d82014 Construction Season Highlights for ODOT District 8

rollover or click a project area for information on a location
Visit ODOT's District 8 Site for more details on these and other projects in this area.  ODOT D6 2014 HighlightsODOT D9 2014 HighlightsODOT D7 2014 HighlightsInterstate 71/MLK interchange: Construction of new interchange at I-71 and Martin Luther King Drive  Interstate 275/State Route 32 Interchange Reconstruction: Reconstruction of I-275/SR 32 interchange to add lanes and eliminate access point conflicts to improve safety and traffic flow on SR 32 and the I-275/SR 32 and Eastgate Blvd. interchanges.Interstate 71/Fields Ertel Interchange Upgrade: Construction of a loop ramp to relieve congestion at the Fields Ertel/Montgomery-Mason intersection.Interstate 75/Mitchell Avenue Interchange Reconstruction: Reconstruction of 1.2 miles of I-75 including the replacement of structures over Clifton Avenue and Mitchell Avenue. Improvements to Mitchell Avenue and adjacent interchange.
Project
Description
Ohio County
  
  
  
  
Project
Interstate 71/MLK interchange
Description
Construction of new interchange at I-71 and Martin Luther King Drive. More info at: www.uptownaccessstudy.com
Ohio CountyHamilton
Est. Construction Cost$90 million
Est. StartJuly-2014
Est. EndJuly-2016
 
Project
Interstate 275/State Route 32 Interchange Reconstruction
Description
Reconstruction of I-275/SR 32 interchange to add lanes and eliminate access point conflicts to improve safety and traffic flow on SR 32 and the I-275/SR 32 and Eastgate Blvd. interchanges.  Click here for more info.
Ohio CountyClermont
Est. Construction Cost$31.9 million
Est. StartJuly-2013
Est. EndOctober-2015
 
Project
Interstate 71/Fields Ertel Interchange Upgrade
Description
Construction of a loop ramp to relieve congestion at the Fields Ertel/Montgomery-Mason intersection. Click here for more info.
Ohio CountyHamilton, Warren
Est. Construction Cost$7.4 million
Est. StartMarch-2014
Est. EndOctober-2015
 
Project
Interstate 75/Mitchell Avenue Interchange Reconstruction
Description
Reconstruction of 1.2 miles of I-75 including the replacement of structures over Clifton Avenue and Mitchell Avenue. Improvements to Mitchell Avenue and adjacent interchange. Click here for more info.
Ohio CountyHamilton
Est. Construction Cost$54.6 million
Est. StartJune-2011
Est. EndSeptember-2014