Highway Construction
Week of September 19, 2016

The following is work scheduled to occur in the coming week on state highways within the Ohio Department of Transportation District 1 which includes the counties of Allen, Defiance, Hancock, Hardin, Paulding, Putnam, Van Wert and Wyandot. For the latest in statewide construction visit www.ohgo.com.
 
Please contact us at 419-999-6803; rhonda.pees@dot.ohio.gov for information regarding highway construction in the area.
 
Allen County
 
Interstate 75 from the Auglaize County line to Fourth Street, through Lima and Allen County, will have occasional lane closures throughout the year during the final year of the reconstruction of the interstate. Current and upcoming impacts to traffic are as follows:

  • Nighttime paving of the final course of asphalt, berm work and striping throughout the entire project area began August 22 and will continue until mid September.
    • Lane restrictions both northbound and southbound will occur from 7 p.m. to 2 p.m. each day.
    • Construction trucks will be entering and exiting frequently throughout the project area during the next several weeks.
    • Posted speed through the work zone will be lowered while work is taking place.
    • Paving will occur this weekend, perhaps both Saturday and Sunday, September 17 and 18, in the southbound direction.

  • Southbound interchange ramps at Ohio 65 and Breese Road will be closed briefly during nighttime hours in the next few days while the paving operation takes place.

  • Yoder Road near the Orthopedic Institute of Ohio (OIO) will close Monday, September 19 for one week for a railroad crossing repair. The OIO facility will be accessible from Yoder Road off of Ohio 65 but will not be accessible from Breese Road during the closure.

  • Traffic patterns on Ohio 65 beneath Interstate 75 will continue to shift for the next few weeks during completion of the concrete pavement.

 
 

Additional Allen County projects:
 
Interstate 75 both northbound and southbound between Ohio 81 to south of Beaverdam will be restricted to one lane through the work zone for pavement repair. Work is being performed by the ODOT Allen County maintenance garage.
 
Ohio 309 (Elida Road) from Eastown Road to U.S. 30, including the village of Elida, is restricted for widening, curb and gutter installation, drainage improvements and resurfacing. The project will continue through the fall. Work is being performed by VTF Excavation LLC, Celina.
 
The following impacts are occurring or upcoming. Traffic patterns will change frequently:
 
o   Paving from Elida to U.S. 30, Delphos, is complete. Pavement striping will continue during the week.
o   Ohio 309 from Greenlawn Avenue to Diller/Baty Road is maintained with two lanes westbound and one eastbound. The turn lane is maintained as well.
§  Traffic is reduced to one lane in each direction at various locations through this area for drainage installation. The restrictions will be in place from 7 a.m. to 2 p.m. each day. Traffic delays should be expected.
§  Traffic patterns will change frequently through this section.
§  Traffic will be reduced to one lane eastbound and one lane westbound between Eastown Road and Diller Road for drainage installation. The turn lane in this area will be available.
 
Ohio 117 and Ohio 501 (Wapak Road) intersection realignment and widening project and construction of left-turn lanes on Ohio 117 began June 30. Work is being performed by Bluffton Paving, Bluffton. The following impacts to traffic are occurring or upcoming:
·       Wapak Road at the intersection of Ohio 117 is now open.
  • Ohio 501 (Wapak Road) south of Ohio 117 is now open.
  • Daytime lane closures are occurring on Ohio 117 for roadway widening work. Traffic is maintained.
 
Defiance County
 
Arrowsmith Road on the east side of Ohio 49 will be closed for approximately two days beginning September 19 for a culvert replacement. Ohio 49 will remain open. Work is being performed by the ODOT Defiance County maintenance garage.
 
U.S. 24 over Krouse Road reduced to one lane through the work zone beginning August 31 for a slope and shoulder repair project. The project will continue until late fall. Work is being performed by Vernon Nagel Construction, Napoleon.
 
U.S. 24 throughout Defiance and Paulding County is restricted both eastbound and westbound at various locations throughout the corridor during repair of the concrete pavement. The project will require ramp closures at the interchanges. Work will continue through late summer. Work is being performed by Kokosing Construction, Columbus.
 
Upcoming closures related to the project are currently scheduled as follows:

·       U.S. 127 over U.S. 24 near Cecil is now open.

·       U.S. 127 from the interchange at U.S. 24 to a few hundred feet to the south is now open.

·       Ramp closures at the following locations have been completed:
o   Ohio 15/18 entrance ramp to eastbound U.S. 24, U.S. 24 westbound exit ramp to Ohio 15/18
o   U.S. 24 eastbound exit ramp to Baltimore Street (County Road 424)

·       U.S. 127 from the interchange at U.S. 24 to a few hundred feet to the north is now open.

·       The Ohio 66 entrance ramp to westbound U.S. 24 and the U.S. 24 eastbound exit ramp to Ohio 66 are now open.

·       Weekend ramp closures at the following locations which were scheduled to begin Friday, September 16 have been postponed. Tentative date of closure is now September 30.:
o   Ohio 281 (Domersville Road) entrance ramp to U.S. 24 westbound
§  Traffic detoured to Elliott Road to the Ohio 66 interchange back to U.S. 24
o   U.S. 24 eastbound exit ramp to Ohio 281 (Domersville Road)
§  Traffic detoured to the U.S. 6 interchange and back
o   U.S. 24 westbound exit ramp to U.S. 127
o   Entrance ramp from U.S. 127 to eastbound U.S. 24

·       Weekend ramps closures at the following locations were delayed due to weather and will now begin Friday, September 21 at 6 p.m. and continue until Monday, September 26 at 6 a.m.:
o   U.S. 24 eastbound exit ramp to Ohio 15/18, Ohio 15/18 entrance ramp to westbound U.S. 24
§  Traffic will be detoured onto U.S. 24 to the Ohio 66 interchange.
o   Ohio 66 entrance ramp to eastbound U.S. 24, westbound U.S. 24 exit ramp to Ohio 66.
§  Traffic will be detoured onto U.S. 24 to the Ohio 15/18 interchange and back.
Hancock County
Ohio 12 eastbound (Fostoria Avenue) from Tiffin Avenue to Bright Road, Findlay, will be closed during daytime hours only, 7 a.m. to 6 p.m., beginning September 6 for installation of a storm sewer line. The project will continue for approximately two months. The project is being administered by the city of Findlay.
Ohio 12 from Findlay to Arcadia, and from the southwest side of Fostoria to the Seneca County line reduced to one lane through the work zone for a resurfacing project which began September 6. The project will continue for two months. Work is being performed by M&B Ashpalt, Old Fort.
The following restrictions related to the project are scheduled to begin during the week:
·       Ohio 12 through the village of Arcadia may be restricted at times through the work zone during installation of curbs, sidewalk and handicap ramps.
·       Ohio 12 through Fostoria will be reduced to one lane in each direction for pavement joint repair followed by pavement resurfacing.
 
Interstate 75 from just south of Ohio 235 north of Bluffton to just south of the County Road 60 overhead near Rawson is reduced to one lane, both northbound and southbound, for a joint repair and resurfacing project. The project will continue until late October. Work is being performed by Shelly Co., Findlay.
 
The following closures are related to the project:
·       Interstate 75 northbound exit ramp to Ohio 235 closed September 15 for two days for pavement joint repairs on the ramp. Traffic detoured onto Ohio 103 at the Interstate 75 interchange back to Ohio 235.
·       Entrance ramp from Ohio 235 to northbound Interstate 75 closed September 15 for two days for pavement joint repair. Traffic detoured onto Ohio 235 north, Interstate 75 southbound to the Ohio 103 interchange back to Interstate 75 northbound.
·       Interstate 75 southbound exit ramp to Ohio 235 will close September 20 for two days for pavement joint repairs on the ramp. Traffic detoured onto Interstate 75 southbound to the Ohio 103 interchange, Interstate 75 northbound back to Ohio 235.
·       Entrance ramp from Ohio 235 to southbound Interstate 75 will close September 20 for two days for pavement repairs on the ramp. Traffic detoured south on Ohio 235 to the Ohio 103 interchange back to Interstate 75 southbound.
·       The southbound rest area closed September 6 for 10 days and is expected to reopen on September 15.
·       The northbound rest area closed September 8 for 10 days and is expected to reopen before the beginning of the week.
 
Interstate 75 between Perrysburg and County Road 99 north of Findlay will have the following restrictions through the fall during reconstruction and widening:
 
·       Through November, overnight lane restrictions, generally from 7 p.m. until 6 a.m., are possible on I-75 between the I-75/I-475 interchange in Perrysburg and County Road 99 in Hancock County. Through December, 11-foot lane width restrictions are in place on I-75 between U.S. 20 in Perrysburg and County Road 99 in Hancock County. 

·       Through December, Township Road 101 in Hancock County, between County Road 220 and Township Road 142, is closed for bridge work over I-75. 
 
Hardin County

Ohio 31 at Letson Avenue at the south end of the city of Kenton closed September 12 for 45 days for an intersection and sewer upgrade project. Traffic detoured onto U.S. 68, Ohio 273, Ohio 292 and Ohio 47 back to Ohio 31. Work is being performed by the Shelly Company, Findlay, for the city of Kenton.
 
Paulding County
 
Pavement repair will take place at the following locations with traffic maintained through the work zone. Work is being performed by the ODOT Paulding County maintenance garage:
-Ohio 49 between Township Road 60 and County Road 204
-Ohio 114 between the Indiana line and Ohio 49
-Ohio 613 in the village of Payne
 
Safe Routes to School project which includes construction of a sidewalk along the north side of Canal Road between Kroos Drive and Harrmann Road, and also along the west side of Harrmann Road between Canal Road and the entrance to the Antwerp School will begin September 19. The project also includes new curbs, curb ramps, signage and crosswalk markings. The project is not expected to have a significant impact to traffic. The project will continue until late October. Work on the project is being performed by Vernon Nagel Construction, Napoleon.
 
U.S. 127 from Jackson Street to Garfield Avenue, and Ohio 111 from Cherry Street to U.S. 127 in the village of Paulding will be restricted for a resurfacing project beginning in late September. Once under way the project will continue until late October. Work is being performed by Gerken Paving, Napoleon.

U.S. 24 throughout Defiance and Paulding County is restricted both eastbound and westbound at various locations throughout the corridor during repair of the concrete pavement. The project will require ramp closures at the interchanges. Work will continue through late summer. Work is being performed by Kokosing Construction, Columbus.
 
Upcoming closures related to the project are currently scheduled as follows:

·       U.S. 127 over U.S. 24 near Cecil is now open.

·       U.S. 127 from the interchange at U.S. 24 to a few hundred feet to the south is now open.

·       Ramp closures at the following locations have been completed:
o   Ohio 15/18 entrance ramp to eastbound U.S. 24, U.S. 24 westbound exit ramp to Ohio 15/18
o   U.S. 24 eastbound exit ramp to Baltimore Street (County Road 424)

·       U.S. 127 from the interchange at U.S. 24 to a few hundred feet to the north is now open.

·       The Ohio 66 entrance ramp to westbound U.S. 24 and the U.S. 24 eastbound exit ramp to Ohio 66 are now open.

·       Weekend ramp closures at the following locations which were scheduled to begin Friday, September 16 have been postponed. Tentative date of closure is now September 30.:
o   Ohio 281 (Domersville Road) entrance ramp to U.S. 24 westbound
§  Traffic detoured to Elliott Road to the Ohio 66 interchange back to U.S. 24
o   U.S. 24 eastbound exit ramp to Ohio 281 (Domersville Road)
§  Traffic detoured to the U.S. 6 interchange and back
o   U.S. 24 westbound exit ramp to U.S. 127
o   Entrance ramp from U.S. 127 to eastbound U.S. 24

·       Weekend ramps closures at the following locations were delayed due to weather and will now begin Friday, September 21 at 6 p.m. and continue until Monday, September 26 at 6 a.m.:
o   U.S. 24 eastbound exit ramp to Ohio 15/18, Ohio 15/18 entrance ramp to westbound U.S. 24
§  Traffic will be detoured onto U.S. 24 to the Ohio 66 interchange.
o   Ohio 66 entrance ramp to eastbound U.S. 24, westbound U.S. 24 exit ramp to Ohio 66.
§  Traffic will be detoured onto U.S. 24 to the Ohio 15/18 interchange and back.
Putnam County

Ohio 15 between the village of Ottawa and the Defiance County line, and Ohio 634 between the village of Continental and Ohio 15 is restricted to one lane through the work zone for a resurfacing project. The project will continue through mid October. Work is being performed by Gerken Paving, Napoleon.
 
Ohio 66 between T-O and T-N closure has been delayed and will now close September 19 for five days for a culvert replacement. Traffic detoured onto Ohio 66, U.S. 224, Ohio 637 and Ohio 114 back to Ohio 66. Work is being performed by the ODOT Putnam County maintenance garage.
 
Ohio 696 between Ohio 12 and the Allen County line will be restricted with traffic maintained for drainage repair. Work is being performed by the ODOT Putnam County maintenance garage.
 
Ohio 65 from Columbus Grove to Leipsic, excluding the village of Ottawa, and from the village of Leipsic to the village of Ottawa is occasionally restricted to one lane through the work zone for finish work relating to a resurfacing project. Work is being performed by Bluffton Paving, Bluffton.
 
Ohio 12 through the village of Columbus Grove is occasionally restricted to one lane through the work zone for finish work relating to a resurfacing project. Work is being performed by Bluffton Paving, Bluffton.
 
Van Wert County
 
U.S. 30 both eastbound and westbound between Middle Point and Delphos will be restricted to one lane through the work zone for berm repair work. Work is being performed by the ODOT Van Wert maintenance garage.
 
U.S. 127 (Washington Street) between Fox Road and Ervin Road in the city of Van Wert closed April 11 for reconstruction and widening of the road. Access to local businesses is maintained. Traffic is detoured onto Ohio 81, Ohio 118, Ervin Road/Van Wert-Decatur Road, U.S. 224 and U.S. 30 back to U.S. 127. The closure will remain in place until fall. Work is being performed by Helms & Sons Excavating, Findlay.
·       The U.S. 127 (Washington St.) and Ervin Road intersection has been reopened.
  • The U.S. 127 (Washington St.) and Fox Road/Ohio 116 intersection closed on September 7th for 40 days. Access to residences and businesses on Washington St. north of Fox Road is available from the north via Ervin Road.
 
Wyandot County
 
Ohio 103 between Ohio 231 and the Crawford County line will close September 19 for three days for a culvert replacement. Traffic detoured onto Ohio 67 and Ohio 100 back to Ohio 103. Work is being performed by the ODOT Wyandot County maintenance garage.
 
 
###
For more information contact:
Rhonda Pees, Public Information Officer, at (419) 999-6803
or email
D01.PIO@dot.state.oh.us
 
The Ohio Department of Transportation maintains the state's largest man-made asset--the transportation system. ODOT's mission is to provide the safe and easy movement of people and goods from place to place. As a $2.8 billion per year enterprise, ODOT invests the bulk of its resources in system preservation through maintenance, construction and snow and ice operations.
 
The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.