Ohio.gov State Agencies  |  Online Services
Skip Ribbon Commands
Skip to main content
Navigate Up
Sign In


The US 33 Carroll Interchange Project


Carroll Graphic.jpg


The Carroll Interchange project will eliminate the intersection at Winchester Rd. and US 33, replacing it with a new interchange with ramps and connector roads. The project will include three new signaled intersections, four new bridge structures, new lighting and retaining walls.  The much needed change will alleviate congestion and allow for a better flow of traffic to the area. ​ 


Carroll aerial photo 2.JPG



Project Details:
Shelly and Sands is the primary contractor for the project.
Total Project Cost: $49,900,000
Construction Cost:$33,500,000
US 33 will be opened to traffic with two lanes in each direction with minimal lane closures
Project estimated completion date is May, 31, 2017.​ ​​​​​​​​​

 

 Images

 
 

 Project Updates

 
Winter 2017
Currently, the interchange has been opened to traffic since November 15, 2016. The contractor is currently placing right of way fence, median light poles and tower lighting. Remaining work on the project includes constructing a cul-de-sac at Lockville Road and Pleasantville road, mill and fill asphalt on US 33, place final pavement marking, place remaining signs, barrier wall and guardrail. The revised completion date is currently June 13, 2017.​

Spring 2015
Crews have begun brush clearning and tree removal operations to prepare for construction which will begin in the upcoming months.
 
Winter 2014
With project funding approved by TRAC and the necessary environmental studies conducted, the Department of Transportation has begun the detailed design phase and right-of-way acquisition process, scheduled to last through the summer of 2014. On February 20, ODOT's project engineering team met with residents and business owners of the immediate vicinity of the interchange to discuss how traffic will be affected throughout construction and to address further concerns. Construction is presently scheduled to begin in the spring of 2015 and to be complete by the fall of 2016.


Summer 2013
In order to present and to receive public comments on the alternatives considered and the ODOT preferred alternative, a public meeting was held on April 30, 2013. Comments pertaining to the project were received during and after the public meeting. A summary of those comments and responses are provided below. Based on input received during the comment period, the Department decided to look closely at the impacts that would occur to the local business and roadway network if the access point to US 33 at Carroll Southern was removed.  As a result it was determined that the access point should be retained by way of a connector road between Winchester Road and Carroll Southern Road. A revised schematic plan of the ODOT Preferred Alternative (Alternative 3) has been provided below. The links that are provided below also include the revised intersection focus areas and the revised project evaluation matrix.
 
 
Revised ODOT Preferred Alternative (Alternative 3)
 
Revised Intersection Focus Areas
 
Revised Project Evaluation Matrix
 
 
 

 Resources

 
 

 Public Information

 
A public meeting was held on April 30, 2013 at the Fairfield Career Center, 3985 Coonpath Road, Carroll, Ohio.  The written comment period was concluded on May 14, 2013.  Public meeting information will be available on this website for your use and comment.
 

 Questions or Comments?

 
Contact:
Morgan Overbey, Public Information Officer
morgan.overbey@dot.ohio.gov
ODOT District 5
9600 Jacksontown Road SE
Jacksontown, Ohio 43030