio CountyBelmont
Est. Construction Cost$9.6 million
Est. StartMarch-2013
Est. EndAugust-2014
 
Project
Interstate 70 Pavement Rehabilitation and Resurfacing
Description
Three miles of I-70 will be repaired and resurfaced from Bridgeport west. Work will include resurfacing, full depth repairs, guardrail, concrete median reconstruction, and pavement markings.
Ohio CountyBelmont
Est. Construction Cost$5.9 million
Est. StartMarch-2014
Est. EndOctober-2014
 
Project
County Route Bridge Repairs over Interstate 70
Description
Two projects approximately five miles apart – CR 26 about a mile west of Exit 208 (SR 149) and CR 80 about a mile west of the SR 331 Exit.
Ohio CountyBelmont
Est. Construction Cost$2.5 million
Est. StartMarch-2014
Est. EndJuly-2014
 
Project
Interstate 70 Bridge Deck Replacement, Bridge Rehab, and Bridge Removal
Description
Two projects including six structures – two located almost four miles west of SR 800 and just east of the Guernsey Co. line, and four located just east of SR 800 and Hendrysburg.
Ohio CountyBelmont
Est. Construction Cost$8.6 million
Est. StartApril-2014
Est. EndOctober 2014/May 2016
 
Project
State Route 7 Slide/Slope Repairs
Description
Three projects within five miles – SR 7 has been reduced to one lane due to rock slides on both sides of Brilliant since 2011.
Ohio CountyJefferson
Est. Construction Cost$73 million
Est. StartSeptember-2012
Est. EndJuly-2016
 
Project
Interstate 77 Bridge Removal over Abandoned Railroad
Description
About one mile north of the CR 80 Exit in Dover Twp.
Ohio CountyTuscarawas
Est. Construction Cost$4.5 million
Est. StartJune-2014
Est. EndNovember-2015
 
Project
State Route 39 (West High Ave.) Safety Improvement/Widening in New Philadelphia
Description
Widening from the railroad tracks to 7th St.
Ohio CountyTuscarawas
Est. Construction Cost$2 million
Est. StartJune-2014
Est. EndJune-2015
 
Project
Interstate 77 Preventive Maintenance Resurfacing
Description
About 3.5 miles both north and south of U.S. 36/Newcomerstown (Exit 65).
Ohio CountyTuscarawas
Est. Construction Cost$1.7 million
Est. StartMay-2014
Est. EndJuly-2014