​2018
Work will begin in mid-March 2018 on a $11.6 million project to construct a new interchange at I-680 and SR 164.The project also includes the addition of a southbound lane on SR 164 between I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion of the SR 626 north junction to a single lane roundabout and the widening and replacement of the SR 164 bridge over I-76/Ohio Turnpike. The entire project is scheduled to be completed in November 2019.

March 2018

  •  I-680 under SR 164 will be reduced to one lane in each direction for roadway widening and drainage improvements. Work will begin on the new interchange.
  • Construction of temporary pavement on SR 164 between I-680 and just south of the SR 164 bridge over the Ohio Turnpike. During this time, SR 164 will be reduced to one lane maintained by flaggers.

Mid-April 2018

  • SR 164 will be shifted, one lane of traffic
    maintained in each direction between I-680 and just south of the SR 164 bridge over the Ohio Turnpike through late October 2019.
  • Work will begin on the SR 164 and SR 626
    roundabout and continue through October 2018.
  • The Ohio Turnpike will have various daily lane restrictions through late October 2018.

Mid- August 2018

  • SR 626 north of SR 164 will be closed for 30 days for roundabout construction. The detour will be SR 164 to SR 7 to US 224 to I-680.

Early October 2018

  • Seven day closure of the south leg of SR 626/164 interchange. The detour will be SR 626 to SR 165 to SR 164. 
 

 Map of 2018 Project Scope

 
2018-I-680andSR164.png
 
 