US 224/Raccoon Rd. Widening and Bridge
Replacement in Canfield Township

​The Ohio Department of Transportation is starting a $6.5 million project to replace and widen the US 224 bridge over SR 11 and widen Raccoon Rd. at US 224. The project also includes the widening of the SR 11 southbound ramp to US 224.

Beginning in late March, US 224 over SR 11 will be reduced to one lane in each direction while the contractor begins to replace and widen the structure. Shortly afterwards in April, work will begin at US 224 and Raccoon Rd. An additional right turn lane will be added to all legs of this intersection. Also, an additional right turn lane will be added on US 224 westbound between Raccoon Rd. and SR 11. This lane will serve as an exclusive exit lane from US 224 westbound to SR 11 northbound. The project also includes the widening of the SR 11 southbound ramp to US 224 to add a dedicated right turn lane. The entire project is scheduled to be completed by late October 2015. The contractor for this project is A.P. O’Horo Company from Youngstown.

All work at Raccoon Rd. is scheduled to be completed by late August 2015, meaning traffic will be able to flow uninterrupted to the Canfield Fair in early September via Raccoon Rd. and Fairgrounds Blvd.

Please use the map below to view restrictions and closures along this corridor.

 

 Map

 
 

 Restrictions & Closures

 
  1. ​(Mid-March) The ramp from US 224 westbound to SR 11 northbound will be closed for two nights for drainage repairs between the hours of 10 p.m. and 5 a.m. The detour will be US 224 west to SR 46 north to Mahoning Ave.
  2. (March - October) US 224 over SR 11 will be reduced to one lane in each direction.
  3. (April - June) Beginning in early April, Raccoon Rd. north of US 224 will have various daily lane restrictions for widening.
  4. (April - August) The ramp from SR 11 southbound to US 224 will one lane reduced while it is widened.
  5. (July - August) Beginning in July, Raccoon Rd. just south of US 224 will be closed for 30 days during road widening. The detour will be US 224 east to Tippecanoe Rd. to Leffingwell Rd.
 

 Rendering of Completed US 224 and Raccoon Rd. Intersection

 
US224andSR11CompletedRendering.jpeg
Click to enlarge 
 
The rendering above shows what the US 224 and Raccoon Rd. intersection will look like when completed.
 
Both the northern and southern legs of Raccoon Rd. at US 224 will include a dedicated left turn lane, through lane and right turn lane to improve traffic flow at US 224.
 
As part of the project, a right lane dedicated to the SR 11 northbound entrance ramp will be added on US 224 westbound.
 
 

 How To Stay Connected !!

 
 

 Sign Up!

 
​ ​For project updates you can also:
follow us on Facebook at ODOTD4
ODOT District 4 on Facebook
check out our Twitter feed at ODOT_Akron
ODOT District 4 on Twitter
  
 
For more information or if you have any additional questions,
please contact the ODOT District 4 Public Information Office at (330) 786-2209,