US Route 33 Corridor Project

US 33 Corridor Map

In November 2001, a comprehensive U.S. 33 Access Management Study was initiated to identify feasible and prudent alternatives to eliminate the existing at-grade intersections along this corridor.  Various stakeholders of the community participated in this study to help ODOT develop proposed projects that were presented for public review and comment.  As a result of numerous meetings with the stakeholders along with the public involvement process, five projects were identified that would eliminate the intersecting roadways along U.S. 33:

  • Ebright Road overpass
    (open to traffic 2007)

  • Bixby Road interchange
    (under development earliest possible construction 2012)

  • Winchester Road “Carroll-area” interchange
    (under development but not scheduled for construction)

  • High Street/Bowen Road overpass
    (not scheduled)

  • Pickerington Road interchange
    (not scheduled)

When all of the proposed projects are complete, at an estimated total of $145 million, this 12-mile stretch of roadway will be a limited-access highway with interchanges and overpasses instead of intersections.  ODOT will partner with local officials to apply for right-of-way and construction funding for these projects.

Bixby Road Project

Carrol Interchange