BOWLING GREEN (Friday, August 17, 2012) - The Ohio Department of Transportation (ODOT) District Two announces the following update concerning construction on the Interstate 475/U.S. 23 Resurfacing & Bridge project. Updates are highlighted in bold and underlined.
Interstate 475/U.S. 23 Resurfacing & Bridge Work *UPDATE*
Lucas County (254-12):
  Through October, northbound US 23, between I-475 and Sylvania Avenue, will be reduced to one lane for bridge work. 
Through November, overnight 8pm until 6am, lane restrictions are possible in both directions of I-475/US 23, from Central Avenue to the Ohio/Michigan border for resurfacing. 
Through August, expect overnight, 8pm through 6am, lane restrictions on southbound I-475 at the Ohio Turnpike for bridge repair.  Beginning Tonight at 8:30pm until noon on Saturday, August 18, southbound I-475/US 23 will be reduced to one lane at the Ohio Turnpike for resurfacing. 
Project complete: November.  All work is weather permitting.