BOWLING GREEN (Wednesday, July 21, 2010)The Ohio Department of Transportation (ODOT) District Two announces the following update to the I-475 Salisbury/Dussel Project. Updates are highlighted in bold and underlined.

4. Interstate 475/Salisbury Road-Dussel Drive:  Interchange Reconstruction/Major Widening

Lucas County (104-09):  Interchange reconstruction of the bridge over I-475 and widening of Salisbury Road/Dussel Drive between Manley Road to Osage Drive. Throughout the project, nightly between 8pm and 6am, intermittent lane and shoulder restrictions on I-475 at the Salisbury Road/Dussel Drive bridge are possible. Through 2011, Salisbury Road/Dussel Drive, from Manley Road to Osage Drive, is reduced to one lane in each direction with turn lanes at intersections. Access to all businesses is maintained.

Beginning Thursday, July 29 at 6pm through Monday, August 2, the ramp from Salisbury Road and Dussel Drive to northbound I-475 will be closed.  Suggested alternate route:  Ford Street; Anthony Wayne Trail (US 24); northbound I-475 or Briarfield Boulevard; US 20A; Ford Street; Anthony Wayne Trail; northbound I-475.

Additionally, at this time, crews will shift lanes of traffic on Salisbury Road/ Dussel Drive, from Manley Road to Osage Drive, from the south side of road to the newly constructed north side.  One lane of traffic will be maintained in each direction with turn lanes at intersections.

Project complete:  November 2011. All work is weather permitting.