Contact:
Rhonda Pees, public information officer, ODOT District 1
(419) 999-6803
 
Highway Construction
Week of July 3, 2017
 
The following is work scheduled to occur on state highways within the Ohio Department of Transportation District 1 which includes the counties of Allen, Defiance, Hancock, Hardin, Paulding, Putnam, Van Wert and Wyandot. The schedule of work is dependent upon weather conditions and, unless otherwise noted, work will take place during daytime hours.
**Note: No work will take place on the July 4 holiday**
For the latest in statewide construction visit www.ohgo.com.
 
Please contact us at 419-999-6803; rhonda.pees@dot.ohio.gov for information regarding highway construction in the area.
 
ALLEN COUNTY
 
Pavement repairs will reduce traffic to one lane through the work zone at the following locations. Work is being performed by the ODOT Allen County maintenance garage:
·        State Route 309 eastbound near the Hardin County line
·        State Route 81, both eastbound and westbound, from Dutch Hollow Road to the Van Wert County line.
 
Interstate 75, and also Bentley Road and Napoleon Road will be affected during bridge deck replacements on Napoleon Road over Interstate 75, Beaverdam, and Bentley Road over Interstate 75, Bluffton. Work is being performed by Eagle Bridge, Sidney. The following are upcoming impacts related to the project:
 
Napoleon Road
  • Napoleon Road bridge over I-75 closed May 22 for approximately four months
    • Traffic detoured onto Sugar Creek Road, Swaney Road and Lincoln Highway (state Route 696) back to Napoleon Road.
  • The northbound exit ramp from Interstate 75 to Napoleon Road closed May 30 for four months.
    • Traffic detoured north on Interstate 75, east on Lincoln Highway (state Route 696), south on Swaney Road and west on Sugar Creek Road back to Napoleon Road; or west onto Lincoln Highway (state Route 696) back to S. West Street in Beaverdam.
  • The entrance ramp to Interstate 75 southbound from Napoleon Road will remain open
  • Motorists traveling northbound on Interstate 75 wishing to access state Route 696 are advised to do so via exit 135 (state Route 696/U.S. 30) at Beaverdam. No access to state Route 696 from Interstate 75 northbound at the Napoleon Road exit will be available.
 
Bentley Road (exit 140)
·        Two bridges on Bentley Road at exit 140 (one over Interstate 75 and one over the railroad north of Interstate 75) closed June 5 for approximately four months.
·        Both the southbound entrance and exit ramps at Bentley Road also closed on June 5 for four months.
o   Interstate 75 northbound traffic will be detoured to the state Route 103 (exit 142) interchange back to Bentley Road.
o   Interstate 75 southbound traffic is advised to access Bentley Road via the state Route 103 interchange (exit 142) and follow state Route 103 through Bluffton back to Bentley Road.
·        The northbound ramps at the interchange remain open; however, left turns onto Bentley Road from northbound Interstate 75 are not permitted.
Interstate 75
·        Interstate 75 both northbound and southbound will be periodically reduced to one lane at times beneath both the Napoleon Road and Bentley Road bridge structures during certain operations related to construction.
·        Lane closures will occur sporadically and are expected to occur mostly during daytime hours but some nighttime closures may occur.
 
DEFIANCE COUNTY

U.S. 24 westbound at Baltimore Street, Defiance, is restricted to one lane through the work zone through early September for repair of the roadside slope. Work is being performed by Miller Brothers, Archbold. The following upcoming closure is related to the project:
·        The entrance ramp from Baltimore Street to westbound U.S. 24 will be closed for the day on Monday, July 10 to allow for pavement markings and barrier wall to be placed for maintenance of traffic through the work zone. Traffic will be detoured to county Road 424 (old U.S 24) to U.S. 127 back to U.S. 24.
 
State Route 66 between Bowman and Watson roads, south of Defiance, closed June 5 for approximately three months for a bridge deck replacement. Traffic detoured onto state Route 613, state Route 634, state Route 15 and Carter Road back to state Route 66. Work is being performed by Vernon Nagel Inc., Napoleon.
 
U.S. 127 between state Route 18 and township Road 34, south of Sherwood, closed April 24 for 60 days for culvert replacement at two locations. Traffic detoured onto U.S. 24, state Route 15 and state Route 18 back to U.S. 127. Work is being performed by VTF Construction, Celina. http://www.dot.state.oh.us/districts/D01/detours/Documents/DEF-127-2.11_2.67.pdf
HANCOCK COUNTY
For information concerning the Interstate 75 reconstruction and widening project through Findlay and Hancock County, visit the website:

http://www.dot.state.oh.us/districts/D01/PlanningPrograms/Projects/hancock75/Pages/Hancock-75.aspx
State Route 613/state Route 18 between Van Buren and Fostoria will be reduced to one lane through the work zone for removal of pavement reflectors in preparation for tarring and chipping of the highway. Work is being performed by the ODOT Hancock County maintenance garage.
 
Resurfacing of the following routes within the city of Findlay will restrict traffic to one lane through the work zone. Work is being performed by M&B Asphalt, Old Fort.
·        U.S. 224 from Broad Street to Main Street
·        State Route 12 from Interstate 75 to Main Street (section between Western Avenue and Glessner Street is now open; project administered by the city of Findlay).
·        State Route 37 from Lincoln Avenue to Blanchard Avenue
·        State Route 568 from Main Street to Beech Avenue
 
U.S. 68 from the Findlay airport to Eagle Creek, south of Findlay, will have daily lane closures in both directions beginning early August for installation of cable barrier in the median. Once work begins it is expected to be completed in approximately eight weeks. Work is being performed by Lake Erie Construction, Norwalk.
 
U.S. 224 just west of state Route 235, west of Findlay, is scheduled to close July 17 for approximately 30 days for a culvert replacement. Traffic will be detoured onto U.S. 224, state Route 235, state Route 12 and state Route 65 back to U.S. 224. Work is being performed by BCC Ohio, New London.
 
U.S. 68 southbound exit ramp to U.S. 68 southbound over Eagle Creek at state Route 15, south of Findlay, closed May 15 for approximately two months for bridge repair. Traffic detoured onto state Route 15 eastbound to the state Route 37 interchange to state Route 15 westbound back to U.S. 68. Work is being performed by Global Outdoor Solutions, Cleveland.
 
State Route 12/state Route 235 overlap between state Route 235 and township Road 57 is now open following a bridge deck repair.
 
HARDIN COUNTY
 
State Route 31 closure between township Road 265 and state Route 273 has been delayed until late summer. Work will begin once a project on state Route 195 south of McGuffey has been completed.
 
When active, the project will close the route for 60 days for bridge repair at two locations: one over Painter Creek just south of township Road 206, the second over Wolf Creek north of township Road 265. Traffic detoured onto state Route 292 and state Route 273 back to state Route 31. Work is being performed by Crossroads Construction, Cambridge.
 
State Route 195 over Cottonwood Ditch, south of McGuffey, between the north and south jog of Cottonwood Road, closed June 5 for 60 days for bridge repair. Traffic detoured onto county Road 110, state Route 235 and state Route 309 back to state Route 195 Work is being performed by Crossroads Construction, Cambridge.
 
State Route 81 at township Road 55, east of Ada, will be restricted to one lane through the work zone for drainage tile repair. Work is being performed by the ODOT Hardin County maintenance garage.
 
PAULDING COUNTY
 
State Route 637 in the village of Grover Hill closed June 5 for three months for road reconstruction. Traffic detoured onto U.S. 224, U.S. 127 and state Route 613 back to state Route 637. Work is being performed by Brenneman Excavating Inc. for the village of Grover Hill.
 
State Route 66 from U.S. 224 in Putnam County to the Defiance County line will be restricted to one lane through the work zone for the tarring and chipping of the roadway. Work is being performed by the ODOT Paulding County maintenance garage.
 
PUTNAM COUNTY
 
The following locations will be restricted to one lane through the work zone for placement of berm stone. Work is being performed by the ODOT Putnam County maintenance garage:
·        State Route 613 between the Paulding County line and Continental
·        State Route 613 between Leipsic and the Hancock County line
 
VAN WERT COUNTY
 
State Route 637 closure between Feasby Wisener Road and Elm Sugar Grove Church Road has been delayed indefinitely due to flooding and will be rescheduled.
http://www.dot.state.oh.us/districts/D01/detours/Documents/VAN-637-2.35.pdf
 
U.S. 30 from just east of township Road 127 to just east of county Road 185 restricted to one lane through the work zone for pavement and joint repair and drainage improvements. Resurfacing of the pavement will follow the repair work. Work is being performed by Shelly Company, Findlay.
 
WYANDOT COUNTY
 
The following locations will be reduced to one lane through the work zone for pavement repair. Work is being performed by the ODOT Wyandot County maintenance garage:
·        State Route 231 from just north of county Highway 330 to state Route 103
·        State Route 293 from state Route 53 to Wharton
 
State Route 53 between Upper Sandusky and state Route 37, Forest, is restricted to one lane through the work zone for resurfacing. Work is being performed by Kokosing Construction Co., Columbus.
 
U.S. 23 and state Route 15 near their interchange with state Route 103, south of Carey, reduced to one lane in each direction for work related to the removal of two bridge structures over abandoned railroads. Work is being performed by Miller Brothers Construction Inc., Archbold. The following are traffic impacts related to the project:
  • All traffic has been shifted to the east side of the road and is reduced to one lane in each direction between county Highway 97 and county Highway 95 for the removal of structures on the U.S. 23 southbound, state Route 15 eastbound lanes. Traffic will remain in this pattern for approximately two months. All ramps at state Route 103 will remain open during this phase.
  • The project also includes the upcoming resurfacing of U.S. 23 from just north of county Highway 97 to the state Route 103 interchange and of the ramps at state Route 103.
State Route 53 between state Route 103 and county Road 2, McCutchenville, closed April 24 for approximately six months for bridge replacements over Thorn Run and Tymochtee Creek. Traffic detoured onto state Route 103, state Route 231 and U.S. 224 back to state Route 53. Work is being performed by R & I Construction, Tiffin. http://www.dot.state.oh.us/districts/D01/detours/Documents/WYA-53-21.85_24.16.pdf