BG N. Main Street Widening Project
BOWLING GREEN (Friday, April 20, 2012) - The Ohio Department of Transportation (ODOT) District Two announces the following update to the BG N. Main Street widening project.  Updates are highlighted in bold and underlined. 
 
6. State Route 25: BG N. Main Street Widening Project
Wood County (136-11):
Through summer of 2012, N. Main Street (SR 25), between Dill Street and Newton Road, is reduced to one lane in both directions with a designated center left-turn lane, for utility work. Through summer of 2012, intermittent lane restrictions are possible in both directions of N. Main Street (SR 25) at Poe Road, for intersection work.  Access to all businesses will be maintained. 
 
Effective, Monday, April 30 through June 30, westbound Poe Road, from Prospect Street to Main Street will be closed.  Detour: North College Drive; Newton Road; Fairview Avenue. Eastbound traffic will be maintained. 
 
Project complete: August 2013. All work is weather permitting.