ODOT Awards the Anthony Wayne Bridge Rehabilitation Project
BOWLING GREEN (Friday, April 12, 2013) –The Ohio Department of Transportation District Two today announced the award of the State Route 2 Anthony Wayne bridge rehabilitation project.
E.S. Wagner Company, of Oregon, Ohio has been awarded the contract to make improvements to the bridge including redecking, replacing the existing truss end spans, rehabilitation of the existing substructures, new street lighting, and rebuilding the sidewalks, railings and fence.
The project bid was $28,694,795.61 or .91% lower than the engineer’s estimate of $28,975,000
Full details on the work schedule, including the project’s 19 month closure of the Anthony Wayne bridge, will be announced in the near future.  The project’s completion date is late fall 2015. 