​Buck Road Roundabouts
Buck Road roundabouts at Lime City Road and Penta Career Center
 
What is being done? 
 
Constructing two roundabouts along Buck Road. One at Lime City Road and one at Penta Career Center entrance.

 

Maintenance of traffic: 
The project began in March with drainage work with occasional flagged traffic when needed. 
 
May 21 at 7pm through mid-September, there will be restrictions on which direction(s) are open to traffic and which ones are detoured. Here is the estimated timeline, but all work is weather permitting:
  • May 21 at 7pm through July, Lime City Rd. will be open to southbound traffic only between Buck Rd. and Mandell Rd.
  • May 21 at 7pm through mid-August, Buck Rd. will be open to eastbound traffic only between Bates Rd. and Lime City Rd.
  • End of July through mid-September, Lime City Rd. will be closed north of Buck Rd.
  • August 17, the roundabouts will be operational except the northern leg (Lime City Rd. will be closed north of Buck Rd. through mid-September.)

The final project completion is October.

 

Typically for roundabouts to be constructed, we have to do a full closure of the intersection for at least a period of time. However, with some creative planning and construction phasing, we’ve managed to keep movements of the intersection open for the duration of the project. 
 
 
 
  
 