Interstate 75/475 Interchange/Widening Project

BOWLING GREEN
(Monday, December 3, 2012) - The Ohio Department of Transportation (ODOT) District Two announces the following update concerning construction on the Interstate 75/475 interchange & widening project.  Updates are highlighted in bold and underlined.
 
Interstate 75/475: Interchange Upgrade
Lucas County (281-10):
 Upgrade the I-75/I-475 interchange, widen I-475 from Rushland Avenue to I-75 and construct a new interchange at ProMedica Parkway.
INTERSTATE RESTRICTIONS
Through 2013, single lane restrictions are possible in both directions of  I-475, between Monroe Street and I-75.  Additional lane restrictions are possible, overnight from 7pm to 6am, on I-475 in both directions from Rushland Avenue to I-75 and on I-75 in both directions from Detroit Avenue to Berdan Avenue.

RAMP RESTRICTIONS 
  • The ramp from ProMedica Parkway to eastbound I-475 is now open. 
  • Through 2013, the ramp from Monroe Street to eastbound I-475 is closed. Detour: Secor Road; eastbound I-475.The ramp from westbound I-475 to Jackman Road is permanently closed.
  • Through 2013, the ramp from eastbound I-475 to Jeep Parkway is closed. Detour: northbound I-75; Berdan Avenue (Exit 205B); Jeep Parkway.
  • Through 2013, the ramp from North Cove Boulevard to westbound I-475 is closed. Detour: Central Avenue; Upton Avenue; westbound I-475.
 
CITY STREET TRAFFIC
·         Through 2013, Upton Avenue, between Georgia Avenue and Central Avenue and Central Avenue, between Upton Avenue and Jackman Road are reduced to one lane in each direction. 
·         Through 2013, Sherbrooke Road, between Groveland Road and Marlow Road, is closed. Detour: Monroe Street; Douglas Road; Berdan Avenue.
·         Through 2013, Giant Street, between Upton Avenue and Bigelow Street, is closed. Suggested alternate route: Jackman Road.
Project complete: Fall 2013. All work is weather permitting.