Interstate 475 Resurfacing Project
BOWLING GREEN (Wednesday, August 20, 2014) - The Ohio Department of Transportation (ODOT) District Two announces the following update to the I-475 resurfacing project.  Updates are highlighted in bold and underlined:
Interstate 475: Resurfacing Project
Lucas and Wood Counties (32-14):
 Effective tonight, through Friday morning, August 22, overnight from 7pm through 6am, intermittent short-term ramp closures are possible at the I-475/US 24 interchange for guardrail installation.  Detours will be posted. 
On Friday, August 22 at 7pm through Monday, August 25 at 6am, southbound I-475, between US 24 and SR 25, will be reduced to one lane for bridge work.
Through October, overnight from 7pm until 6am, lane restrictions are possible on I-475, from SR 25 to US 20A, for resurfacing.  Project complete: October.  All work is weather permitting.