The Ohio Department of Transportation (ODOT) District 3 is in the preliminary stages of designing a project to address the traffic concerns along State Route 18 between the City of Medina and Nettleton Road. The project will include widening SR 18 and improving the intersections with both Foote Road and River Styx Road as well as constructing a multi-use path.
 
Time Schedule
The tentative time schedule for construction is as follows:
Completion of Construction Plans: May 2017                                            
Right-of-Way Acquisition Complete: January 2018
Begin Construction: April 2019
End Construction: October 2020
 
“The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.”
 
 

 March 2016 Public Meeting Files

 
 

 2014 Public Meeting Files

 
  
  
collapse Matrices :  ‎(1)
MED-18-13.54 Public Meeting Handout 02-6-2014.pdfMED-18-13.54 Public Meeting Handout 02-6-2014
collapse Matrices : 01-SR 18 Mainline Alignment west of River Styx Rd ‎(2)
SR18 - Alt B.pdfSR18 - Alt B
SR18 - Recommended Alternative Pt 2 of 2.pdfSR18 - Recommended Alternative Pt 2 of 2
collapse Matrices : 02-SR 18 Mainline Alignment west of Foote Road ‎(2)
SR18 - Alt E.pdfSR18 - Alt E
SR18 - Recommended Alternative Pt 1 of 2.pdfSR18 - Recommended Alternative Pt 1 of 2
collapse Matrices : 03-SR 18 Multi-Use Path ‎(3)
SR18 - Alt C.pdfSR18 - Alt C
SR18 - Alt D.pdfSR18 - Alt D
SR18 - Recommended Alternative Pt 1 of 2 - M03.aspxSR18 - Recommended Alternative Pt 1 of 2 - M03
collapse Matrices : 04-SR 18 Intersection-W Hospital Drive-Woodland Drive ‎(2)
SR18 - Recommended Alternative Pt 1 of 2 - M04.aspxSR18 - Recommended Alternative Pt 1 of 2 - M04
W-E Hospital Dr - Roundabout.pdfW-E Hospital Dr - Roundabout
collapse Matrices : 05-SR 18 Intersection-E Hospital Drive-Glenshire Lane ‎(3)
SR18 - Alt F.pdfSR18 - Alt F
SR18 - Recommended Alternative Pt 1 of 2 - M05.aspxSR18 - Recommended Alternative Pt 1 of 2 - M05
W-E Hospital Dr - Roundabout - M05.aspxW-E Hospital Dr - Roundabout - M05
collapse Matrices : 06-SR 18 Intersection-Foote Road ‎(2)
Foote Rd - Recommended Alternative.pdfFoote Rd - Recommended Alternative
Foote Rd - Roundabout.pdfFoote Rd - Roundabout
collapse Matrices : 07-SR 18 Intersection-Summa Drive ‎(2)
SR18 - Recommended Alternative Pt 1 of 2 - M07.aspxSR18 - Recommended Alternative Pt 1 of 2 - M07
Summa Dr - Roundabaout.pdfSumma Dr - Roundabaout
collapse Matrices : 08-SR 18 Intersection-Village Gate Drive-Octagon Drive ‎(2)
Octagon Dr - Roundabout.pdfOctagon Dr - Roundabout
SR18 - Recommended Alternative Pt 2 of 2 - M08.aspxSR18 - Recommended Alternative Pt 2 of 2 - M08
collapse Matrices : 09-SR 18 Intersection-River Styx Road-Shady Brook Lane ‎(4)
River Styx Rd - Roundabout.pdfRiver Styx Rd - Roundabout
SR18 - Alt M.pdfSR18 - Alt M
SR18 - Alt N.pdfSR18 - Alt N
SR18 - Recommended Alternative Pt 2 of 2 - M09.aspxSR18 - Recommended Alternative Pt 2 of 2 - M09
collapse Matrices : 10-SR 18 Intersection-Rustic Hills Drive ‎(2)
SR18 - Alt H-I.pdfSR18 - Alt H-I
SR18 - Recommended Alternative Pt 2 of 2 - M10.aspxSR18 - Recommended Alternative Pt 2 of 2 - M10
collapse Matrices : 11-River Styx Road between Octagon Drive and Smith Road ‎(2)
River Styx Rd - Alt L.pdfRiver Styx Rd - Alt L
River Styx Rd - Recommended Alternative.pdfRiver Styx Rd - Recommended Alternative