State Route 281 in Wood County Update

BOWLING GREEN
(Friday, July 13, 2012) - The Ohio Department of Transportation (ODOT) District Two announces the following update concerning construction on SR 281.  Updates are highlighted in bold and underlined.
 
State Route 281: Resurfacing and Bridge Work 
Wood County (189-12): Through August, SR 281, between Henry-Wood County Line Road and SR 235 will be reduced to one lane for resurfacing. Traffic will be maintained by flaggers.
 
Beginning Tuesday, July 17, through August, SR 281, between I-75 and Hoffman Road will be closed for bridge repair.  Detour: SR 199; US 6; SR 25.
Beginning Tuesday, July 17, through August, SR 281, between Albert Lane near Custar and Milton Road, will be closed for bridge work.  Detour: SR 235; SR 18; SR 65.  Project Complete: October. All work is weather permitting.