I-75 Downtown & DiSalle Bridge Projects
 
Reconstructing I-75 from Dorr Street to Glenwood Road in two, adjacent projects

 
Dorr Street to South Avenue:
​5-year project beginning summer 2018​
Approximately $158.6 million

 
South Avenue to Glenwood Road:
5-year project beginning spring 2019
Approximately $135 million
(Estimated timeline will be posted as the project start date approaches)
 
 
 
For information from the 2015 public meetings click:

DiSalle Bridge

 
 
Maps of construction by year coming soon
 
 
 
 
 
 
 
 

 Want project updates emailed to you?

 
email_PNG55.png

 
To receive project-specific updates, send an email to d02.pio@dot.ohio.gov, with "I-75 Downtown/Disalle Bridge Project" in the subject header.
 

 Want other ODOT updates? Sign up here!

 
 

 For Latest Information

 
DiSalle portion bubble.jpg 
Tentative timeline for DiSalle Portion
subject to change as project progresses
 
​​  When? ​           Work Summary ​Maintenance of Tra​ffic
​Summer 2019 ​- Installation of temporary pavements throughout I-75 corridor
 
- Installation of temporary lighting and temporary traffic signals
 
- Installation of portable concrete barrier wall

I-75: Various overnight lane closures as the contractor installs temporary pavement and portable concrete barrier wall.

Miami Street Interchange: Short-term (weekend) closures of SB I-75 ramp to EB Miami St and EB Miami St ramp NB I-75 to install temporary pavement at these ramps 
 Late Summer 2019 - Spring 2020 ​-Reconstruction of NB I-75 from Buck Rd to Wales Rd
 
-Construction of new SB I-75 alignment from Wales Rd to Miami St
 
-Partial demolition of SB I-75 DiSalle Bridge
 
-Construction of new SB I-75 DiSalle Bridge
 
-Construction of SB I-75 from DiSalle Bridge to South Ave 
 
-Cul-de-sac construction at ends of Knower St, Morton St and Western Ave

​​
I-75: 2 lanes in each direction. Northbound from Buck Rd to Wales Rd will be crossed into southbound lanes, separated by barrier.

Ramp Buck Rd to northbound I-75: Closed for 210 Days. Reopens early Spring 2020. Detour: southbound I-75; SR 795 (exit 195A); northbound I-75.

Ramp northbound I-75 to Wales Rd (exit 198): Closed for 60 days. Detour: northbound I-75; Miami St (exit 199); southbound I-75.

Ramp South Ave to southbound I-75: Closed for 540 days. Reopens winter 2020. Detour: Broadway St; Western Ave; Anthony Wayne Trail; Collingwood Blvd; Erie St; Washington St; Michigan Ave; southbound I-75.  

Ramp southbound I-75 to South Ave (Exit 200): Closed for 60 days. Reopens fall 2019. Detour: Miami St (Exit 199A); northbound I-75.

 

2020​ ​-Continuation of construction of new SB I-75 alignment from Wales Rd to Miami St
 
-Continuation of construction of new SB I-75 DiSalle Bridge
 
-Continuation of construction of SB I-75 from DiSalle Bridge to South Ave 
 
 -Reconstruction of SB I-75 around Miami St interchange (Exit 199)
 
-Reconstruction of north side of Miami St under I-75
 
-Continuation of Cul-de-sac construction at ends of Knower St, Morton St and Western Ave

I-75: 2 lanes in each direction. 

Ramp southbound I-75 to westbound Miami St (Exit 199B): Closes fall 2020 for 60 days. Reopens late fall 2020. Detour: Modified Miami St ramp (exit 199A).

Ramp South Ave to southbound I-75: Remains closed for 540 days. Reopens winter 2020. Detour: Broadway St; Western Ave; Anthony Wayne Trail; Collingwood Blvd; Erie St; Washington St; Michigan Ave; southbound I-75.  

2021
-Complete construction of new SB I-75 DiSalle Bridge
 
-Reconstruction of SB I-75 from Wales Rd to Buck Rd
 
-Reconstruction of Wales Rd ramps
 
-Reconstruction of south side of Miami St under I-75
 

I-75: 2 lanes in each direction. SB I-75 traffic switched onto newly completed northbound I-75 lanes from Wales Rd to Buck Rd.

Ramp southbound I-75 to eastbound Miami St (Exit 199A): Closes Spring 2021 for 75 days. Reopens Summer 2021. Detour: Newly opened exit lane of DiSalle bridge to Miami St (exit 199).

Ramp southbound I-75 to Wales Rd (Exit 198): Closes summer 2021 for 90 days. Reopens fall 2021. Detour: Buck Rd (Exit 197); northbound I-75.
 
Ramp Wales Rd to southbound I-75: Closes summer 2021 for 90 days. Reopens fall 2021. Detour: northbound I-75 to Miami St (exit 199); Oregon Rd; Wales Rd.
 
Ramp Miami St to southbound I-75: Closes summer 2021 for 75 days. Reopens fall 2021. Detour: Miami St; Oregon Rd; Wales Rd; southbound I-75.
 
2022
-Reconstruction of NB I-75 from Wales Rd South Ave
 
-Removal of existing DiSalle Bridge
 
-Construction of new NB I-75 DiSalle Bridge
 
-Construction of NB I-75 entrance/exit ramps at Miami St
 
-Construction of South Ave interchange
 
-Construction of NB I-75 entrance ramp from Wales Rd
 

I-75: 2 lanes in each direction. All traffic switched onto newly constructed SB I-75 pavement and bridge from South Ave to Wales Rd.

Ramp Wales Rd to northbound I-75: Closes for one weekend in spring 2022. Detour: southbound I-75; Buck Rd (exit 197); northbound I-75.

Ramp northbound I-75 to Miami St (exit 199): Closes for one weekend in spring 2022. Detour: South Ave (exit 200); southbound I-75.

Ramp Miami St to northbound I-75: Closes for 720 days in spring 2022. Reopens summer 2024. Detour: Temporary ramp.

Ramp northbound I-75 to South Ave (exit 200): Closes for 60* days in spring 2022. Detour: Collingwood Blvd (exit 201A); southbound I-75.
 
Ramp South Ave to northbound I-75: Closes for 45 days in spring 2022. Reopens fall 2022. Detour: southbound I-75; Miami St (exit 199).
 
Eastern Ave: Closes for 60 days in spring 2022. Reopens fall 2022. Seek alternate route.
 
2023​
-Continuation of reconstruction of NB I-75 from Wales Rd South Ave
 
-Continuation of construction of new NB I-75 DiSalle Bridge
 
-Continuation of construction of NB I-75 exit ramp at Miami St
 
-Construction of South Avenue
 

I-75: 2 lanes in each direction. All traffic switched onto newly constructed SB I-75 pavement and bridge from South Ave to Wales Rd.

Ramp Miami St to northbound I-75: Remains closed. Reopens summer 2024. Detour: Temporary ramp.

Ramp northbound I-75 to Miami St (exit 199): Closes for summer 2023. 

South Ave under I-75: Closes for 60 days in spring 2023. Reopens summer 2023. Detour: southbound I-75 to Miami St (exit 199); northbound I-75. OR northbound I-75 to Collingwood Blvd (exit 201A); southbound I-75.

 

2024​

-Completion of final paving

-Removal of temporary traffic control items

-Completion of final pavement markings, signs, etc.

​I-75: All lanes reopen
​*or longer; currently under review
Downtown portion bubble.jpg
Tentative timeline for Downtown Portion
subject to change as project progresses​
 

​​  When? ​           Work Summary ​Maintenance of Tra​ffic
​Summer 2018 - Spring 2019 ​- Installation of temporary pavements throughout I-75 corridor

 

- Mill and Fill portions of I-75 & Anthony Wayne Trail in preparation for maintenance of traffic lanes

- Storm sewer installation from Swan Creek heading north along SB I-75 right shoulder

- Dorr St. Bridge recon​struction


I-75: Various overnight lane closures as the contractor installs temporary pavement and mill/fill operations throughout the project in preparation for Stage 1 work

Ramp SB I-75 to outbound Trail: Closes for 14 days. Detour: Washington St/Downtown (exit 202A); Washington St; Michigan St​

Dorr Street over I-75:
Closes January 2019 for 300 days. Reopens late fall 2019. Detour: Dorr St; Collingwood Blvd; Monroe St; 17th St

Weiler Ave: Closes for 14 days. Seek alternate route

Spring 2019 - late Fall 2019 ​-Continuation of storm sewer installations

 

-Continuation of Dorr St. bridge reconstruction

-Reconstruction of NB I-75 from South Ave to Erie St

-Reconstruction of NB I-75 structures over Segar and RR/Emerald Ave/Broadway St

 

-Noise barriers along NB I-75  

 

-Reconstruction of NB I-75 ramp to Collingwood Ave (exit 201A)

-Reconstruction of Logan St

​​
I-75: 2 lanes in each direction. Northbound from South Ave to Erie St will be crossed into southbound lanes, separated by barrier

Broadway St under I-75: Reduced to one lane in each direction in spring 2019 through late summer 2020.

Collingwood Ave under I-75: Reduced to one lane in each direction in summer 2019 through late summer 2020.

Dorr St bridge: Remains closed. Reopens late fall 2019. Detour: Dorr St; Collingwood Blvd; Monroe St; 17th St

Segar Ave under I-75: Closes Spring 2019 for 510 days. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St
Pedestrian access maintained

Emerald Ave under I-75: Closes Spring 2019 for 510 days. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St

Ramp northbound I-75 to Collingwood Ave (exit 201A): Closes Spring 2019 for 240 days. Reopens late fall 2019. Detour: SR 25 north/Downtown (Exit 201B); Erie St

Ramp South Ave to northbound I-75: Closes spring 2019 for 60 days. Reopens summer 2019. Detour: southbound I-75; Miami St (exit 199A); NB I-75

Logan St between Broadway St and Collingwood Ave: Closes fall 2019 for 45 days. Reopens fall 2019. Seek alternate route

St. Clair St at Logan St: Closes fall 2019 for 45 days. Reopens fall 2019. Seek alternate route

Erie St under I-75: Closes fall 2019 for 45 days. Reopens fall 2019. Detour: Harrison St; St. Clair St; Emerald Ave; Anthony Wayne Trail; Collingwood Ave; Erie St

​Late fall 2019- Summer 2020 -Continuation of storm sewer installations

​-Move I-75 traffic onto the newly completed NB lanes from South Ave to Erie St

 

-Reconstruction of SB I-75 from South Ave to Erie St

-Reconstruction of SB I-75 structures over Segar and RR/Emerald Ave/Broadway St

-Reconstruction of ramp Collingwood to SB I-75


​​I-75:
 2 lanes in each direction from South Ave to Erie St, separated by barrier.  All traffic switched onto newly constructed NB I-75 pavement. 

Broadway St under I-75: Remains reduced to one lane in each direction through late summer 2020

Collingwood Ave under I-75: Remains reduced to one lane in each direction through late summer 2020.

Ramp Collingwood to SB I-75: Closes late fall 2019 for 240 days. Reopens late summer 2020. Detour: Collingwood; Erie St; Washington St; Michigan St; SB I-75

Erie St at Sunrise ramp: Closes for 47 days during the above ramp closure. Detour: Harrison St; St. Clair St; Emerald Ave; Anthony Wayne Trail; Collingwood Ave; Erie St

Emerald Ave under I-75: ​Remains closed. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St

Segar Ave under I-75: Remains closed. Reopens late summer 2020. Detour: Bloomfield St; Eastern Ave; South Ave; Sumner St
Pedestrian access maintained

 

Summer 2020- Spring 2021 -Recons​​truction of inside lanes of I-75 from Erie St to Dorr St

 

-Reconstruction of Nebraska Ave over I-75

-Reconstruction of outbound Anthony Wayne Trail at I-75

 


I-75: 2 lanes of traffic on the outside lanes from Erie St to Dorr St

Nebraska Ave over I-75: Closes fall 2020 for 780 days. Reopens fall 2022. Detour: Collingwood Blvd; Erie St

Anthony Wayne Trail at I-75: Lane restrictions for overhead I-75 bridge work.

Outbound Anthony Wayne Trail at I-75: Reduced to one lane beginning Spring 2021 for 45 days.

Ramp outbound Anthony Wayne Trail to SB I-75: Closes late summer 2020 for 690 days. Reopens summer 2022. Detour: Washington St; Superior St; St. Clair St; Logan St; Erie St; SB I-75

Ramp inbound Anthony Wayne Trail to NB I-75: Closes late summer 2020 for 690 days. Reopens summer 2022. Detour: Erie St; Washington St; NB I-75

Spring 2021- Spring 2022 ​-Reconstruction of outside lanes of I-75 from Erie St to Dorr St

-Continuation of work on Nebraska Ave Bridge

-Reconstruction of ramp SB I-75 to Washington St/Downtown (Exit 202A)

 

-Construction of I-75/Anthony Wayne Trail interchange.

 

-Reconstruction of Anthony Wayne Trail from I-75 to City Park


I-75:
2 lanes of traffic on the newly reconstructed inside lanes from Erie St to Dorr St

Ramp SB I-75 to Washington St/Downtown (Exit 202A): Reduced to one lane.

Ramp NB I-75 to SR 25 north/Downtown (Exit 201B): Closes spring 2021 for 420 days. Reopens Summer 2022. Detour: Collingwood Ave (exit 201A); Erie St

Ramp SB I-75 to outbound Anthony Wayne Trail: 60 day closure will be announced. Detour: Washington St/Downtown (Exit 202A); Washington St; Anthony Wayne Trail.

Outbound Anthony Wayne Trail: Between I-75 and City Park reduced to one lane for 60 days during the above ramp closure.

Ramp from Collingwood Blvd to outbound SR 25: Closes summer 2021 for 30 days during above closure for outbound Trail traffic.

​Spring 2022- Fall 2023
-Continuation of work on Nebraska Ave Bridge

 

-Continuation of construction of I-75/Anthony Wayne Trail interchange.

-Reconstruction of inbound Anthony Wayne Trail lanes between City Park and Lafayette St

-Continuation of reconstruction of outside NB I-75 lanes from Nebraska to Dorr St

-Continuation of reconstruction of ramp SB I-75 to Washington St/Downtown (Exit 202A)

-Final surface course of asphalt, pavement markings, RPMs and finish work

​I-75: 3 lanes southbound. 2 lanes northbound. Overnight lane closures for asphalt paving, pavement markings, RPMs, and finish work

Inbound 
Anthony Wayne Trail: Between City Park and Lafayette​ St closes spring 2022 for 90 days. Reopens summer 2022. Traffic maintained single lane, bi-directional in outbound lanes

Ramp 
inbound Anthony Wayne Trail to​ Collingwood Blvd: Closes spring 2022 for 90 days. Reopens Summer 2022.  Detour: Erie St

Indiana Avenue local traffic over I-75: Closed for local traffic one weekend in spring 2022. Detour: Collingwood Blvd; Dorr St; Washington St