Ohio.gov State Agencies  |  Online Services
Skip Ribbon Commands
Skip to main content
Navigate Up
Sign In

​Lorain US 20 Major Rehabilitation

ODOT and the City of North Ridgeville, are working together on the major rehabilitation of US 20. The 2.32 mile project, that stretches from Stoney Ridge Road to Lear Nagle Road, will begin in 2018.

  • Roadway reconstruction and widening from 3 lanes to 5 lanes
  • Constructing a new 10ft shared-use path
  • New storm sewers and water lines 
  • New sidewalks with new curb and gutter throughout the project
  • Upgrading the traffic signals and signage along the corridor
  • Two bridge replacements: US 20 over French Creek and Root Road over French Creek
  • Adding detention basins for storm water control

The 2018 season will include work east of Jaycox Road with the exception of the structure on US 20 over French Creek. The Jaycox Road intersection, the shared-use path, and all side roads east of Jaycox Road, will be completed. 

The 2019 season will include work west of Jaycox Road. This will include the intersections of Stoney Ridge Road, State Route 83, and Root Road. Each of these intersections will have their own phasing due to the size and complexity of the intersections. 

All work on the east end of the project, with the exception of the structure over French Creek, will be completed before work begins on the west end.​ US 20 will have at least one lane of traffic maintained in each direction at all times. The current 35 mph speed limit will remain in effect during the project. Business access will be maintained throughout the project.


 

US 20.png
 
 
 

 Business Meeting Information

 

Cost: $26.8 Million

Contractor: Fechko

Start Construction: April 2018

End Construction: 2020

 

 Traffic Impacts

 

US Route 20

 
US 20, Center Ridge Rd. 
 
  • Work East of Jaycox. ***UPDATE***
    • Curb and gutter installation is anticipated to begin next week
    • The sub-contractor is anticipated to start working on street light foundations and installing the wiring conduit on the north side of Center Ridge Rd. the week of the 23rd.
  • Work West of Jaycox ***UPDATE***
    • Resume work on grading, proof-rolling, and 304 sub grade compaction
  • Root Rd. 
    • Root Rd. is open to SOUTHBOUND traffic ONLY
      • ​This is to accomodate the busses in the afternoon
    • Work will resume on the rest of the bridge
      • ​The current traffic configuration will remain till the bridge and asphalt is complete
***SPECIAL LOGISTICS MESSAGE***
Due to work at the SR 83 and Center Ridge Rd. intersection, ODOT and the City of North Ridgeville would like to ask those businesses that have deliveries using semi-tractor trailers to advise them of the construction adn if possible find an alternative route. We realize that at times it may be unavoidable. Our goal is to try and relieve the possible delays during peak hours. Traffic lanes have been shortened to 10 ft. lanes and semi-tractor trailers may find it difficult to make the turns. We appreciate anything you can do to help would be greatly appreciated. 
​​
​​Please use caution and patience while driving through the work zone. 

Expect minor delays and/or a change in traffic pattern including temporary closures at intersecting crossing streets and/or entrances from the work described.​  


PEDESTRIAN TRAFFIC
Since work has picked up, we have also notice the same goes for our pedestrian traffic as well. For anyone or if you know of anyone that utilizes the construction zone as walk way/bike path, FOR YOUR SAFETY AND FOR THE SAFTY OF THE WORKERS WE ASK THAT YOU PLEASE FIND AN ALTERNATIVE ROUTE! We understand that there are not many options, however, with dump trucks loading and unloading, coming in and out of the work zone, heavy equipment backing up and swinging their boom with limited visibility can make for a very dangerous area to be in and we do not want to see anyone get hurt. So we respectfully ask that you please find an alternative route. Everyone on the project thanks you. 

Expect minor delays throughout the day. Please be advised to use caution while traveling throughout the corridor as there will be trucks and equipment entering and exiting the work zones. To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing by the work zone.       
 
​SCHEDULE IS SUBJECT TO CHANGE AND WEATHER PERMITTING

 

 
​​

“The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.”​