Stark County Projects
Interstate 77/State Route 687 Project
​in the city of Canton and Plain Township
 

Work is scheduled to begin in late March on a $3.7 million project to widen and resurface the northbound and southbound ramps at I-77 and SR 687/Fulton Rd./US 62 interchange. The project also includes median wall construction and various

other work to the ramps at the interchange, the construction of a cul de sac on Blake Ave. NW and the resurfacing of SR 687 between Blake Ave. and the I-77 entrance ramp. The entire project will be completed in Late October 2018. 

 

 I-77 Project Map

 
 

 Sign Up!

 
March 26 (Weather Permitting)
  • I-77 south to SR 687/ Fulton Rd. ramp will have various lane restrictions for drainage and pavement work.
  • SR 687/Fulton Rd. between Broad Ave. NW and Harrison Ave. NW will have various nightly lane restrictions.
April 2 (Weather Permitting)
  • The ramp from I-77 south to SR 687/Fulton Rd. will be closed through late July for roadway widening. The detour will be I-77 south to 13th St. to I-77 north to SR 687/Fulton Rd.
  • The ramp from US 62 west to I-77 south will be closed through late June. The detour will be US 62 west to SR 687/Fulton Rd. east to I-77 south.
  • Traffic on SR 687/Fulton Rd. between Broad Ave. NW and Harrison Ave. NW will be shifted into a new traffic pattern through late July for roadway widening. Two lanes of traffic will be maintained. July 25, through August 5, no closures or lane restrictions.
August 7
  • The ramp from I-77 north to SR 687/Fulton​Rd. will have various lane restrictions through for pavement work through late August.
  • SR 687/Fulton Rd. between SR 687/Fulton Rd. between Broad Ave. NW and Harrison Ave. NW will have various nightly lane restrictions between 9 p.m. ​and 5 a.m. through late August.
Late September
The following ramps will have various restrictions
and ramp closures for the placement of the surface
course of asphalt. Visit Ohgo.com/Stark to see
specific closure times.
  • SR 687/Fulton Rd. between Clear View Ave.
  • The ramp from I-77 north to SR 687/Fulton Rd.
  • The ramp from I-77 south to SR 687/Fulton Rd.
  • The ramp from US 62 west to I-77 south​
 