I-75 Downtown & DiSalle Bridge Projects
 
Reconstructing I-75 from Dorr Street to Glenwood Road in two, adjacent projects

 
Dorr Street to South Avenue:
4-year project beginning summer 2018
Approximately $158.6 million

 
South Avenue to Glenwood Road:
3-year project beginning spring 2019
Approximately $135 million
(Estimated timeline will be posted as the project start date approaches)
 
 
 
For information from the 2015 public meetings click:

DiSalle Bridge

 
 
 
 
 
 
 

 Want project updates emailed to you?

 
email_PNG55.png

 
To receive project-specific updates, send an email to d02.pio@dot.ohio.gov, with "I-75 Downtown/Disalle Bridge Project" in the subject header.
 

 Want other ODOT updates? Sign up here!

 
 

 For Latest Information

 
 

 Tentative timeline for Downtown Project

 
 
 
​​  When? ​           Work Summary ​Maintenance of Tra​ffic
​Summer 2018 - Spring 2019 ​- Installation of temporary pavements throughout I-75 corridor

 

- Mill and Fill portions of I-75 & Anthony Wayne Trail in preparation for maintenance of traffic lanes

- Storm sewer installation from Swan Creek heading north along SB I-75 right shoulder

- Dorr St. Bridge recon​struction


I-75: Various overnight lane closures as the contractor installs temporary pavement and mill/fill operations throughout the project in preparation for Stage 1 work

Ramp SB I-75 to outbound Trail: Closes summer for 14 days. Detour: Washington St/Downtown (exit 202A); Washington St; Michigan St​

Dorr Street over I-75:
Closes late summer 2018 for 300 days. Reopens fall 2019. Detour: Dorr St; Collingwood Blvd; Monroe St; 17th St

Weiler Ave: Closes late summer for 14 days. Seek alternate route

Spring 2019 - late Fall 2019 ​-Continuation of storm sewer installations

 

-Continuation of Dorr St. bridge reconstruction

-Reconstruction of NB I-75 from South Ave to Erie St

-Reconstruction of NB I-75 structures over Segar and RR/Emerald Ave/Broadway St

 

-Noise barriers along NB I-75  

 

-Reconstruction of NB I-75 ramp to Collingwood Ave (exit 201A)

-Reconstruction of Logan St

​​
I-75: 2 lanes in each direction. Northbound from South Ave to Erie St will be crossed into southbound lanes, separated by barrier

Broadway St under I-75: Reduced to one lane in each direction in spring 2019 through late summer 2020.

Collingwood Ave under I-75: Reduced to one lane in each direction in summer 2019 through late summer 2020.

Dorr St bridge: Remains closed. Reopens fall 2019. Detour: Dorr St; Collingwood Blvd; Monroe St; 17th St

Segar Ave under I-75: Closes Spring 2019 for 510 days. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St
Pedestrian access maintained

Emerald Ave under I-75: Closes Spring 2019 for 510 days. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St

Ramp northbound I-75 to Collingwood Ave (exit 201A): Closes Spring 2019 for 240 days. Reopens late fall 2019. Detour: SR 25 north/Downtown (Exit 201B); Erie St

Ramp South Ave to northbound I-75: Closes spring 2019 for 60 days. Reopens summer 2019. Detour: southbound I-75; Miami St (exit 199A); NB I-75

Logan St between Broadway St and Collingwood Ave: Closes fall 2019 for 45 days. Reopens fall 2019. Seek alternate route

St. Clair St at Logan St: Closes fall 2019 for 45 days. Reopens fall 2019. Seek alternate route

Erie St under I-75: Closes fall 2019 for 45 days. Reopens fall 2019. Detour: Harrison St; St. Clair St; Emerald Ave; Anthony Wayne Trail; Collingwood Ave; Erie St

​Late fall 2019- Summer 2020 -Continuation of storm sewer installations

​-Move I-75 traffic onto the newly completed NB lanes from South Ave to Erie St

 

-Reconstruction of SB I-75 from South Ave to Erie St

-Reconstruction of SB I-75 structures over Segar and RR/Emerald Ave/Broadway St

-Reconstruction of ramp Collingwood to SB I-75


​​I-75:
 2 lanes in each direction from South Ave to Erie St, separated by barrier.  All traffic switched onto newly constructed NB I-75 pavement. 

Broadway St under I-75: Remains reduced to one lane in each direction through late summer 2020

Collingwood Ave under I-75: Remains reduced to one lane in each direction through late summer 2020.

Ramp Collingwood to SB I-75: Closes late fall 2019 for 240 days. Reopens late summer 2020. Detour: Collingwood; Erie St; Washington St; Michigan St; SB I-75

Erie St at Sunrise ramp: Closes for 47 days during the above ramp closure. Detour: Harrison St; St. Clair St; Emerald Ave; Anthony Wayne Trail; Collingwood Ave; Erie St

Emerald Ave under I-75: ​Remains closed. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St

Segar Ave under I-75: Remains closed. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St
Pedestrian access maintained

 

Summer 2020- Spring 2021 -Recons​​truction of inside lanes of I-75 from Erie St to Dorr St

 

-Reconstruction of Nebraska Ave over I-75

-Reconstruction of outbound Anthony Wayne Trail at I-75

 


I-75: 2 lanes of traffic on the outside lanes from Erie St to Dorr St

Nebraska Ave over I-75: Closes fall 2020 for 780 days. Reopens fall 2022. Detour: Collingwood Blvd; Erie St

Anthony Wayne Trail at I-75: Lane restrictions for overhead I-75 bridge work.

Outbound Anthony Wayne Trail at I-75: Reduced to one lane beginning Spring 2021 for 45 days.

Ramp outbound Anthony Wayne Trail to SB I-75: Closes late summer 2020 for 690 days. Reopens summer 2022. Detour: Washington St; Superior St; St. Clair St; Logan St; Erie St; SB I-75

Ramp inbound Anthony Wayne Trail to NB I-75: Closes late summer 2020 for 690 days. Reopens summer 2022. Detour: Erie St; Washington St; NB I-75

Spring 2021- Spring 2022 ​-Reconstruction of outside lanes of I-75 from Erie St to Dorr St

-Continuation of work on Nebraska Ave Bridge

-Reconstruction of ramp SB I-75 to Washington St/Downtown (Exit 202A)

 

-Construction of I-75/Anthony Wayne Trail interchange.

 

-Reconstruction of Anthony Wayne Trail from I-75 to City Park


I-75:
2 lanes of traffic on the newly reconstructed inside lanes from Erie St to Dorr St

Ramp SB I-75 to Washington St/Downtown (Exit 202A): Reduced to one lane.

Ramp NB I-75 to SR 25 north/Downtown (Exit 201B): Closes spring 2021 for 420 days. Reopens Summer 2022. Detour: Collingwood Ave (exit 201A); Erie St

Ramp SB I-75 to outbound Anthony Wayne Trail: 60 day closure will be announced. Detour: Washington St/Downtown (Exit 202A); Washington St; Anthony Wayne Trail.

Outbound Anthony Wayne Trail: Between I-75 and City Park reduced to one lane for 60 days during the above ramp closure.

Ramp from Collingwood Blvd to outbound SR 25: Closes summer 2021 for 30 days during above closure for outbound Trail traffic.

​Spring 2022- Fall 2022
-Continuation of work on Nebraska Ave Bridge

 

-Continuation of construction of I-75/Anthony Wayne Trail interchange.

-Reconstruction of inbound Anthony Wayne Trail lanes between City Park and Lafayette St

-Continuation of reconstruction of outside NB I-75 lanes from Nebraska to Dorr St

-Continuation of reconstruction of ramp SB I-75 to Washington St/Downtown (Exit 202A)

-Final surface course of asphalt, pavement markings, RPMs and finish work

​I-75: 3 lanes southbound. 2 lanes northbound. Overnight lane closures for asphalt paving, pavement markings, RPMs, and finish work

Inbound 
Anthony Wayne Trail: Between City Park and Lafayette​ St closes spring 2022 for 90 days. Reopens summer 2022. Traffic maintained single lane, bi-directional in outbound lanes

Ramp 
inbound Anthony Wayne Trail to​ Collingwood Blvd: Closes spring 2022 for 90 days. Reopens Summer 2022.  Detour: Erie St

Indiana Avenue local traffic over I-75: Closed for local traffic one weekend in spring 2022. Detour: Collingwood Blvd; Dorr St; Washington St