BOWLING GREEN (Thursday, March 21, 2013) - The Ohio Department of Transportation (ODOT) District Two announces the following update to the I-75/475 interchange upgrade project.  Updates are highlighted in bold and underlined.  
Interstate 75/475: Interchange Upgrade
Lucas County (281-10):
 Upgrade the I-75/I-475 interchange, widen I-475 from Rushland Avenue to I-75 and construct a new interchange at ProMedica Parkway.
INTERSTATE RESTRICTIONS
Through 2013, single lane restrictions are possible in both directions of I-475, between Monroe Street and I-75.  Additional lane restrictions are possible, overnight from 7pm to 6am, on I-475 in both directions from Rushland Avenue to I-75 and on I-75 in both directions from Detroit Avenue to Berdan Avenue.
Through March, overnight, 10pm-5am, intermittent lane restrictions and short-term (30 minute) traffic stops are possible for bridge work in the following locations:
-I-475 in both directions between Douglas Avenue and Auburn Avenue
-The ramp from northbound I-75 to westbound I-475
-Southbound I-75 from Willys Parkway to Detroit Avenue
On Friday, March 22, from noon until 3pm, Expect short-term, intermittent moving closures of the following ramps for striping:
The ramp from ProMedica Parkway/Upton Avenue to westbound I-475. 
The ramp from westbound I-475 to Douglas Road (Exit 18B).  
The ramp from Douglas Road to eastbound I-475. 
Suggested alternate route: Secor Road.  
Following ramp work, between 2pm and 4pm, intermittent lane restrictions are possible on I-475 from I-75 to Monroe Street for striping.   Motorists should be advised of moving work zones during this time  Traffic will be maintained by law enforcement.
RAMP RESTRICTIONS  
  • Through 2013, the ramp from Monroe Street to eastbound I-475 is closed. Detour: Secor Road; eastbound I-475.
  • Through 2013, the ramp from eastbound I-475 to Jeep Parkway is closed. Detour: northbound I-75; Berdan Avenue (Exit 205B); Jeep Parkway.
  • Through 2013, the ramp from North Cove Boulevard to westbound I-475 is closed. Detour: Central Avenue; Upton Avenue; westbound I-475.
CITY STREET TRAFFIC
·         Through 2013, Upton Avenue, between Georgia Avenue and Central Avenue and Central Avenue, between Upton Avenue and Jackman Road are reduced to one lane in each direction. 
·         Through 2013, Sherbrooke Road, between Groveland Road and Marlow Road, is closed. Detour: Monroe Street; Douglas Road; Berdan Avenue.
·         Through 2013, Giant Street, between Upton Avenue and Bigelow Street is closed. Suggested alternate route: Jackman Road.
Project complete: Fall 2013. All work is weather permitting.