The following is the weekly report concerning construction and maintenance work on state highways within the Ohio Department of Transportation District 1 which includes the counties of Allen, Defiance, Hancock, Hardin, Paulding, Putnam, Van Wert and Wyandot. This report is issued each week beginning in April and continues through November.

 For the latest in statewide construction visit www.ohgo.com. Please contact us at 419-999-6803 with any information needs.

 

Construction and Maintenance Projects

Week of June 2, 2014

Allen County

Interstate 75 Reconstruction Project For the most recent information concerning the Interstate 75 reconstruction project through Lima and Allen County please visit www.odotlima75.org

U.S. 30/Ohio 309
near Delphos may be restricted to one lane at times through the work zone for culvert work. Work is expected to be completed mid June. Work is being performed by Platinum Painting, Boardman.

Defiance County

 

Ohio 18 in the city of Defiance just east of the Ohio 15 (Ottawa Avenue) and Ohio 18 (East Second Street) intersection will close June 9 for two months for culvert replacement. Traffic detoured onto Ohio 281 and U.S. 24 back to Ohio 15/18. Traffic may also detour to Ohio 15/18 to Ohio 66, U.S. 24, to Ohio 281 back to Ohio 18. Work is being performed by Sand Ridge Excavating, Cloverdale.

 

Ohio 2 from just north of Hicksville to just west of Farmer will be restricted to one lane through the work zone for pavement repair. Work is being performed by the Defiance County ODOT maintenance garage.

 

 Hancock County

 

U.S. 224 interchange at Interstate 75 reconstruction, Findlay

 

The U.S. 224 interchange with Interstate 75, Findlay, is currently being reconstructed. The project began in February and is expected to be completed late this fall. Work is being performed by Miller Brothers Construction, Archbold.

 

The following traffic impacts related to the reconstruction are in effect or will occur in the upcoming weeks:

 

Interstate 75

 

- Both the northbound and southbound lanes are narrowed and shifted approaching the U.S. 224 interchange.

 

-For two nights beginning the night of June 2 and continuing until early morning on June 4, generally between 11 p.m. and 6 a.m. each day, short-term stops of traffic on Interstate 75 will occur during setting of bridge beams on the U.S. 224 structure. Both northbound and southbound traffic will be affected on the first night. Only northbound traffic will be affected the second night. Law enforcement will slow traffic approaching the interchange and direct traffic onto the exit ramps at the U.S. 224 interchange. Traffic on the ramps will then be allowed to turn onto U.S. 224 or proceed onto the entrance ramp to re-enter I-75. Traffic at the ramp intersections with U.S. 224 will be controlled by law enforcement officers. Traffic on U.S. 224 will be allowed to cross the bridge over I-75 during this time as well. Traffic stops on I-75 are expected to last up to 20 minutes at which time traffic will be allowed to clear out before the next stoppage occurs. Following the beam setting lane restrictions will continue for the rest of the week both northbound and southbound for overhead work at the bridge. Restrictions will occur between 8 p.m. and 10 a.m.

 

U.S. 224

 

-Traffic on the bridge over Interstate 75, Findlay, is traveling on the north half of the bridge, one lane in each direction with no turn lanes. All ramps at the interchange are currently open.

 

-Motorists are cautioned to watch for construction vehicles entering and exiting at various locations throughout the work zone on U.S. 224 and along the interchange ramps.

 

--------------------------------------------------

 

Ohio 15 westbound between Western Avenue in Findlay and Ohio 37 will be restricted to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Hancock County ODOT maintenance garage.

 

U.S. 224 on the east side of Findlay between Plaza Road (Best Buy) and County Road 236 is occasionally restricted to one lane through the work zone during a traffic signal upgrade project. The new and upgraded signals are now in operation. Work on constructing curb ramps and pavement striping is expected to continue during the week. Work is being performed by Perram Electric, Wadsworth.

 

Ohio 568 between Blanchard Avenue in Findlay to County Road 180 will be restricted to one lane through the work zone for pavement repair and resurfacing. Work is being performed by Shelly Co., Findlay.

 

Ohio 330 from Ohio 15 to Vanlue High School will be restricted to one lane through the work zone for pavement repair and resurfacing. Pavement striping will continue during the week, weather permitting. Work is being performed by Shelly Co., Findlay.

 

Ohio 15 between U.S. 23 in Carey to Ohio 37 in Findlay is restricted to one lane through the work zone for resurfacing. Work is occurring in both the eastbound and westbound direction and during daytime hours. Work is being performed by Kokosing, Fredericksburg.

 

Hardin County

 

U.S. 68 between County Road 80 and County Road 90 will be restricted to one lane through the work zone for shoulder work. Work is being performed by the Hardin County ODOT maintenance garage.

 

Ohio 309 from Kenton to Marion will be reduced to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Hardin County ODOT maintenance garage.

 

U.S. 68 from the Kenton corporation limit to the Logan County line will be reduced to one lane through the work zone for pavement resurfacing. The project is expected to continue through June. Work is being performed by the Shelly Co., Findlay.

 

Ohio 235 from Ohio 309 to County Road 60 will be restricted to one lane through the work zone for shoulder work. Work is being performed by the Hardin County ODOT maintenance garage.

                                                                                                                                       

Paulding County

 

Ohio 637 just south of Ohio 613 east of Broughton will close June 9 for approximately five days for railroad crossing repair. Traffic detoured onto Ohio 114, U.S. 127 and Ohio 613 back to Ohio 637. Work is being performed by Roadsafe Traffic.

 

Ohio 114 and Ohio 637 in Grover Hill will be restricted at times through the work zone for pothole repair. Work is being performed by the Paulding County ODOT maintenance garage.

 

U.S. 127 south of Paulding will be restricted to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Paulding County ODOT maintenance garage.

 

Putnam County

 

Ohio 634 between Ft. Jennings and Continental will be reduced to one lane through the work zone for pavement resurfacing. The project will continue through June. Work is being performed by Gerken Paving, Napoleon.

 

Ohio 115 one mile south of Vaughnsville  closed May 27 for culvert replacement. The route is expected to reopen by the beginning of the week. Traffic detoured onto Ohio 65 and Ohio 12 back to Ohio 115. Work is being performed by the Putnam County ODOT maintenance garage.

 

Van Wert County

 

U.S. 127 north of Van Wert will be reduced to one lane through the work zone for sealing of pavement cracks. Work is being performed by the Van Wert County ODOT maintenance garage.

 

Wyandot County

 

There are no projects scheduled during the week which will have a significant impact on traffic.

 

 ###

 

For more information contact:
Rhonda Pees, Public Information Officer, at (419) 999-6803