I-75 at Wooster St/SR 64 interchange project
 
Convert the two existing Wooster St/SR 64 signalized ramp intersections at I-75 to single lane roundabouts. 
Rehabilitate the existing bridge with new bridge deck. 
Construct a new multi-use path across I-75
Incorporate aesthetic features and lighting
 
August 2018-July 2019
Approximately $10 million


 
For information and graphics from the 2017 public meeting click:
 ​



 

 Want other ODOT updates? Sign up here!

 
 
​​  When? ​           Work Summary ​Maintenance of Tra​ffic
​Prephase
Aug 20-September 3
​- Removing brush

- Constructing temporary pedestrian path

- Removing concrete median

- Bridge falsework

- Begin Waterline & Sanitary work


I-75: Various overnight lane restrictions

Wooster St: Two 11' lanes westbound, one 11' lane eastbound​


Phase 1
September 4- Spring 2019 
- Constructing pedestrian/bike path from Alumni Dr. to Dunbridge Rd.

- Constructing north side of bridge

- Ramp work

- Continue waterline & sanitary work

- Installing temporary pavement to maintain traffic through winter
​​
I-75: Various overnight lane restrictions

​Wooster St: One 11' lane each direction

Ramps: 14-day closure of ramp from SB I-75 to Wooster St

​Phases 2-4
Spring 2019- July 2019
- Constructing south side of bridge

- Ramp work

- Constructing roundabouts

- Finishing bridge construction

- Finish work

​​I-75:
 Various overnight lane restrictions

Wooster St: Westbound Wooster St detoured using Poe while eastbound Wooster one 11' lane; 60-day closure of Wooster St to be announced

Ramps: Closure of ramp from Wooster St to NB I-75; Closure of ramp from NB I-75 to Wooster St

 

​*All work, dates and maintenance of traffic, subject to change