The following is a weekly report concerning construction and maintenance work on state highways within the Ohio Department of Transportation District 1 which includes the counties of Allen, Defiance, Hancock, Hardin, Paulding, Putnam, Van Wert and Wyandot. This report is issued each week beginning in April and continues through November.
For the latest in statewide construction visit www.ohgo.com. Please contact us at 419-999-6803 with any information needs.
 
Construction and Maintenance Projects
Week of October 12, 2015

*Note: No work will take place on Monday, October 12 due to the Columbus Day holiday*
 
Allen County
 
Ohio 117 within the village of Spencerville at Ohio 66 will be closed October 19 for two weeks for a waterline replacement. Traffic will be detoured onto Ohio 66 to Kolter Road to Monfort Road back to Ohio 117. Work is being performed by village of Spencerville.
 
Interstate 75 Reconstruction project For the most recent information concerning the Interstate 75 reconstruction project through Lima and Allen County please visit www.odotlima75.org.
 
Defiance County

Ohio 15 at the Tiffin River bridge, Defiance, will be one lane through the work for pavement repair. Work is being performed by the Defiance County ODOT maintenance garage.
 
U.S. 24 eastbound from Ohio 281 to the Henry County line will be one lane through the work zone three days during the week for pavement repair. Work is being performed by the Defiance County ODOT maintenance garage.
 
 
 
Hancock County
 
U.S. 224 from Trenton Avenue in Findlay to County Road 212 east of Findlay including Main Street is restricted at some locations for a resurfacing project. Work on Tiffin Avenue is nearly complete with some incidental finish work occurring which will require short-term lane closures. Work is also occurring on Main Street between Center Street and Trenton Avenue where paving work is nearing completion which will be followed by finish work. Work is expected to be completed within the next two weeks. Work is being performed by Bluffton Paving, Bluffton.
 
Interstate 75 northbound and southbound south of Findlay, from three miles south of the rest areas to the Interstate 75/Ohio 15 interchange is restricted to one lane in each direction for a joint repair and resurfacing project. Traffic both northbound and southbound is currently traveling in the driving lane. Work will continue through late fall. Work is being performed by Shelly Company, Findlay.
 
Ohio 15 from the Findlay airport to Ohio 37 eastbound and westbound is largely complete with some minor finish work remaining. The route is currently unrestricted but work to complete the project is expected to resume within a few weeks. Work is being performed by the Shelly Company, Findlay.
 
Interstate 75 in Wood and Hancock counties: Through 2016, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through November, from 8pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg to CR 99 in Hancock County. Through 2016, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg to CR 99 in Hancock County.  Project complete: October 2017. All work is weather permitting.
Special events . . .
  • Effective Monday, April 27, through December, Township Road 101 in Hancock County, between CR 220 and TR 142, will be closed for bridge work on I-75.
 
Hardin County
 
Ohio 235 north of Ada to the Hancock County line will be reduced to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Hardin County ODOT maintenance garage.
 
Ohio 309 at Ohio 235 south of Ada to the Allen County line will be reduced to one lane through the work zone for sealing of pavement cracks.  Work is being performed by the Hardin County ODOT maintenance garage.
 
Ohio 235 between Ohio 309 and the south corporation limit of Alger will be reduced to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Hardin County ODOT maintenance garage.
 
Ohio 31 south of Kenton, south of Ohio 292 between County Road 190 and County Road 200 closed September 14 for a culvert replacement. Due to a delay in material delivery, the project will continue through late October.
Traffic is detoured onto Ohio 292 and Ohio 47 back to Ohio 31. Work is being performed by Vernon Nagel, Inc., Napoleon.
·       Within this current closure area, work to repair the railroad crossing on Ohio 31 just north of County Road 175 south of Kenton will begin October 12 and will be completed in approximately two weeks. Traffic will utilize the same detour. Work is being performed by CSX Railroad.
 
 
Paulding County
 
Ohio 500 from Ohio 49 in Payne to the Indiana state line is undergoing pavement repair. The project will close the road according to the following schedule. Work is being performed by Gerken Paving, Napoleon:
·       Ohio 500 between Ohio 49 and County Road 21 closed September 30 for approximately one month. Access to residences is available from Township Road 39, Township Road 33 and Township Road 21.  All other traffic is detoured onto County Road 1, Ohio 613 and Ohio 49 back to Ohio 500.
·       In late October, the section of Ohio 500 between Township Road 21 and County Road 1 (Indiana state line) will be closed for approximately one month. Access to residences will be available from Township Road 21, County Road 11 and County Road 1. All other traffic will be detoured onto County Road 1, Ohio 613 and Ohio 49 back to Ohio 500.
·       ODOT is coordinating with local landowners regarding access to residences and farm fields during the project.

U.S. 127 between Garfield Avenue and Jackson Street in the village of Paulding closed April 13 for approximately eight months for a sewer separation project. Traffic is detoured onto Ohio 111, Ohio 637 and Ohio 114 back onto U.S. 127. Work is being performed by VTF Excavation, Celina.
 
Putnam County
 
Ohio 12 at the west edge of Columbus Grove closed October 7 for approximately five weeks for installation of sanitary sewer. Traffic detoured onto Ohio 65, U.S. 30 and Ohio 115 back to Ohio 12. Work is being performed by Underground Utilities, Inc.
 
Ohio 613 east of West Leipsic will be closed October 13 for approximately four days for culvert replacement at two locations. Traffic detoured onto Ohio 65, U.S. 224 and Ohio 235 back to Ohio 613. Work is being performed by the Putnam County ODOT maintenance garage.
 
Ohio 189 at the east edge of Ottoville closed May 27 for an unplanned culvert repair. The road is closed for an indefinite amount of time. Traffic is being detoured onto Ohio 190, Ohio 634 and U.S. 224 back to Ohio 189.
 
Van Wert County
 
Ohio 49 between U.S. 30 and U.S 224 will be reduced to one lane through the work zone for placement of berm stone. Work is being performed by the Van Wert County ODOT maintenance garage.
 
Wyandot County
 
U.S. 23 northbound just east of Ohio 67 at Upper Sandusky and southbound just south of Ohio 294 near Harpster will be restricted to one lane through the work zone for guardrail repair. The lane closures will occur on Tuesday of the week, generally from 8 a.m. to 2:30 p.m. Work is being performed by ODOT District 1 roadway services.
 
U.S. 23/30 northbound and southbound from south of Ohio 182 to just south of County Road 47 at Upper Sandusky is restricted at certain locations for finish work following a bridge repair and resurfacing project. Work is being performed by Kokosing Construction, Columbus.
 
 
·       As part of the project, bridge work on Ohio 53/Ohio 67 over U.S. 23 is nearing completion. No further long-term restrictions on Ohio 53/67 are anticipated.
 
###
 