Interstate 475/U.S. 23: Resurfacing & Bridge Work *UPDATE*

BOWLING GREEN (Friday, September 21, 2012) - The Ohio Department of Transportation (ODOT) District Two announces the following update concerning the Interstate 475/U.S. 23 resurfacing & bridge project in Lucas County.  Updates are highlighted in bold and underlined.
 
Interstate 475/U.S. 23: Resurfacing & Bridge Work *UPDATE*
Lucas County (254-12):  Through October, northbound US 23, between I-475 and Sylvania Avenue, is reduced to one lane for bridge work. 
 
Beginning Sunday, September 23, at 9pm until Monday, September 24, at 6am, the ramp from westbound I-475 to northbound US 23 will be closed. Suggested alternate route: southbound I-475/US 23; Central Avenue (Exit 13); northbound US 23.
Through November, overnight 8pm until 6am, lane restrictions are possible in both directions of I-475/US 23, from Central Avenue to the Ohio/Michigan border for resurfacing. 
Work on I-475 at the Ohio Turnpike is complete. 
Project complete: November.  All work is weather permitting.