​​This is a $9.7 million project to make repairs to 12 bridges along I-680 between SR 711 to just south of US 224. It is scheduled to be completed by July 2021.
 

 I-680 Northbound Closure

 
Begining Monday, July 9, I-680 northbound between US 62/SR 7 to Edwards St. will be closed through early August. The detour is US 62 to US 422 to SR 193.
 

 Mahoning Avenue Entrance Ramp Closure

 
Mahoning Ave. entrance ramp to I-680 southbound will be closed for 60 days in September/October 2018.
 

 SR 711 Southbound Closures

 
I680 SR711 Southbound Closure
SR 711 southbound to I-680 southbound will have 4 and 1/2 month closures one between April and September 2019 and another between April and September 2020.
 

 I-680 Southbound to South Ave Closure

 
I-680 South Avenue Closure 
I-680 southbound to South Ave. will be closed for 14 days in September/October 2018.
 

 Bella Vista Avenue Closure

 
Bella Vista Ave. entrance ramp to I-680 northbound will be closed for 45 days in July/August 2019.