U.S. Route 6/State Route 101
Railroad Grade Separation Project
The project will construct a grade separation of U.S. Route 6/State Route 101 at the Norfolk Southern railroad tracks on a new roadway alignment. The project will involve the reconstruction of portions of Venice Road, Tiffin Avenue, Wilson Street, George Street, Superior Street, Huron Street, Ferndale Drive, and improvements to Harbor Boulevard.
Project Contractor: Mosser Construction
Project Cost: $8,154,128.72
Completion Date: July 2014
Current Project Closures:
- Superior Street - Closed permenantly for cul-de-sac construction at US Route 6
- George Street - Closed through the end of the project for drainage work and improvements